A project is being initiated for a new regulatory compliance system. The Executive has delegated day-to-day decision-making to the project manager within defined tolerances. During a project board meeting, a Senior User requests a change that would increase costs beyond stage tolerance but would deliver an additional mandatory compliance benefit. Who should decide how to proceed?
In PRINCE2, the project board sets tolerances for the project manager. When an issue or change is forecast to exceed those tolerances, it must be escalated to the project board for a decision. The board can then approve, reject, or defer the change, and may also adjust tolerances. This preserves management by exception and keeps accountability at the right level.
Why this answer
The project manager works within the tolerances set by the project board. A change that would breach stage cost tolerance must be escalated as an exception. The project board is the body with the authority to approve, reject, or defer such a change, and to revise tolerances if appropriate.
This maintains management by exception and proper accountability.
Exam trap
The trap here is assuming that a mandatory benefit or the Executive's ownership of the Business Case allows a decision to be made outside the project board's tolerance-setting authority.