PRINCE2F People: organizations, teams, and leadership Practice Question
Which TWO of the following are responsibilities of the Project Board?
Answer choices
Why each option matters
Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.
Correct answer & explanation
✓
Approving the Stage Plan for the next stage
The Project Board is responsible for approving Stage Plans for the next stage (Option A) and authorizing deviations from stage tolerances (Option E). Option B (Preparing the Highlight Report) is the Project Manager's responsibility. Option C (Maintaining the Business Case) is primarily the Senior User's role, with the Project Manager supporting. Option D (Managing the delivery of Work Packages) is the Team Manager's responsibility. Thus, only A and E are correct.
Answer analysis
Option-by-option breakdown
For each option: why learners choose it and why it is or isn't the right answer here.
- ✓
Approving the Stage Plan for the next stage
Why this is correct
The Board approves Stage Plans.
- ✗
Preparing the Highlight Report
Why it's wrong here
The Project Manager prepares the Highlight Report.
- ✗
Maintaining the Business Case
Why it's wrong here
The Project Manager maintains it; the SRO is accountable.
- ✗
Managing the delivery of Work Packages
Why it's wrong here
That is the Team Manager's responsibility.
- ✓
Authorizing deviations from stage tolerances
Why this is correct
The Board authorizes any tolerance deviations.
Go deeper
Related to this question
About these practice questions
Courseiva writes every PRINCE2F question from scratch — 1,599 in total, each with an explanation and a wrong-answer breakdown. None are copied from real exams or dumps. Learn why practice questions differ from exam dumps →
Same concept, more angles
6 more ways this is tested on PRINCE2F
These questions test the same concept from different angles. Work through them to make sure you can recognise it however the exam phrases it.
Variation 1. Which THREE of the following are responsibilities of the Project Board in PRINCE2?
hard- ✓ A.Authorizing the start of each stage
- ✓ B.Approving the Stage Plans
- C.Authorizing work packages
- ✓ D.Providing overall direction and guidance
- E.Day-to-day management of the project
Why A: The Project Board is responsible for authorizing the start of each stage, including the initiation stage and subsequent management stages. This ensures that the project proceeds only when the board has reviewed and approved the Stage Plan for that stage, providing governance and control over the project's progression.
Variation 2. Which THREE of the following are responsibilities of the Project Board?
medium- A.Manage day-to-day activities
- ✓ B.Provide overall direction and control
- C.Produce Checkpoint Reports
- ✓ D.Authorize deviations from tolerances
- ✓ E.Approve Stage Plans
Why B: The Project Board is responsible for overall direction and control of the project, including authorizing deviations from tolerances and approving Stage Plans. These duties ensure the project remains aligned with business objectives and governance requirements.
Variation 3. Which TWO of the following are responsibilities of the Project Board?
medium- A.Specify the user requirements
- ✓ B.Authorize the Project Plan
- ✓ C.Authorize Stage Plans
- D.Maintain the Business Case
- E.Produce the Project Plan
Why B: The Project Board is collectively responsible for overall project governance. Its key responsibilities include authorizing the Project Plan (option B) and authorizing Stage Plans (option C) to ensure the project remains aligned with business objectives. Option A (Specify the user requirements) is the responsibility of the Senior User, not the Board. Option D (Maintain the Business Case) is primarily the Executive's role, though the Board approves the Business Case. Option E (Produce the Project Plan) is the Project Manager's responsibility. Therefore, the correct answers are B and C.
Variation 4. Which TWO of the following are responsibilities of the Project Board?
medium- ✓ A.Authorize expenditure beyond delegated authority
- ✓ B.Approve the Stage Plans
- C.Manage the day-to-day activities of the team
- D.Produce the Project Plan
- E.Update the Business Case
Why A: The Project Board is responsible for overall project governance, including authorizing expenditure beyond the delegated authority of the Project Manager. This ensures that financial control remains at the senior management level, preventing unauthorized spending that could jeopardize the project's budget.
Variation 5. Which TWO of the following are responsibilities of the Project Board?
medium- A.Write Work Packages
- B.Perform Project Assurance
- C.Manage the project on a day-to-day basis
- ✓ D.Provide resources and authorize funds
- ✓ E.Authorize stage plans and major deviations
Why D: The Project Board is responsible for providing resources and authorizing funds for the project. This is a key duty of the board, as they own the business case and must ensure the project remains viable by approving the necessary budget and resource allocation.
Variation 6. Which THREE of the following are responsibilities of the Project Board?
hard- ✓ A.Defining project tolerances
- B.Preparing the Highlight Report
- ✓ C.Authorizing the start of each management stage
- ✓ D.Approving the Project Plan
- E.Managing the team's day-to-day activities
Why A: The Project Board is responsible for strategic decisions: approving plans, defining tolerances, and authorizing stage boundaries. Day-to-day management is the PM's role.
JA
Written by Johnson Ajibi, MSc IT Security
Senior Network & Security Engineer · founder of Courseiva
This PRINCE2F practice question is part of Courseiva's free PeopleCert certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PRINCE2F exam.