Courseiva
PRINCE2 PracticesmediumMultiple ChoiceObjective-mapped

PRINCE2F PRINCE2 Practices Practice Question

What is the difference between a Highlight Report and a Checkpoint Report?

⚠ Common exam trap

Many exam-takers confuse the reporting direction and audience, as candidates often mix up which report goes to the Project Board versus the Project Manager, leading to a reversal of the correct roles.

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

Highlight Report is from Project Manager to Project Board; Checkpoint Report is from Team Manager to Project Manager

In PRINCE2, the Highlight Report is a formal report from the Project Manager to the Project Board, summarizing progress, risks, and issues at a stage level. The Checkpoint Report is a detailed report from the Team Manager to the Project Manager, covering work package progress at a team level. This distinction ensures the right level of detail reaches the appropriate management layer.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • Highlight Report is from Project Manager to Project Board; Checkpoint Report is from Team Manager to Project Manager

    Why this is correct

    Correct.

  • Highlight Report is from Team Manager to Project Manager; Checkpoint Report is from Project Manager to Project Board

    Why it's wrong here

    Reversed.

  • Both are from Project Manager to Project Board

    Why it's wrong here

    Incorrect.

  • Both are from Team Manager to Project Manager

    Why it's wrong here

    Incorrect.

About these practice questions

Courseiva writes every PRINCE2F question from scratch — 1,599 in total, each with an explanation and a wrong-answer breakdown. None are copied from real exams or dumps. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

Same concept, more angles

6 more ways this is tested on PRINCE2F

These questions test the same concept from different angles. Work through them to make sure you can recognise it however the exam phrases it.

Variation 1. What is the primary difference between a Highlight Report and a Checkpoint Report?

hard
  • A.A Highlight Report is sent to the Project Board; a Checkpoint Report is sent to the Project Manager
  • B.A Highlight Report is produced weekly; a Checkpoint Report is produced daily
  • C.A Highlight Report covers the entire project; a Checkpoint Report covers a stage
  • D.There is no difference; they are the same report with different names

Why A: Highlight Reports are from PM to Project Board; Checkpoint Reports are from Team Manager to PM.

Variation 2. In PRINCE2, what is the difference between a Highlight Report and a Checkpoint Report?

medium
  • A.Highlight Report covers the entire project; Checkpoint Report covers only a stage
  • B.Highlight Report is sent by the Team Manager; Checkpoint Report is sent by the Project Manager
  • C.There is no difference; they are the same document
  • D.Highlight Report is sent to the Project Board; Checkpoint Report is sent to the Project Manager

Why D: A Highlight Report is sent from the Project Manager to the Project Board regularly, while a Checkpoint Report is sent from the Team Manager to the Project Manager more frequently.

Variation 3. What is the difference between a Checkpoint Report and a Highlight Report?

easy
  • A.Checkpoint Reports are from Team Manager to Project Manager; Highlight Reports are from Project Manager to Project Board
  • B.Checkpoint Reports are produced by the Project Manager; Highlight Reports by the Team Manager
  • C.Checkpoint Reports are only produced at stage boundaries; Highlight Reports are produced weekly
  • D.Checkpoint Reports are sent to the Project Board; Highlight Reports are sent to the Project Manager

Why A: Checkpoint Reports are from Team Managers to the Project Manager, while Highlight Reports are from the Project Manager to the Project Board.

Variation 4. What is the difference between a Highlight Report and a Checkpoint Report?

hard
  • A.Highlight Reports are for the Project Board; Checkpoint Reports are for the Project Manager
  • B.They are the same but with different names
  • C.Highlight Reports are written by the team; Checkpoint Reports are written by the PM
  • D.Highlight Reports are for stakeholders; Checkpoint Reports are for the Project Board

Why A: Highlight Reports are from PM to Project Board; Checkpoint Reports are from Team Manager to PM.

Variation 5. What is the difference between a Highlight Report and a Checkpoint Report?

hard
  • A.Highlight Reports are produced by the Project Manager; Checkpoint Reports are produced by the Team Manager
  • B.Highlight Reports are for the Project Board; Checkpoint Reports are for the Project Manager
  • C.Highlight Reports are produced weekly; Checkpoint Reports are produced daily
  • D.There is no difference; they are the same document

Why A: Highlight Reports are from Project Manager to Project Board and cover the whole stage. Checkpoint Reports are from Team Manager to Project Manager and cover a team's work.

Variation 6. What is the difference between a Highlight Report and a Checkpoint Report?

medium
  • A.The Highlight Report is used to escalate exceptions, while the Checkpoint Report is for routine communication
  • B.The Highlight Report is produced only at stage boundaries, while the Checkpoint Report is produced weekly
  • C.The Highlight Report is from the Project Manager to the Project Board, while the Checkpoint Report is from the Team Manager to the Project Manager
  • D.The Highlight Report focuses on risks and issues, while the Checkpoint Report focuses on product quality

Why C: In PRINCE2, the Highlight Report is produced by the Project Manager and sent to the Project Board to provide a summary of stage progress, while the Checkpoint Report is produced by the Team Manager and sent to the Project Manager to report on work package progress. Option A is wrong because the Exception Report (not Highlight Report) is used to escalate exceptions. Option B is wrong because the Highlight Report is typically produced at regular intervals during a stage (e.g., weekly), not only at stage boundaries. Option D is wrong because both reports cover progress, risks, and issues; the focus difference is on audience and level of detail.

JA

Written by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

This PRINCE2F practice question is part of Courseiva's free PeopleCert certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PRINCE2F exam.