PRINCE2 Practices →mediumMultiple Choice

PRINCE2F PRINCE2 Practices Practice Question

What is the difference between a Highlight Report and a Checkpoint Report?

⚠ Common exam trap

Many exam-takers confuse the reporting direction and audience, as candidates often mix up which report goes to the Project Board versus the Project Manager, leading to a reversal of the correct roles.

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

✓

Highlight Report is from Project Manager to Project Board; Checkpoint Report is from Team Manager to Project Manager

In PRINCE2, the Highlight Report is a formal report from the Project Manager to the Project Board, summarizing progress, risks, and issues at a stage level. The Checkpoint Report is a detailed report from the Team Manager to the Project Manager, covering work package progress at a team level. This distinction ensures the right level of detail reaches the appropriate management layer.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • ✓

    Highlight Report is from Project Manager to Project Board; Checkpoint Report is from Team Manager to Project Manager

    Why this is correct

    Reports flow along distinct accountability lines: the Highlight Report gives the Project Board progress against the Stage Plan at agreed intervals, while the Checkpoint Report gives the Project Manager progress against the Work Package at frequencies set in that Work Package.

  • ✗

    Highlight Report is from Team Manager to Project Manager; Checkpoint Report is from Project Manager to Project Board

    Why it's wrong here

    The directions are reversed: the Highlight Report goes from Project Manager to Project Board, and the Checkpoint Report from Team Manager to Project Manager. The option is tempting because it names all four roles correctly, but it would be right only if the two reports' senders and recipients were swapped as stated.

  • ✗

    Both are from Project Manager to Project Board

    Why it's wrong here

    Highlight Reports travel from the Project Manager to the Project Board, while Checkpoint Reports travel from the Team Manager to the Project Manager, so the two do not share a single sender-recipient pair. The option is tempting because both are progress reports, but it would be correct only if both flowed along the same management line.

  • ✗

    Both are from Team Manager to Project Manager

    Why it's wrong here

    Only the Checkpoint Report runs from Team Manager to Project Manager; the Highlight Report runs from Project Manager to Project Board. The option is tempting because the Checkpoint Report's route is correct, but it would be right only if the Highlight Report also terminated at the Project Manager rather than the Board.

About these practice questions

Courseiva writes every PRINCE2F question from scratch — 1,189 in total, each with an explanation and a wrong-answer breakdown. None are copied from real exams or dumps. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

Same concept, more angles

6 more ways this is tested on PRINCE2F

These questions test the same concept from different angles. Work through them to make sure you can recognise it however the exam phrases it.

Variation 1. What is the primary difference between a Highlight Report and a Checkpoint Report?

hard
  • ✓ A.A Highlight Report is sent to the Project Board; a Checkpoint Report is sent to the Project Manager
  • B.A Highlight Report is produced weekly; a Checkpoint Report is produced daily
  • C.A Highlight Report covers the entire project; a Checkpoint Report covers a stage
  • D.There is no difference; they are the same report with different names

Why A: The defining difference is the audience and reporting line: a Highlight Report is produced by the Project Manager for the Project Board to summarize stage progress, while a Checkpoint Report is produced by the Team Manager for the Project Manager to report progress within a stage. This distinction is about who receives the report, not just frequency.

Variation 2. In PRINCE2, what is the difference between a Highlight Report and a Checkpoint Report?

medium
  • A.Highlight Report covers the entire project; Checkpoint Report covers only a stage
  • B.Highlight Report is sent by the Team Manager; Checkpoint Report is sent by the Project Manager
  • C.There is no difference; they are the same document
  • ✓ D.Highlight Report is sent to the Project Board; Checkpoint Report is sent to the Project Manager

Why D: A Highlight Report is sent from the Project Manager to the Project Board regularly, while a Checkpoint Report is sent from the Team Manager to the Project Manager more frequently.

Variation 3. What is the difference between a Checkpoint Report and a Highlight Report?

easy
  • ✓ A.Checkpoint Reports are from Team Manager to Project Manager; Highlight Reports are from Project Manager to Project Board
  • B.Checkpoint Reports are produced by the Project Manager; Highlight Reports by the Team Manager
  • C.Checkpoint Reports are only produced at stage boundaries; Highlight Reports are produced weekly
  • D.Checkpoint Reports are sent to the Project Board; Highlight Reports are sent to the Project Manager

Why A: Checkpoint Reports flow from the Team Manager to the Project Manager at the frequency defined in the Work Package, covering progress, issues, and next steps. Highlight Reports flow from the Project Manager to the Project Board at the frequency defined in the Communication Management Strategy, summarising stage status, risks, and exceptions.

Variation 4. What is the difference between a Highlight Report and a Checkpoint Report?

hard
  • ✓ A.Highlight Reports are for the Project Board; Checkpoint Reports are for the Project Manager
  • B.They are the same but with different names
  • C.Highlight Reports are written by the team; Checkpoint Reports are written by the PM
  • D.Highlight Reports are for stakeholders; Checkpoint Reports are for the Project Board

Why A: In PRINCE2, the Highlight Report is produced by the Project Manager and sent to the Project Board to summarize stage progress, while the Checkpoint Report is produced by the Team Manager and sent to the Project Manager to report on Work Package progress. Thus, the key difference is the audience: Project Board versus Project Manager.

Variation 5. What is the difference between a Highlight Report and a Checkpoint Report?

hard
  • ✓ A.Highlight Reports are produced by the Project Manager; Checkpoint Reports are produced by the Team Manager
  • B.Highlight Reports are for the Project Board; Checkpoint Reports are for the Project Manager
  • C.Highlight Reports are produced weekly; Checkpoint Reports are produced daily
  • D.There is no difference; they are the same document

Why A: Highlight Reports are from Project Manager to Project Board and cover the whole stage. Checkpoint Reports are from Team Manager to Project Manager and cover a team's work.

Variation 6. What is the difference between a Highlight Report and a Checkpoint Report?

medium
  • A.The Highlight Report is used to escalate exceptions, while the Checkpoint Report is for routine communication
  • B.The Highlight Report is produced only at stage boundaries, while the Checkpoint Report is produced weekly
  • ✓ C.The Highlight Report is from the Project Manager to the Project Board, while the Checkpoint Report is from the Team Manager to the Project Manager
  • D.The Highlight Report focuses on risks and issues, while the Checkpoint Report focuses on product quality

Why C: In PRINCE2, the Highlight Report is a progress report produced by the Project Manager and sent to the Project Board at a frequency defined in the Communication Management Strategy (typically monthly or at stage boundaries). The Checkpoint Report is produced by the Team Manager and sent to the Project Manager at a frequency defined by the Work Package, typically weekly or at agreed checkpoints. This creates a clear upward reporting chain: Team Manager → Project Manager (Checkpoint) → Project Board (Highlight).

JA

Written by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

This PRINCE2F practice question is part of Courseiva's free PeopleCert certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PRINCE2F exam.