Courseiva
PRINCE2 PracticeshardMultiple ChoiceObjective-mapped

PRINCE2F PRINCE2 Practices Practice Question

During the Controlling a Stage process, the Team Manager reports that a work package is likely to be completed later than planned. The Project Manager assesses that stage tolerances will not be exceeded. What should the Project Manager do?

⚠ Common exam trap

Watch out — candidates often confuse a work package delay with a stage tolerance breach and incorrectly escalate to the Project Board via an Exception Report, failing to recognize that the Project Manager has authority to take corrective action within tolerances.

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

Take corrective action within the stage tolerance

D is correct because the Project Manager has assessed that the delay will not exceed the stage tolerances set by the Project Board. In PRINCE2, the Project Manager is empowered to take corrective action within stage tolerances without escalating to the Project Board. This ensures the stage remains on track while the Project Manager manages the work package deviation at their level.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • Request a change to the Work Package

    Why it's wrong here

    No change is needed as tolerances are not exceeded.

  • Update the Project Plan to reflect the delay

    Why it's wrong here

    The Project Plan is updated at stage boundaries, not during controlling a stage for minor delays.

  • Raise an Exception Report to the Project Board

    Why it's wrong here

    Exception Report is only needed if tolerances are forecast to be exceeded.

  • Take corrective action within the stage tolerance

    Why this is correct

    The PM can manage deviations within tolerance.

About these practice questions

This PRINCE2F question is part of Courseiva's 1,599-question bank — original exam-style content with full explanations and wrong-answer analysis, never real exam questions or exam dumps. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

This PRINCE2F practice question is part of Courseiva's free PeopleCert certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PRINCE2F exam.