PRINCE2 Practices →hardMultiple Choice

PRINCE2F PRINCE2 Practices Practice Question

During the Controlling a Stage process, the Team Manager reports that a work package is likely to be completed later than planned. The Project Manager assesses that stage tolerances will not be exceeded. What should the Project Manager do?

⚠ Common exam trap

Watch out — candidates often confuse a work package delay with a stage tolerance breach and incorrectly escalate to the Project Board via an Exception Report, failing to recognize that the Project Manager has authority to take corrective action within tolerances.

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

✓

Take corrective action within the stage tolerance

D is correct because the Project Manager has assessed that the delay will not exceed the stage tolerances set by the Project Board. In PRINCE2, the Project Manager is empowered to take corrective action within stage tolerances without escalating to the Project Board. This ensures the stage remains on track while the Project Manager manages the work package deviation at their level.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • ✗

    Request a change to the Work Package

    Why it's wrong here

    A change to the Work Package is not required: the Team Manager is already delivering it, and the reported slippage sits inside stage tolerances. Work Package changes suit altering scope, cost or acceptance criteria mid-stage; here the Project Manager simply monitors and records progress against the Stage Plan.

  • ✗

    Update the Project Plan to reflect the delay

    Why it's wrong here

    Updating the Project Plan is unnecessary because the delay stays within stage tolerances, so the stage-level plan and Work Package are the artefacts affected. The Project Plan is revised only when project-level tolerances are threatened or a Exception Plan is triggered, not for routine in-stage slippage.

  • ✗

    Raise an Exception Report to the Project Board

    Why it's wrong here

    An Exception Report is only raised when stage tolerances are forecast to be exceeded; here they are not, so the Project Manager should record the deviation and take corrective action within the stage. Escalating to the Project Board is tempting as a formal route, but tolerances remain intact.

  • ✓

    Take corrective action within the stage tolerance

    Why this is correct

    Because the deviation stays within stage tolerances, the Project Manager retains authority and handles it at stage level without escalation. Corrective action restores the work package to plan, satisfying the stem's condition that tolerances are not exceeded.

About these practice questions

This PRINCE2F question is part of Courseiva's 1,189-question bank — original exam-style content with full explanations and wrong-answer analysis, never real exam questions or exam dumps. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

This PRINCE2F practice question is part of Courseiva's free PeopleCert certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PRINCE2F exam.