PRINCE2F PRINCE2 Processes Practice Question
Which THREE of the following are roles that are appointed during the Starting Up a Project process?
Answer choices
Why each option matters
Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.
Correct answer & explanation
✓
Project Board
The Executive and Project Manager are appointed during SU, along with the Project Board members. The Team Manager is appointed later.
Answer analysis
Option-by-option breakdown
For each option: why learners choose it and why it is or isn't the right answer here.
- ✗
Project Assurance
Why it's wrong here
Project Assurance is appointed during Initiating a Project, not SU.
- ✓
Project Board
Why this is correct
The Project Board is appointed during Starting Up a Project.
- ✗
Team Manager
Why it's wrong here
The Team Manager is appointed later during the process.
- ✓
Project Manager
Why this is correct
During Starting Up a Project, the Project Manager is appointed to produce the Project Brief and initiate detailed planning, satisfying the requirement for a named individual to manage the day-to-day activities before the project board formally authorises initiation. This role is essential because the process mandates that a Project Manager be assigned to ensure the business case is viable and the project is feasible.
- ✓
Executive
Why this is correct
The Executive is appointed during Starting Up a Project.
Go deeper
Related to this question
About these practice questions
One of 1,599 original PRINCE2F practice questions on Courseiva, each with a full explanation and wrong-answer analysis — not exam dumps or protected exam content. Learn why practice questions differ from exam dumps →
Same concept, more angles
1 more way this is tested on PRINCE2F
These questions test the same concept from different angles. Work through them to make sure you can recognise it however the exam phrases it.
Variation 1. Which TWO roles are appointed during the Starting Up a Project process?
easy- A.Project Assurance
- ✓ B.Executive
- C.Senior User
- ✓ D.Project Manager
- E.Team Manager
Why B: During SU, the Executive and the Project Manager are appointed. The Project Board is also appointed, but the question asks for two specific roles. The Senior User and Senior Supplier are part of the Project Board but may be appointed later if not already in place.
JA
Written by Johnson Ajibi, MSc IT Security
Senior Network & Security Engineer · founder of Courseiva
This PRINCE2F practice question is part of Courseiva's free PeopleCert certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PRINCE2F exam.