PRINCE2 ProcessesmediumMultiple SelectObjective-mapped

PRINCE2F PRINCE2 Processes Practice Question

Which THREE of the following are roles that are appointed during the Starting Up a Project process?

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

Project Board

The Executive and Project Manager are appointed during SU, along with the Project Board members. The Team Manager is appointed later.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • Project Assurance

    Why it's wrong here

    Project Assurance is appointed during Initiating a Project, not SU.

  • Project Board

    Why this is correct

    The Project Board is appointed during Starting Up a Project.

  • Team Manager

    Why it's wrong here

    The Team Manager is appointed later during the process.

  • Project Manager

    Why this is correct

    During Starting Up a Project, the Project Manager is appointed to produce the Project Brief and initiate detailed planning, satisfying the requirement for a named individual to manage the day-to-day activities before the project board formally authorises initiation. This role is essential because the process mandates that a Project Manager be assigned to ensure the business case is viable and the project is feasible.

  • Executive

    Why this is correct

    The Executive is appointed during Starting Up a Project.

About these practice questions

One of 1,599 original PRINCE2F practice questions on Courseiva, each with a full explanation and wrong-answer analysis — not exam dumps or protected exam content. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

Same concept, more angles

1 more way this is tested on PRINCE2F

These questions test the same concept from different angles. Work through them to make sure you can recognise it however the exam phrases it.

Variation 1. Which TWO roles are appointed during the Starting Up a Project process?

easy
  • A.Project Assurance
  • B.Executive
  • C.Senior User
  • D.Project Manager
  • E.Team Manager

Why B: During SU, the Executive and the Project Manager are appointed. The Project Board is also appointed, but the question asks for two specific roles. The Senior User and Senior Supplier are part of the Project Board but may be appointed later if not already in place.

JA

Written by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

This PRINCE2F practice question is part of Courseiva's free PeopleCert certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PRINCE2F exam.