PRINCE2 Foundation (PRINCE2F) — Questions 12011275

1731 questions total · 24pages · All types, answers revealed

Page 16

Page 17 of 24

Page 18
1201
Multi-Selecthard

Which THREE of the following are threat responses in PRINCE2?

Select 3 answers
A.Transfer
B.Reduce
C.Enhance
D.Exploit
E.Avoid
AnswersA, B, E

Transfer is a threat response.

Why this answer

Avoid, reduce, and transfer are threat responses. Exploit and enhance are opportunity responses.

1202
Multi-Selectmedium

Which TWO of the following are activities performed during the Controlling a Stage process?

Select 2 answers
A.Produce the Project Initiation Documentation
B.Review the Business Case
C.Produce the End Project Report
D.Appoint the Executive
E.Authorize Work Packages
AnswersB, E

The PM reviews the Business Case in CS.

Why this answer

CS includes authorizing Work Packages, reviewing progress, and reporting. Producing the PID is done in IP.

1203
Multi-Selectmedium

Which THREE of the following are common reasons why projects fail, which PRINCE2 addresses?

Select 3 answers
A.Unclear project objectives
B.Lack of stakeholder engagement
C.Insufficient planning
D.Budget overrun due to inflation
E.Technology failure
AnswersA, B, C

PRINCE2 requires a clear Business Case.

Why this answer

PRINCE2 addresses lack of stakeholder involvement, unclear objectives, and insufficient planning. It does not address technology failures directly.

1204
MCQhard

What is the difference between a Request for Change (RFC) and an Off-Specification (Off-spec)?

A.An RFC is raised by the Project Manager; an Off-spec is raised by the Team Manager
B.An RFC is used in the Managing Product Delivery process; an Off-spec is used in the Controlling a Stage process
C.An RFC always requires approval; an Off-spec never requires approval
D.An RFC requests a change to a product; an Off-spec indicates a product does not meet its specification
AnswerD

Correct distinction.

Why this answer

An RFC proposes a change to an approved product, while an Off-spec identifies that a product does not meet its specification.

1205
Multi-Selecthard

Which TWO of the following statements about the Progress practice are correct?

Select 2 answers
A.An Exception Report is produced by the Project Manager when the project is closed early.
B.An Exception Plan is used to replace the Project Plan when the project exceeds its tolerances.
C.The Project Manager sets tolerances for the Team Managers.
D.Highlight Reports are produced by the Project Manager for the Project Board at stage end.
E.The Project Board sets tolerances for the Project Manager.
AnswersC, E

Correct. The Project Manager sets stage or work package tolerances for Team Managers.

Why this answer

Tolerances are set for each management level, and Exception Plans are created when tolerances are forecast to be exceeded.

1206
MCQhard

A Project Manager is in the Managing a Stage Boundary process and has produced the End Stage Report. The project is forecasting to exceed the project-level cost tolerance. What must the PM include in the next Stage Plan?

A.No Stage Plan; the project must be escalated immediately
B.A request to close the project
C.An Exception Plan that outlines the corrective actions and revised tolerances
D.A normal Stage Plan, but with additional cost contingencies
AnswerC

When project-level tolerances are threatened, an Exception Plan replaces the next Stage Plan.

Why this answer

If project-level tolerance is forecast to be exceeded, an Exception Plan is required instead of a normal Stage Plan. The Exception Plan must be approved by the Project Board.

1207
MCQmedium

In the Closing a Project process, what is the Project Manager responsible for producing?

A.End Project Report
B.Stage Plan
C.Benefits Review Plan
D.Project Brief
AnswerA

End Project Report is a key output of CP.

Why this answer

CP produces the End Project Report and Lessons Report. Benefits Review Plan is created earlier.

1208
MCQeasy

Which document is the key output of the Initiating a Project process?

A.Project Initiation Documentation (PID)
B.Project Brief
C.End Stage Report
D.Business Case
AnswerA

The PID is the key output of IP.

Why this answer

The Initiating a Project process is where the project's foundations are solidified, and its key output is the Project Initiation Documentation (PID). The PID consolidates all essential information—including the Business Case, project plan, risk register, and controls—into a single, comprehensive document that defines what the project will deliver, why, and how it will be managed. This makes it the definitive reference for project governance and the baseline against which progress is measured.

Exam trap

The trap here is that candidates often confuse the Project Brief (an early, high-level document) with the PID (the detailed, approved baseline), or they mistakenly think the Business Case alone is the key output, overlooking that the PID is the comprehensive package that includes it.

How to eliminate wrong answers

Option B (Project Brief) is wrong because the Project Brief is created during the Starting Up a Project process, not Initiating a Project; it provides the initial outline and is later refined into the PID. Option C (End Stage Report) is wrong because it is produced at the end of each management stage to report performance against the stage plan, not as an output of the initiation process. Option D (Business Case) is wrong because while the Business Case is a key component within the PID, it is not the sole output of Initiating a Project; the PID is the overarching document that includes the Business Case along with other critical sections.

1209
MCQmedium

During which process does the Project Board give ad-hoc direction to the Project Manager?

A.Controlling a Stage
B.Directing a Project
C.Initiating a Project
D.Starting Up a Project
AnswerB

Why this answer

The Directing a Project (DP) process includes the activity of giving ad-hoc direction to the Project Manager as needed.

1210
Multi-Selecthard

Which THREE of the following are typical components of a Business Case?

Select 3 answers
A.Major risks
B.Project Initiation Documentation
C.Investment appraisal
D.Expected benefits
E.Project management team roles
AnswersA, C, D

Risks are documented in the Business Case.

Why this answer

Options A, C, and D are correct. A Business Case typically includes reasons, expected benefits, dis-benefits, costs, timescales, major risks, and investment appraisal. Option B is incorrect because the PID is a separate document that contains the Business Case but is not itself a component of the Business Case.

Option E is incorrect because team roles are part of the Organising practice.

1211
MCQeasy

Which practice defines the project management team structure and roles?

A.Business Case
B.Plans
C.Progress
D.Organising
AnswerD

Organising defines the project management team structure and roles.

Why this answer

The Organising practice defines the project management team structure, roles, and responsibilities.

1212
MCQeasy

Who chairs the Project Board meetings?

A.Project Manager
B.Senior User
C.Senior Supplier
D.Executive (Senior Responsible Owner)
AnswerD

The Executive chairs the Project Board.

Why this answer

The Executive (Senior Responsible Owner) chairs the Project Board meetings.

1213
MCQeasy

Who is responsible for maintaining the Business Case throughout the project?

A.Senior User
B.Executive
C.Project Assurance
D.Project Manager
AnswerB

The Executive owns the Business Case and is responsible for ensuring business justification is maintained throughout the project.

Why this answer

Option A is correct. The Executive owns the Business Case and is responsible for ensuring it remains viable. The Project Manager maintains it on a day-to-day basis but the Executive has ultimate accountability.

Option B is wrong because the Project Manager maintains it but is not responsible for its ongoing viability. Option C is wrong because the Senior User is a role on the Project Board, not the owner of the Business Case. Option D is wrong because Project Assurance provides independent oversight, not business justification.

1214
MCQhard

A Team Manager is assigned a Work Package. The Team Manager realizes that the work cannot be completed within the agreed tolerances. What should the Team Manager do?

A.Take corrective action to bring the work back within tolerance
B.Continue working and report the issue in the next Checkpoint Report
C.Raise an Exception Report to the Project Board
D.Raise an Issue Report to the Project Manager
AnswerD

Correct. The Team Manager escalates to the PM via an Issue Report when Work Package tolerances are forecast to be exceeded.

Why this answer

If a Team Manager forecasts that a Work Package tolerance will be exceeded, they must escalate to the Project Manager via an Issue Report. The Project Manager then decides how to proceed.

1215
MCQhard

A project is forecast to exceed its cost tolerance. What should the Project Manager do?

A.Close the project as the Business Case is no longer viable
B.Continue with the current Plan and report in the next Highlight Report
C.Increase the project budget to absorb the additional cost
D.Raise an Exception Report to the Project Board
AnswerD

An Exception Report is the correct mechanism to escalate tolerance breaches.

Why this answer

When a forecast indicates that a stage or project tolerance will be exceeded, the Project Manager must escalate via an Exception Report to the Project Board. This is management by exception.

1216
MCQmedium

What is the purpose of a Checkpoint Report?

A.To provide the Project Manager with information on team progress
B.To provide the Project Board with information on stage progress
C.To report an exception to the Project Board
D.To document lessons learned
AnswerA

Correct. Checkpoint Reports are from Team Manager to Project Manager.

Why this answer

A Checkpoint Report is prepared by the Team Manager and given to the Project Manager to report progress at regular intervals (e.g., weekly).

1217
Multi-Selecteasy

Which TWO are roles that are part of the Project Board?

Select 2 answers
A.Project Manager
B.Project Assurance
C.Team Manager
D.Senior User
E.Executive (Senior Responsible Owner)
AnswersD, E

The Senior User represents user interests.

Why this answer

The Project Board consists of Executive (Senior Responsible Owner), Senior User, and Senior Supplier.

1218
MCQhard

A project is using the PRINCE2 risk management procedure. A risk has been identified that, if it occurs, could cause a major delay to the project. The risk owner decides to take action to reduce the probability of the risk occurring. Which risk response type is being used?

A.Accept
B.Avoid
C.Reduce
D.Transfer
AnswerC

Correct. Taking action to lower probability or impact is the Reduce response.

Why this answer

The 'Reduce' response involves actions to lower the probability and/or impact of a threat. The scenario describes reducing probability, which fits 'Reduce'. 'Avoid' would change the plan to eliminate the risk; 'Transfer' would shift the risk to a third party; 'Accept' would acknowledge the risk without action.

1219
MCQhard

In PRINCE2, what is the definition of quality?

A.Freedom from defects
B.Conformance to specifications
C.Customer satisfaction
D.Fit for purpose
AnswerD

The PRINCE2 definition of quality is 'fit for purpose'.

Why this answer

PRINCE2 defines quality as 'fit for purpose', meaning the product meets its stated requirements and acceptance criteria.

1220
Multi-Selectmedium

Which TWO of the following are opportunity responses in PRINCE2?

Select 2 answers
A.Enhance
B.Transfer
C.Exploit
D.Reduce
E.Avoid
AnswersA, C

Enhance is an opportunity response to increase the probability or impact.

Why this answer

The PRINCE2 opportunity responses are Exploit, Enhance, Share, and Reject. Avoid and Reduce are threat responses.

1221
MCQhard

A project is forecast to exceed its stage cost tolerance. What should the Project Manager do?

A.Continue and report the overrun in the next Highlight Report
B.Close the project as the Business Case is no longer viable
C.Raise an Exception Report to the Project Board
D.Increase the stage budget to absorb the overrun and continue
AnswerC

This is the correct escalation procedure when a stage tolerance is forecast to be exceeded.

Why this answer

In PRINCE2, management by exception means the Project Manager must escalate to the Project Board when a stage tolerance is forecast to be exceeded. The correct action is to raise an Exception Report.

1222
MCQhard

A project is in the Initiating a Project process. Which document is created to define how issues and changes will be managed?

A.Issue Register
B.Business Case
C.Change Management Approach
D.Project Plan
AnswerC

This document defines the approach to managing issues and changes.

Why this answer

The Change Management Approach document is created during initiation to define how issues, changes, and configuration management will be handled.

1223
Multi-Selectmedium

Which TWO of the following are responsibilities of the Senior Responsible Owner (SRO/Executive) on the Project Board?

Select 2 answers
A.Day-to-day management of the project
B.Accountable for the Business Case
C.Chairing the Project Board
D.Preparing the Highlight Report
E.Defining the technical specifications of products
AnswersB, C

The SRO owns the Business Case and ensures its viability.

Why this answer

The Senior Responsible Owner (SRO/Executive) is accountable for the Business Case, ensuring the project remains viable and aligned with organizational objectives. This includes approving the Business Case at initiation and any subsequent changes, as well as securing the necessary funding. The SRO also chairs the Project Board, providing overall leadership and direction, and is ultimately responsible for the project's success.

Exam trap

PeopleCert often tests the distinction between accountability (SRO/Executive) and responsibility (Project Manager or Senior User), leading candidates to confuse the SRO's strategic duties with the Project Manager's tactical tasks like reporting or management.

1224
MCQeasy

Who is responsible for approving the Project Plan?

A.Senior User
B.Project Manager
C.Project Board
D.Executive
AnswerC

The Project Board approves the Project Plan.

Why this answer

The Project Plan is approved by the Project Board as part of the PID approval.

1225
MCQeasy

Which document describes the quality management approach for the project, including quality assurance and quality control activities?

A.Quality Register
B.Project Plan
C.Quality Management Approach
D.Product Description
AnswerC

Defines the project-specific quality management strategy.

Why this answer

The Quality Management Approach defines how quality will be managed on the project, including assurance and control activities. The Project Plan includes overall schedule, and the Quality Register records results.

1226
MCQeasy

What does PRINCE2 NOT cover?

A.Human resource management
B.Risk management
C.Change control
D.Quality management
AnswerA

Correct.

Why this answer

PRINCE2 does not cover HR management; it provides a project management methodology.

1227
MCQmedium

What is the purpose of the Directing a Project process?

A.To enable the Project Board to make key decisions and exercise overall control
B.To deliver the project's products
C.To plan the next stage
D.To manage the day-to-day activities of the project
AnswerA

DP is the Project Board's process for decision-making and direction.

Why this answer

DP enables the Project Board to make key decisions and provide overall direction and control throughout the project.

1228
MCQmedium

A Project Manager receives a Checkpoint Report from a Team Manager. What should the Project Manager do with this information?

A.Use it to update the Stage Plan and prepare the Highlight Report
B.File it without action as it is only for information
C.Forward it directly to the Project Board
D.Send it to Project Assurance for review
AnswerA

Checkpoint Reports provide detailed progress that feeds into the Highlight Report.

Why this answer

The Project Manager uses Checkpoint Reports to monitor progress and compile the Highlight Report for the Project Board.

1229
MCQeasy

What is the purpose of the Directing a Project process?

A.To produce the Project Plan
B.To manage the day-to-day activities of the project
C.To ensure that project products are delivered on time
D.To enable the Project Board to make key decisions and exercise overall control
AnswerD

This is the correct purpose.

Why this answer

Directing a Project enables the Project Board to make key decisions and exercise overall control.

1230
MCQhard

What is the difference between a Request for Change and an Off-specification?

A.Request for Change is for new requirements; Off-specification is for defects
B.Request for Change is for minor changes; Off-specification is for major changes
C.Off-specification is raised by the Project Board; Request for Change is raised by the Project Manager
D.They are synonyms
AnswerA

Correct. An RFC proposes a change; an Off-specification identifies a failure to meet specifications.

Why this answer

A Request for Change is a proposal for a change to a product that has been baselined; an Off-specification is a product that does not meet its specification.

1231
MCQhard

During a stage, the Project Manager receives a Checkpoint Report from a Team Manager. What is the primary purpose of this report?

A.To communicate progress of a Work Package to the Project Manager
B.To request changes to the Work Package
C.To escalate issues that cannot be resolved at team level
D.To inform the Project Board of stage progress
AnswerA

The Checkpoint Report is from Team Manager to Project Manager.

Why this answer

A Checkpoint Report is a progress report from the Team Manager to the Project Manager, typically covering the frequency defined in the Work Package.

1232
MCQeasy

Who is responsible for creating the Project Initiation Documentation?

A.Project Board
B.Senior Supplier
C.Project Manager
D.Senior User
AnswerC

The PM creates the PID.

Why this answer

The Project Manager is responsible for creating the Project Initiation Documentation (PID) because PRINCE2 assigns the Project Manager the role of assembling and producing the PID, which consolidates key planning documents like the Business Case, Project Plan, and Risk Register. The Project Board approves the PID, but does not create it, as the Project Manager acts as the single point of accountability for its preparation and quality.

Exam trap

PeopleCert often tests the distinction between 'creating' and 'approving' management products, and the trap here is that candidates confuse the Project Board's approval authority with the Project Manager's production responsibility, leading them to incorrectly select the Project Board.

How to eliminate wrong answers

Option A is wrong because the Project Board is responsible for approving the PID, not creating it; their role is to provide governance and make key decisions, not to produce detailed documentation. Option B is wrong because the Senior Supplier represents the supplier interests on the Project Board and provides resources and expertise, but does not create the PID, which is a management product owned by the Project Manager. Option D is wrong because the Senior User represents the user community and specifies requirements, but the PID creation is a project management responsibility, not a user representative function.

1233
MCQeasy

Which role is responsible for defining the project's acceptance criteria?

A.Project Manager
B.Project Board
C.Senior User
D.Executive
AnswerC

The Senior User defines the acceptance criteria on behalf of the users.

Why this answer

The Senior User is responsible for specifying user requirements and acceptance criteria. The Executive focuses on business justification, the Project Manager on delivery, and the Project Board on overall direction.

1234
Multi-Selecthard

Which THREE of the following are purposes of the Highlight Report?

Select 3 answers
A.To highlight the achievements and next-period plans
B.To provide a summary of progress during a management stage
C.To inform the Project Board of any issues or risks that need their attention
D.To provide a full review of the stage and recommend changes for the next stage
E.To provide a detailed account of Work Package progress to the Project Manager
AnswersA, B, C

The report includes accomplishments and plans for the next period.

Why this answer

The Highlight Report is used to provide the Project Board with a summary of progress, including achievements, next steps, and issues. Option A, C, and D are correct. Option B is the purpose of the Checkpoint Report.

Option E is the purpose of the End Stage Report.

1235
Multi-Selectmedium

Which TWO of the following are components of the PRINCE2 quality management approach?

Select 2 answers
A.The quality register
B.The quality responsibilities of the project management team
C.The project assurance responsibilities
D.The quality review technique
E.The quality methods and tools to be used
AnswersB, E

Correct. Responsibilities are defined in the quality management approach.

Why this answer

The quality management approach includes the quality responsibilities of the project team (option A) and the quality methods and tools to be used (option C). The quality register is a log, not part of the approach; the quality review technique is a method but the approach includes overall methods; project assurance is a role, not a component of the approach.

1236
MCQhard

In the Organizing practice, what is the role of Project Assurance?

A.To perform administrative tasks for the Project Manager
B.To manage the project on behalf of the Project Board
C.To provide independent monitoring of the project's progress and adherence to standards
D.To represent the users' interests
AnswerC

Correct.

Why this answer

Project Assurance provides independent oversight, not management or support. It checks that the project is being run correctly.

1237
MCQmedium

When should the Project Manager escalate an issue to the Project Board?

A.When the issue involves the Project Manager's own performance
B.Only at the end of a stage
C.When the issue cannot be resolved within the delegated tolerances
D.Only when the issue is identified
AnswerC

Escalation is required when tolerances are forecast to be exceeded.

Why this answer

Issues that threaten tolerances or require changes to baselines should be escalated. The PM manages issues within their authority.

1238
Multi-Selectmedium

Which TWO of the following are benefits of adopting PRINCE2?

Select 2 answers
A.Encourages consistency of project delivery
B.Guarantees project success
C.Provides a common language across projects
D.Ensures lower project costs
E.Eliminates the need for change control
AnswersA, C

Standard processes promote consistency.

Why this answer

Benefits include common terminology and consistency across projects. Option B and C are correct. Option A is false because PRINCE2 does not guarantee success.

Option D is false because it does not eliminate change. Option E is false because it does not guarantee lower costs.

1239
Multi-Selectmedium

Which TWO are types of issue in PRINCE2?

Select 2 answers
A.Opportunity
B.Request for Change
C.Off-specification
D.Risk
E.Constraint
AnswersB, C

An RFC is an issue type.

Why this answer

Issue types are: Request for Change, Off-specification, and Problem/Concern.

1240
MCQeasy

Which PRINCE2 process is triggered by the authorization of an Exception Plan?

A.Managing Product Delivery
B.Directing a Project
C.Controlling a Stage
D.Managing a Stage Boundary
AnswerC

Correct. After an Exception Plan is approved, the Project Manager executes it within Controlling a Stage.

Why this answer

An Exception Plan is approved by the Project Board, and the project then returns to the Controlling a Stage process to execute the plan.

1241
MCQmedium

What is the difference between a Request for Change and an Off-specification?

A.A Request for Change is always accepted, while an Off-specification is always rejected
B.A Request for Change is submitted by the Project Board, while an Off-specification is submitted by the Project Manager
C.A Request for Change proposes a change to a baseline, while an Off-specification is a product that does not meet its specification
D.A Request for Change must be approved by the Project Board, while an Off-specification can be approved by the Project Manager
AnswerC

This is the correct distinction.

Why this answer

A Request for Change is a proposal to change a baseline, while an Off-specification is a deviation from an agreed baseline that already exists.

1242
MCQmedium

A project is forecast to exceed its cost tolerance. What should the Project Manager do?

A.Close the project immediately as the Business Case is no longer viable
B.Increase the project budget to absorb the additional cost and continue with the current Stage Plan
C.Continue with the current Stage Plan and report the cost overrun in the next Highlight Report
D.Raise an Exception Report to the Project Board and await their direction before proceeding
AnswerD

This is the correct action when a stage tolerance is forecast to be exceeded.

Why this answer

When a tolerance is forecast to be exceeded, the Project Manager must escalate to the Project Board via an Exception Report, following the management by exception principle.

1243
MCQhard

You are the project manager for a large-scale IT infrastructure project for a multinational corporation. The project involves deploying new servers across 20 countries, with a budget of $5 million and a timeline of 18 months. The project has been running for 6 months and is currently in its second stage. The project board consists of the executive, senior user, and senior supplier. Recently, the senior user has been raising concerns that the project is not delivering the expected benefits, and the business case may no longer be viable due to changes in market conditions. The senior supplier argues that the project should continue because significant resources have already been invested. The executive is undecided. As the project manager, you need to advise the project board on the best course of action based on PRINCE2 principles. Which of the following should you recommend?

A.Postpone the decision until the end of the current stage to conduct a full review.
B.Request the project board to review and update the business case immediately. If it is no longer viable, recommend stopping the project.
C.Tailor the continued business justification principle to allow the project to continue due to its strategic importance.
D.Continue with the project as planned because significant investment has already been made.
AnswerB

This aligns with the continued business justification principle.

Why this answer

B is correct because PRINCE2's continued business justification principle requires that the business case remain viable throughout the project. As project manager, you must escalate to the project board for an immediate review when the senior user raises concerns about benefits and market changes. If the business case is no longer viable, the project should be stopped to avoid further waste of resources, regardless of sunk costs.

Exam trap

The trap here is that candidates confuse the 'manage by stages' principle with delaying decisions, or they incorrectly believe that tailoring can override a fundamental principle like continued business justification.

How to eliminate wrong answers

Option A is wrong because postponing the decision until the end of the stage violates the continued business justification principle, which demands immediate reassessment when viability is questioned. Option C is wrong because tailoring cannot override a core principle; the continued business justification principle must be upheld, not tailored away to allow an unviable project to continue. Option D is wrong because continuing due to significant investment already made is a classic sunk cost fallacy, which PRINCE2 explicitly rejects in favor of ongoing business justification.

1244
MCQeasy

Who is responsible for providing independent assurance that the project is being managed correctly?

A.Team Manager
B.Project Board (via Project Assurance)
C.Project Manager
D.Project Support
AnswerB

Correct: Project Assurance is independent of management.

Why this answer

Project Assurance is a Project Board responsibility, delegated to independent individuals to ensure objectivity.

1245
Multi-Selectmedium

Which TWO of the following describe the role of Project Assurance?

Select 2 answers
A.Assures the Project Board that the project is on track
B.Provides administrative support to the project team
C.Reports to the Project Board via Highlight Reports
D.Independent of the Project Manager
E.Manages the delivery of Work Packages
AnswersA, D

This is the primary purpose of Project Assurance.

Why this answer

Project Assurance is an independent role that checks the project is on track and cannot be delegated to the Project Manager. It supports the Board.

1246
MCQmedium

What is the primary difference between Project Assurance and a quality review?

A.Project Assurance is a continuous activity; a quality review is a scheduled event
B.Project Assurance is performed by the Project Manager; quality reviews are performed by the team
C.There is no difference; they are the same
D.Project Assurance focuses on risks; quality reviews focus on issues
AnswerA

Assurance is ongoing throughout the project; quality reviews are specific events.

Why this answer

Project Assurance is an ongoing independent oversight of the project's management, while a quality review is a specific technique to assess the quality of a product at a given point in time.

1247
Multi-Selectmedium

Which TWO of the following are types of issue in PRINCE2?

Select 2 answers
A.Off-specification
B.Opportunity
C.Risk
D.Change budget
E.Request for Change
AnswersA, E

Correct issue type.

Why this answer

PRINCE2 defines three issue types: Request for Change, Off-specification, and Problem/Concern. 'Risk' and 'Change budget' are not issue types.

1248
MCQhard

What is the purpose of the Quality Review technique in PRINCE2?

A.To approve the Stage Plan
B.To assess whether a product is fit for purpose and identify any defects
C.To create the Product Description
D.To update the Risk Register
AnswerB

This is the purpose of the Quality Review technique.

Why this answer

The Quality Review technique in PRINCE2 is a structured assessment to evaluate whether a product meets its defined quality criteria and is fit for purpose. Its primary purpose is to identify defects and ensure the product is complete and correct before it is approved for use. This aligns with option B, as the review focuses on verifying product quality rather than planning or risk management.

Exam trap

The trap here is that candidates confuse the Quality Review technique with other management activities, such as planning or risk management, because PRINCE2 integrates quality checks into multiple processes, but the review's sole purpose is product assessment and defect identification.

How to eliminate wrong answers

Option A is wrong because approving the Stage Plan is a function of the Project Board, not the Quality Review technique; the review assesses products, not plans. Option C is wrong because the Product Description is created during product-based planning, not by the Quality Review technique; the review uses the Product Description as a reference to check quality. Option D is wrong because updating the Risk Register is part of the Risk Management practice, not the Quality Review technique; the review focuses on product defects, not risk identification or updates.

1249
MCQeasy

Which document describes the quality methods and tools to be used on a project?

A.Quality Register
B.Product Description
C.Quality Management Approach
D.Project Plan
AnswerC

This document describes how quality will be managed on the project.

Why this answer

The Quality Management Approach defines the quality procedures, techniques, and responsibilities for the project.

1250
Multi-Selectmedium

Which TWO of the following are responsibilities of the Project Board?

Select 2 answers
A.Specify the user requirements
B.Authorize the Project Plan
C.Authorize Stage Plans
D.Maintain the Business Case
E.Produce the Project Plan
AnswersB, C

The Project Board approves the Project Plan at initiation.

Why this answer

The Project Board provides direction and control. Options A and B are correct. Option C is the PM's responsibility, D is the Senior User's, E is the SRO's.

1251
MCQhard

In PRINCE2, what is the difference between a risk owner and a risk actionee?

A.The risk owner owns the risk budget; the risk actionee does not
B.The risk owner is a senior role; the risk actionee is a team role
C.The risk owner is responsible for managing the risk; the risk actionee is responsible for implementing the response actions
D.There is no difference; the terms are interchangeable
AnswerC

Correct. Owner: management; Actionee: implementation.

Why this answer

The risk owner manages the risk overall; the risk actionee performs specific actions.

1252
MCQmedium

Who is responsible for ensuring that Project Assurance is performed?

A.Project Board
B.Project Manager
C.Senior Supplier
D.Team Manager
AnswerA

The Project Board is responsible for ensuring that Project Assurance is performed independently.

Why this answer

The Project Board is accountable for the project and must ensure that independent assurance is in place. The Executive (SRO) often appoints assurance roles, but ultimate responsibility lies with the Project Board.

1253
MCQmedium

A project is in the Managing a Stage Boundary process. Which document should the Project Manager produce to report the current stage's performance?

A.End Stage Report
B.Highlight Report
C.Lesson Log
D.Project Brief
AnswerA

The End Stage Report is produced during Managing a Stage Boundary to report on the current stage.

Why this answer

During Managing a Stage Boundary, the Project Manager produces an End Stage Report to report the performance of the current stage. Highlight Reports are produced during Controlling a Stage. The Lesson Log is updated throughout.

The Project Brief is from Starting Up a Project.

1254
MCQmedium

A project is forecast to exceed its stage cost tolerance. What should the Project Manager do?

A.Raise an Exception Report to the Project Board
B.Increase the budget and continue
C.Close the project immediately
D.Continue and report in the next Highlight Report
AnswerA

The PM must escalate via an Exception Report.

Why this answer

Escalation via Exception Report is required when a tolerance is forecast to be exceeded.

1255
Multi-Selecthard

Which THREE of the following are components of the Project Initiation Documentation (PID)?

Select 3 answers
A.Project Plan
B.Highlight Report
C.Checkpoint Report
D.Risk Management Approach
E.Business Case
AnswersA, D, E

Project Plan is part of PID.

Why this answer

Options A, C, and D are correct. PID includes Project Plan, Business Case, and Risk Management Approach. Highlight Report is from CS; Checkpoint Report is from MP.

1256
MCQhard

In PRINCE2, what is the difference between a risk owner and a risk actionee?

A.Risk owner and risk actionee are the same role
B.Risk owner is accountable for managing the risk; risk actionee carries out the response actions
C.Risk owner identifies risks; risk actionee assesses them
D.Risk owner is a role on the Project Board; risk actionee is a team member
AnswerB

Correct distinction.

Why this answer

The risk owner manages the risk and is accountable for its management. The risk actionee carries out specific actions but is not accountable. This is a key distinction in PRINCE2 risk practice.

1257
MCQhard

Given the exhibit, what is a potential issue with the decision-making process for the project board?

A.Using majority vote may undermine the principle of unified direction
B.Progress reports are too frequent, causing information overload
C.The Senior Supplier is represented by an individual rather than the organization
D.The roles are filled by three individuals, but there should be only two
AnswerA

PRINCE2 recommends consensus, not majority vote.

Why this answer

Option A is correct because the PRINCE2 principle of 'continued business justification' and 'manage by stages' require the project board to make decisions by consensus, not majority vote. Using majority vote undermines the principle of unified direction, as the project board must act as a single, cohesive unit representing business, user, and supplier interests. The exhibit likely shows a board where voting could lead to a split decision, violating the PRINCE2 requirement for joint decision-making.

Exam trap

PeopleCert often tests the misconception that majority voting is a valid decision-making method in PRINCE2, when in fact it violates the principle of unified direction and collective responsibility.

How to eliminate wrong answers

Option B is wrong because the question focuses on the decision-making process, not the frequency of progress reports; while too-frequent reports could cause overload, this is not directly related to the board's decision-making mechanism. Option C is wrong because the Senior Supplier role is correctly filled by an individual who represents the supplier organization's interests; PRINCE2 does not require the organization itself to be on the board. Option D is wrong because PRINCE2 specifies three distinct roles for the project board (Executive, Senior User, Senior Supplier), not two; having three individuals is correct and required.

1258
Multi-Selecthard

Which TWO of the following are responsibilities of the Project Manager during the Controlling a Stage process?

Select 2 answers
A.Review progress and take corrective action
B.Authorize Work Packages
C.Produce the End Project Report
D.Produce Checkpoint Reports
E.Authorize the stage plan
AnswersA, B

The PM monitors progress and takes action to keep the stage within tolerance.

Why this answer

Option A is correct because the Project Manager is responsible for reviewing progress against the stage plan and taking corrective action when deviations occur, as defined in the Controlling a Stage process. This ensures the stage remains within tolerance and aligns with the project plan.

Exam trap

PeopleCert often tests the distinction between who produces versus who authorizes management products, and the trap here is confusing the Project Manager's role in creating a stage plan with the Project Board's authority to approve it.

1259
MCQmedium

Which document is created during the Initiating a Project process and provides a baseline against which the project is managed?

A.Project Initiation Documentation (PID)
B.Project Brief
C.Project Plan
D.Business Case
AnswerA

Correct. The PID is the key output of the Initiating a Project process and serves as the baseline.

Why this answer

The Project Initiation Documentation (PID) is the key output of the Initiating a Project process. It defines the project's scope, objectives, and plan, and is used as a baseline for management decisions.

1260
MCQhard

During a stage, the Team Manager identifies a problem that affects the quality of a product. The product description specifies a quality criterion that cannot be met. What type of issue is this?

A.Problem/concern
B.Risk
C.Request for change
D.Off-specification
AnswerD

An off-specification is when a product does not meet its specification.

Why this answer

This is an off-specification because an agreed product is not meeting its specification. A problem/concern is a general issue, but this is specifically an off-specification.

1261
MCQmedium

Who is responsible for producing a Checkpoint Report?

A.Project Board
B.Project Manager
C.Team Manager
D.Project Support
AnswerC

The Team Manager produces Checkpoint Reports in MP.

Why this answer

Checkpoint Reports are produced by the Team Manager (or the person managing the Work Package) and sent to the Project Manager during the Managing Product Delivery process.

1262
MCQmedium

Which role is responsible for authorizing the initiation of a project?

A.The Executive
B.The Project Manager
C.The Project Board
D.The Senior User
AnswerC

The Project Board authorizes initiation, approves stage plans, and makes key decisions throughout the project.

Why this answer

The Project Board provides overall direction and authorizes key decisions including initiation. The Executive is a member of the Project Board but does not act alone.

1263
Multi-Selecthard

Which THREE of the following are integrated elements of PRINCE2?

Select 3 answers
A.Principles
B.Project Mandate
C.Tailoring
D.Practices (Themes)
E.Processes
AnswersA, D, E

Correct. The 7 principles are a core element.

Why this answer

The integrated elements are the principles, practices (themes), and processes. Tailoring is how they adapt, but it is not an element itself. The project mandate is an input.

1264
MCQhard

In the Controlling a Stage process, a Team Manager reports that a product is complete. Which activity does the Project Manager perform next?

A.Send a Highlight Report to the Project Board
B.Approve the next Stage Plan
C.Review the product to confirm it meets quality criteria
D.Update the Project Plan
AnswerC

The PM must check that the product meets the defined quality criteria before acceptance.

Why this answer

In the Controlling a Stage process, after a Team Manager reports that a product is complete, the Project Manager must first review the product to confirm it meets the quality criteria defined in the Product Description. This is part of the 'Review Work Package' activity, ensuring that the product is fit for purpose before any further actions, such as reporting or planning, occur. Only after this quality check can the Project Manager proceed to other activities like updating logs or sending reports.

Exam trap

The trap here is that candidates often confuse the immediate operational step (quality review) with higher-level reporting or planning activities, assuming that a completion report automatically triggers a Highlight Report or stage approval without the necessary quality check first.

How to eliminate wrong answers

Option A is wrong because sending a Highlight Report is a periodic activity to inform the Project Board of progress, not the immediate next step after a product completion report; the Project Manager must first verify the product's quality. Option B is wrong because approving the next Stage Plan occurs during the Managing a Stage Boundary process, not within Controlling a Stage, and it is not triggered by a single product completion. Option D is wrong because updating the Project Plan is a broader planning activity that typically happens after stage boundaries or when significant changes occur, not as the immediate response to a completed product; the Project Manager first checks quality, then updates the Quality Register and logs.

1265
Multi-Selectmedium

Which TWO of the following are outputs of the Closing a Project process?

Select 2 answers
A.End Project Report
B.Project Product Description
C.Benefits Management Approach
D.Lessons Log
E.Project Plan
AnswersA, B
1266
MCQeasy

Who chairs the Project Board?

A.Senior User
B.Senior Supplier
C.Senior Responsible Owner (Executive)
D.Project Manager
AnswerC

The SRO chairs the Project Board.

Why this answer

The Senior Responsible Owner (Executive) chairs the Project Board. Option A is correct.

1267
Multi-Selectmedium

Which THREE of the following are types of issue in PRINCE2?

Select 3 answers
A.Request for Change
B.Problem/Concern
C.Risk
D.Off-specification
E.Change
AnswersA, B, D

An RFC is a proposal to change a baseline.

Why this answer

Options B, C, and D are correct. The three types of issue are: Request for Change (RFC), Off-specification, and Problem/Concern. 'Risk' is not an issue; it is a potential future event. 'Change' is a general term, not a specific type.

1268
MCQmedium

During the Starting Up a Project process, what is the role of the Project Manager?

A.To assist the Executive in developing the Project Brief and preparing for initiation
B.To create the Project Initiation Documentation
C.To assign work packages to the team
D.To produce the Project Plan
AnswerA

Correct. The PM supports the Executive in Starting Up a Project.

Why this answer

The Project Manager assists the Executive in preparing the Project Brief and other initiation documentation.

1269
MCQhard

A project is forecast to exceed its cost tolerance. According to PRINCE2, what should the Project Manager do?

A.Raise an Exception Report to the Project Board and await their direction before proceeding
B.Increase the project budget to absorb the additional cost and continue with the current Stage Plan
C.Continue with the current Stage Plan and report the cost overrun in the next Highlight Report
D.Close the project immediately as the Business Case is no longer viable
AnswerA

Escalation via Exception Report is required when a tolerance is forecast to be breached.

Why this answer

When a tolerance is forecast to be exceeded, the Project Manager must escalate to the Project Board via an Exception Report. Option C is correct. This is PRINCE2's management by exception principle.

1270
MCQhard

A project is in its final stage. The Project Manager has prepared the End Project Report and Lessons Report. What must happen before the project can be closed?

A.The final products must be delivered to the operations team
B.The Business Case must be updated with actual costs and benefits
C.The Project Board must approve the End Project Report and authorize closure
D.The project team must be released
AnswerC

Closure is authorized by the Project Board in DP, after reviewing the End Project Report.

Why this answer

The Project Board must authorize project closure through the Directing a Project process. The PM prepares the recommendation, but only the Board can formally close.

1271
MCQmedium

Who is responsible for managing the project's day-to-day activities within the tolerances set by the Project Board?

A.Project Manager
B.Senior User
C.Project Board
D.Team Manager
AnswerA

The PM manages the project day-to-day.

Why this answer

In PRINCE2, the Project Manager is responsible for the day-to-day management of the project within the tolerances set by the Project Board. This includes planning, monitoring, and controlling project activities, escalating issues or deviations that exceed tolerances. The Project Board sets the overall direction and tolerances but does not manage daily tasks.

Exam trap

The trap here is that candidates often confuse the Project Manager's operational authority with the Team Manager's delivery focus, or mistakenly think the Project Board handles daily tasks because it 'manages' the project at a high level.

How to eliminate wrong answers

Option B (Senior User) is wrong because the Senior User represents the interests of those who will use the project's products and is responsible for specifying requirements and benefits, not for day-to-day management. Option C (Project Board) is wrong because the Project Board provides overall direction, approves plans, and sets tolerances, but does not manage daily activities. Option D (Team Manager) is wrong because the Team Manager is responsible for delivering specific products within a work package, but the Project Manager retains overall day-to-day management responsibility for the project.

1272
MCQhard

During the Managing a Stage Boundary process, the Project Manager produces an End Stage Report. What is the primary purpose of this report?

A.To document lessons learned for future projects
B.To request additional budget for the next stage
C.To provide information for the Project Board to decide on proceeding to the next stage
D.To hand over completed products to the customer
AnswerC

Correct: The End Stage Report informs the Board's go/no-go decision.

Why this answer

The primary purpose of the End Stage Report in the Managing a Stage Boundary process is to provide the Project Board with a summary of the stage's performance against the plan, including progress, issues, and risks, so they can make an informed decision on whether to authorize the next stage. This aligns with PRINCE2's principle of management by stages, where the board reviews stage-end information to confirm continued business justification.

Exam trap

PeopleCert often tests the distinction between the End Stage Report (for stage-end decision-making) and the Lessons Report (for organizational learning), tempting candidates to choose 'lessons learned' because both involve review activities.

How to eliminate wrong answers

Option A is wrong because lessons learned are formally captured in the Lessons Log and Lessons Report, not the End Stage Report; the End Stage Report focuses on stage performance, not future project improvements. Option B is wrong because requesting additional budget is handled through an Exception Report or a formal Change Request, not the End Stage Report, which reports on actuals versus plan. Option D is wrong because handing over completed products to the customer occurs during the Managing Product Delivery process or as part of product handover activities, not via the End Stage Report, which is a management product for the Project Board.

1273
MCQeasy

Who is responsible for maintaining the Business Case throughout the project?

A.Project Assurance
B.Senior User
C.Project Manager
D.Executive
AnswerC

The Project Manager maintains the Business Case throughout the project.

Why this answer

The Project Manager is responsible for maintaining the Business Case on a day-to-day basis, while the Executive owns it.

1274
MCQeasy

Which role is ultimately accountable for the project's Business Case throughout the project?

A.Senior User
B.Senior Responsible Owner (Executive)
C.Senior Supplier
D.Project Manager
AnswerB

The SRO is accountable for the Business Case and its maintenance throughout the project.

Why this answer

The Senior Responsible Owner (Executive) is accountable for the Business Case, ensuring the project remains viable and aligned with organizational objectives.

1275
MCQeasy

Which document is used by the Project Manager to capture lessons learned during a stage?

A.Lessons Log
B.Checkpoint Report
C.End Stage Report
D.Lessons Report
AnswerA

The Lessons Log records lessons as they are identified.

Why this answer

The Lessons Log is used to capture lessons throughout the project, including during a stage.

Page 16

Page 17 of 24

Page 18