PRINCE2F PRINCE2 Practices Practice Question
A project is using the recommended risk management procedure. After identifying a risk, what is the next step?
Answer choices
Why each option matters
Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.
Correct answer & explanation
✓
Assess the risk
The recommended risk management procedure steps are: Identify, Assess, Plan, Implement, Communicate. So after Identify, the next step is Assess (evaluate probability and impact).
Answer analysis
Option-by-option breakdown
For each option: why learners choose it and why it is or isn't the right answer here.
- ✗
Plan responses
Why it's wrong here
Plan comes after Assess.
- ✗
Communicate the risk
Why it's wrong here
Communication occurs throughout, but the formal step after Identify is Assess.
- ✓
Assess the risk
Why this is correct
After identification, the risk is assessed in terms of probability and impact.
- ✗
Implement responses
Why it's wrong here
Implement comes after Plan.
Go deeper
Related to this question
About these practice questions
One of 1,599 original PRINCE2F practice questions on Courseiva, each with a full explanation and wrong-answer analysis — not exam dumps or protected exam content. Learn why practice questions differ from exam dumps →
JA
Written by Johnson Ajibi, MSc IT Security
Senior Network & Security Engineer · founder of Courseiva
This PRINCE2F practice question is part of Courseiva's free PeopleCert certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PRINCE2F exam.