Which TWO of the following are responsibilities of the Project Board in the Directing a Project process?
Correct. The Board authorizes stage plans and provides direction as needed.
Why this answer
The Project Board authorizes initiation, authorizes the project, authorizes stage plans, gives ad-hoc direction, and authorizes closure. They do not manage day-to-day work or produce Checkpoint Reports.