PRINCE2F PRINCE2 Processes Practice Question
During the Closing a Project process, which document is produced to capture lessons for future projects?
Answer choices
Why each option matters
Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.
Correct answer & explanation
✓
Lessons Report
The Lessons Report is produced during CP to document what went well and what could be improved, for the benefit of future projects.
Answer analysis
Option-by-option breakdown
For each option: why learners choose it and why it is or isn't the right answer here.
- ✗
Lessons Log
Why it's wrong here
The Lessons Log is maintained throughout; the Lessons Report is a summary at closure.
- ✓
Lessons Report
Why this is correct
The Lessons Report is created during CP.
- ✗
Project Plan
Why it's wrong here
Project Plan is updated in SB, not a closure document.
- ✗
End Project Report
Why it's wrong here
End Project Report summarises performance, but lessons are separate.
Go deeper
Related to this question
About these practice questions
Courseiva writes every PRINCE2F question from scratch — 1,599 in total, each with an explanation and a wrong-answer breakdown. None are copied from real exams or dumps. Learn why practice questions differ from exam dumps →
Same concept, more angles
2 more ways this is tested on PRINCE2F
These questions test the same concept from different angles. Work through them to make sure you can recognise it however the exam phrases it.
Variation 1. During the Closing a Project process, which document is produced to capture lessons for future projects?
medium- A.Project Product Description
- B.Benefits Management Approach
- C.End Project Report
- ✓ D.Lessons Report
Why D: The Lessons Report is produced during the Closing a Project process to capture lessons learned for future projects.
Variation 2. In the Closing a Project process, which document is produced to capture lessons learned for future projects?
medium- ✓ A.Lessons Report
- B.Project Product Description
- C.End Project Report
- D.Benefits Management Approach
Why A: The Lessons Report is produced during CP to document lessons for future benefit. The End Project Report also includes lessons, but the specific document for lessons is the Lessons Report.
JA
Written by Johnson Ajibi, MSc IT Security
Senior Network & Security Engineer · founder of Courseiva
This PRINCE2F practice question is part of Courseiva's free PeopleCert certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PRINCE2F exam.