Courseiva

CCNA PRINCE2 Processes Questions

75 of 479 questions · Page 4/7 · PRINCE2 Processes · Answers revealed

226
MCQeasy

Who is responsible for maintaining the Business Case throughout the project?

A.Team Manager
B.Project Manager
C.Executive
D.Senior User
AnswerC

The Executive is responsible for the Business Case.

Why this answer

The Executive (Senior Responsible Owner) owns the Business Case and ensures its ongoing viability.

227
Multi-Selectmedium

Which THREE of the following are components of the Project Initiation Documentation (PID)?

Select 3 answers
A.Daily Log
B.Project Plan
C.Risk Management Approach
D.Business Case
E.Checkpoint Report
AnswersB, C, D

The Project Plan is a mandatory component of the Project Initiation Documentation (PID) because it defines the detailed timing, cost, and resource baselines against which the project will be managed. In the PRINCE2 framework, the PID must contain the Project Plan to satisfy the "plans" theme, which requires a baseline for the project’s stage-level control and progress measurement.

Why this answer

The PID includes the Project Plan, Business Case, and Risk Management Approach. The Daily Log is a project log used throughout, not part of PID. The Checkpoint Report is a product of Managing Product Delivery.

228
MCQmedium

A Project Manager is reviewing progress during a stage and notices that the stage is on track. Which report should the Project Manager send to the Project Board?

A.Exception Report
B.End Stage Report
C.Checkpoint Report
D.Highlight Report
AnswerD

Highlight Reports are sent periodically by the Project Manager to the Project Board.

Why this answer

The Highlight Report is the correct choice because it is the PRINCE2 management product used to provide the Project Board with a summary of progress at regular intervals during a stage. Since the stage is on track and no issues or deviations require escalation, the Project Manager should send a Highlight Report to keep the Board informed, not an Exception or End Stage Report.

Exam trap

PeopleCert often tests the distinction between reports sent to the Project Board versus those used within the project management team, and the trap here is confusing the Checkpoint Report (team-to-PM) with the Highlight Report (PM-to-Board) when the question specifies the recipient is the Project Board.

How to eliminate wrong answers

Option A is wrong because an Exception Report is only used when a stage is forecast to exceed tolerance levels, which is not the case here as the stage is on track. Option B is wrong because an End Stage Report is produced at the end of a stage to summarize performance and request authorization for the next stage, not during a stage when progress is being reviewed. Option C is wrong because a Checkpoint Report is a team-level report from the Team Manager to the Project Manager, not a report sent from the Project Manager to the Project Board.

229
MCQeasy

Which process produces the End Project Report?

A.Closing a Project
B.Managing a Stage Boundary
C.Initiating a Project
D.Directing a Project
AnswerA

CP produces the End Project Report and Lessons Report.

Why this answer

Closing a Project includes producing the End Project Report, Lessons Report, and confirming benefits review arrangements.

230
MCQhard

What is the key difference between the Starting Up a Project (SU) and Initiating a Project (IP) processes?

A.SU is performed by the Project Board; IP is performed by the Project Manager
B.SU is optional; IP is mandatory
C.SU includes the creation of the Business Case; IP does not
D.SU produces the Project Brief; IP produces the Project Initiation Documentation (PID)
AnswerD

The Starting Up a Project process produces the Project Brief, which provides the baseline justification and scope for the project, while the Initiating a Project process produces the Project Initiation Documentation (PID), which refines that brief into a detailed, auditable plan and business case. This satisfies the stem’s requirement to identify the specific output-based constraint distinguishing the two processes.

Why this answer

The Starting Up a Project (SU) process produces the Project Brief, which outlines the project's scope and feasibility, while the Initiating a Project (IP) process produces the Project Initiation Documentation (PID), which provides a detailed plan and baseline for execution. This distinction is fundamental in PRINCE2 as SU focuses on pre-project preparation and IP on detailed planning and governance.

Exam trap

The trap here is that candidates confuse the outputs of SU and IP, often thinking the Business Case is only created in SU, when in fact it is outlined in SU and detailed in IP, making option C seem plausible but incorrect.

How to eliminate wrong answers

Option A is wrong because SU is performed by the Project Manager with input from the Executive, not the Project Board; the Project Board is involved in IP for approval, but the Project Manager performs both processes. Option B is wrong because both SU and IP are mandatory processes in PRINCE2; SU is not optional as it ensures the project is viable before initiation. Option C is wrong because the Business Case is developed during SU (as part of the Project Brief) and further refined in IP; both processes involve the Business Case, not just SU.

231
Multi-Selecthard

Which THREE of the following are activities performed during the Controlling a Stage process?

Select 3 answers
A.Review progress against the Stage Plan
B.Produce the Project Plan
C.Produce the End Stage Report
D.Authorize Work Packages
E.Manage issues and risks
AnswersA, D, E

Monitoring progress is a key activity in Controlling a Stage.

Why this answer

Authorizing Work Packages, reviewing progress, and managing risks and issues are key activities of Controlling a Stage. Producing the End Stage Report is done in Managing a Stage Boundary, and producing the Project Plan is done in Initiating a Project.

232
MCQmedium

A Project Manager receives a Checkpoint Report from a Team Manager. Which process is the Team Manager executing when producing this report?

A.Controlling a Stage
B.Managing a Stage Boundary
C.Directing a Project
D.Managing Product Delivery
AnswerD

The Team Manager produces Checkpoint Reports during Managing Product Delivery to report progress on Work Packages.

Why this answer

Checkpoint Reports are produced by Team Managers during the Managing Product Delivery process. They report progress on Work Package delivery. Controlling a Stage is the PM's process for managing the stage; Highlight Reports go from PM to Project Board.

Managing a Stage Boundary and Directing a Project do not involve Checkpoint Reports.

233
MCQhard

During the Controlling a Stage process, a Team Manager reports that a work package is complete. What is the next step for the Project Manager?

A.Inform the Project Board immediately
B.Close the project
C.Accept the completed work package and update the stage plan
D.Start planning the next stage immediately
AnswerC

The Project Manager accepts the completed products and updates the stage plan to reflect progress.

Why this answer

According to PRINCE2, when a Team Manager reports a work package as complete, the Project Manager must first accept the completed work package and then update the stage plan to reflect the actual progress. This ensures the stage plan remains accurate and provides a basis for assessing the impact on the project plan and any necessary corrective actions.

Exam trap

The trap here is that candidates often confuse the completion of a single work package with the end of a stage, leading them to incorrectly select options related to stage boundaries or project closure.

How to eliminate wrong answers

Option A is wrong because the Project Manager does not inform the Project Board immediately upon completion of a work package; the Board is only informed at stage boundaries or via exception reports. Option B is wrong because closing the project is a separate process (Closing a Project) that occurs only after all stages are complete and the project is formally closed. Option D is wrong because planning the next stage is part of the Managing a Stage Boundary process, which occurs at the end of a stage, not upon completion of a single work package within the current stage.

234
MCQhard

A Project Manager is reviewing progress during a stage and discovers that a Work Package is behind schedule. The Team Manager has not submitted a Checkpoint Report this week. What should the Project Manager do?

A.Close the Work Package and reassign the work to another team
B.Contact the Team Manager to understand the delay and agree corrective actions
C.Escalate the issue to the Project Board immediately via an Exception Report
D.Update the Project Plan to reflect the delay and inform the Project Board in the next Highlight Report
AnswerB

The PM should first assess the situation with the Team Manager and decide if corrective action within tolerance is possible.

Why this answer

The Project Manager should contact the Team Manager to understand the situation and take corrective action. This is part of the 'Review Work Package Status' activity in Controlling a Stage.

235
MCQmedium

A project is in the Initiating a Project process. Which of the following is produced during this process?

A.Benefits Management Approach
B.Project Brief
C.End Stage Report
D.Exception Report
AnswerA

This is created during IP as part of the PID.

Why this answer

The Benefits Management Approach is produced during the Initiating a Project process because it defines how the project's benefits will be measured, managed, and realized. This document is created as part of the detailed planning and governance setup that occurs in this process, ensuring alignment with the business case.

Exam trap

The trap here is that candidates confuse the Project Brief (produced in Starting Up a Project) with outputs of Initiating a Project, but PRINCE2 explicitly separates these processes to ensure the Project Brief is refined into the PID during initiation.

How to eliminate wrong answers

Option B is wrong because the Project Brief is created in the Starting Up a Project process, not in Initiating a Project; it provides the initial outline of the project's scope and justification. Option C is wrong because the End Stage Report is produced at the end of each management stage during the Managing a Stage Boundary process, not during initiation. Option D is wrong because the Exception Report is created during the Controlling a Stage process when a stage is forecast to exceed tolerances, not during initiation.

236
MCQmedium

The Project Manager receives a Highlight Report from the Project Board. Is this correct?

A.No, the Project Manager sends Highlight Reports to the Project Board
B.Yes, the Project Board uses Highlight Reports to direct the Project Manager
C.No, Highlight Reports are only used during the Initiating a Project process
D.Yes, the Project Board sends Highlight Reports to the Project Manager
AnswerA

Correct: The PM sends Highlight Reports to the Board.

Why this answer

In PRINCE2, the Highlight Report is a management product that is prepared by the Project Manager and sent to the Project Board. The purpose of the Highlight Report is to provide the Project Board with a summary of the project's progress at intervals defined in the Communication Management Strategy. Therefore, the statement that the Project Manager receives a Highlight Report from the Project Board is incorrect; the flow is from the Project Manager to the Project Board.

Exam trap

The trap here is that candidates may confuse the direction of communication, assuming the Project Board sends reports to the Project Manager, when in fact the Highlight Report is a bottom-up reporting mechanism from the Project Manager to the Project Board.

How to eliminate wrong answers

Option B is wrong because the Project Board does not use Highlight Reports to direct the Project Manager; direction is provided via other management products such as the Project Mandate or Project Brief, and the Highlight Report is an upward reporting mechanism. Option C is wrong because Highlight Reports are not limited to the Initiating a Project process; they are produced during the Managing a Stage Boundary and Controlling a Stage processes as part of ongoing stage management. Option D is wrong because the Project Board does not send Highlight Reports to the Project Manager; the Project Manager creates and sends them to the Project Board.

237
Multi-Selectmedium

Which TWO of the following reports are produced by the Project Manager during the Controlling a Stage process?

Select 2 answers
A.Lessons Report
B.Highlight Report
C.End Stage Report
D.Exception Report
E.Checkpoint Report
AnswersB, D

The Project Manager produces Highlight Reports during Controlling a Stage.

Why this answer

During Controlling a Stage, the Project Manager produces Highlight Reports and Exception Reports. Checkpoint Reports are produced by Team Managers during Managing Product Delivery. The End Stage Report is from Managing a Stage Boundary.

The Lessons Report is from Closing a Project.

238
MCQeasy

What is the purpose of the Starting Up a Project (SU) process?

A.To produce the Project Initiation Documentation (PID)
B.To ensure that there is a viable and worthwhile project before detailed planning begins
C.To authorize the initiation of the project
D.To produce the Benefits Management Approach
AnswerB

SU confirms the project is viable and worthwhile before committing to detailed initiation.

Why this answer

The Starting Up a Project (SU) process is designed to ensure that the project has a viable business justification and is worthwhile before committing significant resources. It answers the question 'Do we have a viable and worthwhile project?' by creating the Project Brief and selecting the Project Manager, not by producing detailed plans or the PID.

Exam trap

PeopleCert often tests the distinction between 'Starting Up a Project' and 'Initiating a Project' — candidates confuse the SU process (which produces the Project Brief) with the IP process (which produces the PID and detailed plans).

How to eliminate wrong answers

Option A is wrong because the Project Initiation Documentation (PID) is produced during the Initiating a Project (IP) process, not during Starting Up a Project (SU). Option C is wrong because authorizing the initiation of the project is the purpose of the Directing a Project (DP) process, specifically the 'Authorize Initiation' activity. Option D is wrong because the Benefits Management Approach is developed during the Initiating a Project (IP) process, not during SU.

239
MCQmedium

During which process is the Project Initiation Documentation (PID) created?

A.Directing a Project
B.Starting Up a Project
C.Initiating a Project
D.Managing a Stage Boundary
AnswerC

The PID is created during Initiating a Project.

Why this answer

The PID is the key output of Initiating a Project, which establishes solid foundations for the project.

240
Multi-Selecthard

Which THREE activities are part of the Initiating a Project process?

Select 3 answers
A.Prepare the Project Plan
B.Prepare the Risk Management Approach
C.Authorize the initiation stage
D.Appoint the project board and project manager
E.Assemble the Project Initiation Documentation
AnswersA, B, E

The Project Plan is developed during initiation.

Why this answer

Preparing the Project Plan is a key activity in the Initiating a Project process, where the detailed plan for the project is developed based on the Project Brief and the chosen strategy. This plan covers time, cost, quality, and scope, and is a core component of the Project Initiation Documentation (PID).

Exam trap

The trap here is that candidates confuse the activities of Starting up a Project (like authorizing the initiation stage and appointing roles) with those of Initiating a Project, which focuses on detailed planning and documentation.

241
MCQmedium

The Project Board receives a Highlight Report indicating that the stage is on track. However, a Team Manager has identified a potential risk that could impact the next stage. What should the Project Manager do?

A.Wait until the next stage to address the risk
B.Update the Project Plan to include the risk
C.Update the Risk Register and manage the risk as part of the current stage
D.Raise an Exception Report to the Project Board
AnswerC

Correct. Risks should be recorded and managed as they are identified, even if impact is in the future.

Why this answer

Risks are managed by the Project Manager. The risk should be added to the Risk Register and monitored. The Highlight Report is for reporting current stage progress; the risk can be mentioned but the immediate action is to record it.

242
MCQmedium

Which process is used by the Project Manager to prepare the End Stage Report and the next Stage Plan?

A.Controlling a Stage
B.Managing a Stage Boundary
C.Directing a Project
D.Closing a Project
AnswerB

Managing a Stage Boundary is the process through which the Project Manager produces the End Stage Report to summarise performance against the current Stage Plan, and simultaneously creates the next Stage Plan for the upcoming work package. This satisfies the constraint in the stem that both the report and the subsequent plan must be prepared within a single process, as the PRINCE2 method explicitly mandates these two outputs together at the boundary between stages.

Why this answer

The Managing a Stage Boundary process is where the Project Manager reviews the current stage, produces an End Stage Report, and creates the next Stage Plan (or Exception Plan) for the Project Board's approval.

243
MCQmedium

During which process are lessons for the project first recorded?

A.Initiating a Project
B.Managing a Stage Boundary
C.Starting Up a Project
D.Closing a Project
AnswerC

The Lessons Log is created in SU and populated with relevant lessons from previous projects.

Why this answer

In PRINCE2, the first formal recording of lessons occurs during the 'Starting Up a Project' process. This process includes the activity 'Capture Previous Lessons' (from the 'Learn from Experience' principle), where the project manager reviews lessons from similar previous projects and records them in the Lessons Log before the project is even initiated. This ensures that the project starts with the benefit of past experience.

Exam trap

The trap here is that candidates often confuse 'Initiating a Project' (where detailed planning and the PID are created) with the first recording of lessons, but PRINCE2 explicitly requires lessons to be captured before initiation begins, during the 'Starting Up a Project' process.

How to eliminate wrong answers

Option A is wrong because 'Initiating a Project' is where the Lessons Log is updated with lessons from the initiation stage itself, but the first recording of lessons happens earlier, in Starting Up a Project. Option B is wrong because 'Managing a Stage Boundary' is where lessons from the current stage are captured and reported, but this occurs after the project has already started and is not the first recording. Option D is wrong because 'Closing a Project' is where final lessons are formally documented and the Lessons Log is completed, but this is the last recording, not the first.

244
MCQhard

In the Starting Up a Project process, the project manager is appointed. Who appoints the project manager?

A.The project board
B.The senior user
C.The executive
D.The senior supplier
AnswerC

Correct. The Executive appoints the Project Manager.

Why this answer

According to PRINCE2, the Executive appoints the project manager during SU. The Executive is the key decision-maker for this appointment.

245
Multi-Selectmedium

Which TWO outputs are produced during the Initiating a Project process?

Select 2 answers
A.Project Initiation Documentation (PID)
B.Benefits Management Approach
C.Project Brief
D.Work Package
E.End Stage Report
AnswersA, B

PID is the key output of Initiating a Project.

Why this answer

The PID and Benefits Management Approach are both produced in IP. The Project Brief is from SU, and the End Stage Report is from SB.

246
MCQeasy

What is the key output of the Starting Up a Project process?

A.End Project Report
B.Benefits Management Approach
C.Project Brief
D.Project Initiation Documentation
AnswerC

SU produces the Project Brief.

Why this answer

The Starting Up a Project process is the first process in PRINCE2, executed before project initiation. Its key output is the Project Brief, which provides a high-level overview of the project's justification, scope, and approach, enabling the project board to decide whether to proceed to the Initiation Stage. The Project Brief is derived from the project mandate and is used to create the Project Initiation Documentation later.

Exam trap

The trap here is that candidates often confuse the Project Brief with the Project Initiation Documentation, mistakenly thinking the latter is the first key output, but PRINCE2 explicitly separates these two documents across different processes.

How to eliminate wrong answers

Option A is wrong because the End Project Report is an output of the Closing a Project process, not Starting Up a Project. Option B is wrong because the Benefits Management Approach is developed during the Initiating a Project process, not Starting Up a Project. Option D is wrong because the Project Initiation Documentation is the key output of the Initiating a Project process, which occurs after Starting Up a Project has been completed and the project board has authorized initiation.

247
Multi-Selecteasy

Which TWO of the following are outputs of the Starting Up a Project process?

Select 2 answers
A.Initiation Stage Plan
B.Project Brief
C.Benefits Management Approach
D.Project Initiation Documentation (PID)
E.End Stage Report
AnswersA, B

Correct. The plan for the initiation stage is produced in SU.

Why this answer

The Starting Up a Project process is the pre-project phase where the project board is appointed, the project brief is created, and the initiation stage plan is produced. The Initiation Stage Plan (A) is a direct output because it details the activities, resources, and controls needed for the initiation stage itself, enabling the project board to authorize the next process. The Project Brief (B) is also an output as it captures the initial business justification, scope, and approach, forming the basis for the project mandate and subsequent detailed planning.

Exam trap

The trap here is that candidates often confuse the Project Brief (output of Starting Up a Project) with the Project Initiation Documentation (PID) (output of Initiating a Project), or mistakenly think the Benefits Management Approach is created early, when it is actually developed during initiation.

248
MCQhard

A Work Package is being executed. The Team Manager discovers a product cannot meet its quality criteria due to an unforeseen technical limitation. What should the Team Manager do?

A.Directly inform the Project Board
B.Raise an issue to the Project Manager
C.Proceed with the work and accept the lower quality
D.Update the Work Package and continue
AnswerB

The Team Manager should report the issue so that the Project Manager can decide on appropriate action.

Why this answer

The Team Manager should raise an issue (or off-specification) to the Project Manager via the MP process. The Project Manager will then decide on corrective action or escalation.

249
Multi-Selectmedium

Which TWO of the following are produced during the Starting Up a Project process?

Select 2 answers
A.Initiation Stage Plan
B.Benefits Management Approach
C.End Project Report
D.Project Brief
E.Project Initiation Documentation
AnswersA, D

Correct: The plan for the initiation stage is created in SU.

Why this answer

SU produces the Project Brief and the Initiation Stage Plan. The PID and End Project Report are produced later.

250
MCQeasy

Which document is the key output of the Initiating a Project process?

A.End Stage Report
B.Exception Report
C.Project Brief
D.Project Initiation Documentation (PID)
AnswerD

The PID is the key document produced during IP.

Why this answer

The Initiating a Project process is where the project's baselines are established, and its key output is the Project Initiation Documentation (PID). The PID consolidates all essential information—such as the Business Case, project plan, risk register, and project controls—into a single, approved document that defines what the project will deliver and how it will be managed. This document is the foundation for decision-making and is used throughout the project.

Exam trap

PeopleCert often tests the distinction between the Project Brief (an input from Starting Up a Project) and the Project Initiation Documentation (the key output of Initiating a Project), so candidates mistakenly select the Project Brief thinking it is the main deliverable of the initiation phase.

How to eliminate wrong answers

Option A is wrong because the End Stage Report is produced at the end of each management stage (including the final stage) to report on progress against the plan, not as an output of Initiating a Project. Option B is wrong because the Exception Report is created when a project is forecast to exceed its tolerances, triggering an exception management process, and is not a deliverable of the initiation phase. Option C is wrong because the Project Brief is actually an input to the Initiating a Project process (created during Starting Up a Project), not its key output; the PID refines and replaces the Project Brief.

251
MCQmedium

A project is in the Initiating a Project process. Which management product defines how the project will be controlled?

A.Business Case
B.Project Plan
C.Project Initiation Documentation
D.Stage Plan
AnswerC

Why this answer

The PID contains all the approaches (risk, quality, change, communication) and the Project Plan, defining how the project will be controlled. The Project Plan is a component of the PID, but PID is the overall management product. Stage Plan is more detailed for a stage.

Business Case justifies viability.

252
MCQeasy

Which process covers the day-to-day management of a stage by the Project Manager?

A.Managing a Stage Boundary
B.Directing a Project
C.Managing Product Delivery
D.Controlling a Stage
AnswerD

Why this answer

The Controlling a Stage (CS) process covers the day-to-day management activities of the Project Manager within a stage.

253
MCQmedium

A project is in the Initiating a Project process. Which document is the key output of this process?

A.End Stage Report
B.Lessons Report
C.Project Brief
D.Project Initiation Documentation
AnswerD

The PID is the definitive document produced during Initiating a Project.

Why this answer

The Project Initiation Documentation (PID) is the key output of Initiating a Project. It brings together all the information needed to justify the project and define its scope.

254
MCQmedium

The Project Board is reviewing the End Stage Report and the next Stage Plan. Which process are they performing?

A.Closing a Project
B.Managing a Stage Boundary
C.Controlling a Stage
D.Directing a Project
AnswerD

DP includes the activity of authorizing a stage plan.

Why this answer

The Project Board reviews stage-end reports and decides whether to authorize the next stage. This is part of Directing a Project (DP). The PM produces the End Stage Report and next Stage Plan during Managing a Stage Boundary (SB).

255
MCQmedium

During the Controlling a Stage process, the Project Manager needs to assign work to a team. What should the Project Manager create?

A.Work Package
B.Team Plan
C.Project Plan
D.Product Description
AnswerA

A Work Package is the set of instructions for the team to produce one or more products.

Why this answer

The Project Manager authorizes work by issuing a Work Package to the Team Manager.

256
MCQeasy

Who is responsible for authorising the initiation of a project?

A.Project Board
B.Executive
C.Corporate management
D.Project Manager
AnswerA

The Project Board authorises initiation via DP.

Why this answer

In PRINCE2, the Project Board is collectively responsible for authorizing the initiation of a project. This decision is made during the 'Directing a Project' process, where the Project Board reviews the Project Brief and decides whether to proceed to the Initiation Stage. The Project Board's authority is derived from the corporate or programme management, but the actual authorization to initiate is a board-level responsibility.

Exam trap

The trap here is that candidates often confuse the Executive's role as the single decision-maker with the collective responsibility of the Project Board, leading them to select 'Executive' instead of 'Project Board'.

How to eliminate wrong answers

Option B is wrong because the Executive is a single role on the Project Board, not the sole authority for authorizing initiation; the Project Board as a whole must agree. Option C is wrong because corporate or programme management provides the mandate and high-level direction but does not directly authorize initiation—they delegate this to the Project Board. Option D is wrong because the Project Manager manages the project on a day-to-day basis and does not have the authority to authorize initiation; they prepare the initiation documentation for the Project Board's approval.

257
Multi-Selecthard

Which THREE of the following are responsibilities of the Project Manager during the Controlling a Stage process?

Select 3 answers
A.Authorize Work Packages
B.Review the progress of work packages
C.Produce the Project Plan
D.Produce the Stage Plan for the next stage
E.Manage issues and risks
AnswersA, B, E

The PM authorizes work packages in CS.

Why this answer

The PM authorizes Work Packages, monitors progress, and manages issues and risks. Producing the next stage plan is done in SB, and producing the Project Plan is done in IP.

258
Multi-Selectmedium

Which TWO of the following statements about the Directing a Project process are correct?

Select 2 answers
A.It is performed by the Project Board
B.It includes producing Highlight Reports
C.It includes the day-to-day management of the project
D.It includes authorizing the initiation of the project
E.It is performed only at the start and end of the project
AnswersA, D

DP is the Project Board's process.

Why this answer

DP is performed by the Project Board and runs throughout the project. The Project Board gives direction and authorizes key decisions but does not manage day-to-day. The PM manages day-to-day in CS.

259
Multi-Selectmedium

Which TWO of the following are outputs of the Starting Up a Project process?

Select 2 answers
A.Project Initiation Documentation
B.End Stage Report
C.Project Brief
D.Benefits Management Approach
E.Initiation Stage Plan
AnswersC, E

The Project Brief is formally created during the Starting Up a Project process to provide a firm foundation for the initiation stage. It consolidates the outline business case, project product description, and project approach, satisfying the constraint that the project board must have sufficient information to authorise initiation. Without this output, the board cannot evaluate whether the project is viable before committing resources.

Why this answer

The Starting Up a Project process is the pre-project phase where the project is evaluated for viability before full initiation. Its key outputs include the Project Brief, which outlines the project's scope, objectives, and approach, and the Initiation Stage Plan, which details the work needed to produce the Project Initiation Documentation. These two outputs are formally defined in PRINCE2 as products of this process.

Exam trap

A common trap in PRINCE2 exams is confusing the outputs of Starting Up a Project (pre-project) with those of Initiating a Project. Specifically, the Project Brief and Initiation Stage Plan are produced in Starting Up a Project, while the Project Initiation Documentation and Benefits Management Approach are created later during the Initiating a Project process.

260
Multi-Selectmedium

Which TWO of the following are responsibilities of the Project Board?

Select 2 answers
A.Manage day-to-day activities
B.Authorize the Project Plan
C.Produce Checkpoint Reports
D.Authorize the start of each stage
E.Update the Daily Log
AnswersB, D

The board approves the Project Plan.

Why this answer

The Project Board is responsible for overall project governance, including authorizing the Project Plan (which defines the project's scope, cost, and schedule) and authorizing the start of each management stage. These decisions ensure the project remains aligned with business objectives and that stage boundaries are properly controlled.

Exam trap

PeopleCert often tests the distinction between strategic governance (Project Board) and operational management (Project Manager), so candidates mistakenly assign day-to-day tasks like updating logs or producing reports to the board.

261
MCQhard

During a stage, a Team Manager identifies a quality problem with a product. The product fails its quality inspection. What should the Team Manager do?

A.Proceed with delivery and inform the Project Manager in the next Checkpoint Report
B.Reject the Work Package and stop all work
C.Raise an Exception Report directly to the Project Board
D.Raise an Issue Report to the Project Manager
AnswerD

The Team Manager should raise an Issue Report (Off-specification) to the PM via the CS process.

Why this answer

According to PRINCE2, if a product fails its quality inspection, the Team Manager should raise an Issue Report (specifically, an Off-specification) to the Project Manager. The PM then decides how to handle it. Option D is correct; Option B is wrong because the Team Manager should not bypass the PM.

262
Multi-Selectmedium

Which TWO of the following are outputs of the Starting Up a Project process?

Select 2 answers
A.Project Initiation Documentation
B.Benefits Management Approach
C.Daily Log
D.End Stage Report
E.Project Brief
AnswersC, E

Yes, Daily Log is created in SU.

Why this answer

SU produces the Project Brief, Daily Log, and Initiation Stage Plan. PID is from IP.

263
MCQmedium

During which process is the Benefits Management Approach first produced?

A.Managing a Stage Boundary
B.Closing a Project
C.Initiating a Project
D.Starting Up a Project
AnswerC

IP produces all management approaches, including Benefits Management Approach.

Why this answer

The Benefits Management Approach is first produced during the Initiating a Project process, as it forms part of the Project Initiation Documentation (PID). Options A, B, and D are incorrect: Managing a Stage Boundary reviews and may update the approach, Closing a Project evaluates benefits, and Starting Up a Project does not create it.

264
MCQeasy

Which process is the Project Board's primary process for making key decisions?

A.Starting Up a Project
B.Managing a Stage Boundary
C.Directing a Project
D.Controlling a Stage
AnswerC

Correct: DP covers all key decision points for the Project Board.

Why this answer

Directing a Project (DP) is the process used by the Project Board to authorize initiation, stage plans, exception plans, and closure.

265
MCQmedium

During the Controlling a Stage process, the Project Manager receives a Highlight Report from a Team Manager. What should the Project Manager do with this information?

A.File the report and take no further action
B.Escalate any deviations immediately to the Project Board via an Exception Report
C.Review the report and use it to update the Stage Plan and produce the next Highlight Report for the Project Board
D.Forward the report directly to the Project Board as the next Highlight Report
AnswerC

Correct. The Project Manager uses Checkpoint Reports (and Highlight Reports from Team Managers) to monitor progress and report to the Board.

Why this answer

The Project Manager uses the Controlling a Stage process to monitor progress, review Highlight Reports, and report to the Project Board via Highlight Reports.

266
MCQmedium

During the Closing a Project process, which document is produced to capture lessons for future projects?

A.Lessons Log
B.Lessons Report
C.Project Plan
D.End Project Report
AnswerB

The Lessons Report is created during CP.

Why this answer

The Lessons Report is produced during CP to document what went well and what could be improved, for the benefit of future projects.

267
MCQmedium

Who is responsible for authorising the initiation of a project?

A.Project Manager
B.Team Manager
C.Project Board
D.Senior User
AnswerC

Why this answer

The Project Board (in the Directing a Project process) is responsible for authorising project initiation, as well as authorising the project itself.

268
MCQmedium

During the Managing Product Delivery process, what does the Team Manager produce to inform the Project Manager of progress?

A.Exception Report
B.Checkpoint Report
C.End Stage Report
D.Highlight Report
AnswerB

Correct. Checkpoint Reports are produced by the Team Manager.

Why this answer

In PRINCE2, the Team Manager produces a Checkpoint Report during the Managing Product Delivery process to inform the Project Manager of progress at a regular, predefined frequency. This report provides a snapshot of actual progress against the Work Package plan, including achievements, next steps, and any issues or risks. It is the primary mechanism for the Team Manager to communicate status to the Project Manager within this process.

Exam trap

The trap here is that candidates often confuse the Checkpoint Report (produced by the Team Manager) with the Highlight Report (produced by the Project Manager), as both report progress but at different levels and to different audiences.

How to eliminate wrong answers

Option A is wrong because an Exception Report is produced by the Project Manager (not the Team Manager) to escalate a deviation that exceeds tolerance thresholds to the Project Board. Option C is wrong because an End Stage Report is produced by the Project Manager at the end of a management stage to summarize performance and is not part of the Managing Product Delivery process. Option D is wrong because a Highlight Report is produced by the Project Manager to inform the Project Board of progress between stage boundaries, not by the Team Manager during product delivery.

269
MCQmedium

A Team Manager sends a Checkpoint Report to the Project Manager. Which process is the Team Manager executing?

A.Managing Product Delivery
B.Managing a Stage Boundary
C.Controlling a Stage
D.Directing a Project
AnswerA

MP includes Checkpoint Reports.

Why this answer

The Team Manager is executing the 'Managing Product Delivery' process because this process controls the work of the team, including the creation and delivery of products. A key activity within this process is the production of Checkpoint Reports, which provide the Project Manager with progress updates on the work assigned to the team. The Checkpoint Report is a formal PRINCE2 management product that is specifically defined as an output of the 'Managing Product Delivery' process.

Exam trap

The trap here is that candidates often confuse the process that produces the Checkpoint Report (Managing Product Delivery) with the process that receives and uses it (Controlling a Stage), leading them to incorrectly select 'Controlling a Stage'.

How to eliminate wrong answers

Option B is wrong because 'Managing a Stage Boundary' is executed by the Project Manager, not the Team Manager, and its outputs include End Stage Reports and Exception Reports, not Checkpoint Reports. Option C is wrong because 'Controlling a Stage' is executed by the Project Manager to monitor and control the stage, and while it receives Checkpoint Reports, it does not produce them. Option D is wrong because 'Directing a Project' is executed by the Project Board, not the Team Manager, and its focus is on high-level decision-making and authorization, not on producing operational progress reports like Checkpoint Reports.

270
MCQhard

During the Closing a Project process, the Project Manager produces a Lessons Report. What should happen to this report?

A.It should be filed in the project records and not reviewed
B.It should be published to the organization's lessons database
C.It should be destroyed to maintain confidentiality
D.It should be passed to the Executive for personal use
AnswerB

Lessons are recorded and shared to improve future projects.

Why this answer

The Lessons Report is used to inform future projects and improve organizational project management. It should be shared with the relevant stakeholders and added to the organizational lessons database. It is not just filed or destroyed.

271
MCQmedium

What is the main difference between the Starting Up a Project process and the Initiating a Project process?

A.SU is done by the Project Manager; IP is done by the Project Board
B.SU includes risk management; IP does not
C.SU creates the Project Brief; IP creates the Project Initiation Documentation
D.SU is optional; IP is mandatory
AnswerC

Correct. SU produces a high-level brief; IP produces detailed PID.

Why this answer

SU is a pre-project process to determine if the project is viable and worth initiating, while IP formally establishes the project foundation with detailed plans.

272
MCQmedium

The Project Board has authorized the project and the first stage. Which process is used by the Project Manager to manage the work of the first stage?

A.Initiating a Project
B.Controlling a Stage
C.Managing a Stage Boundary
D.Managing Product Delivery
AnswerB

CS is used by the PM to manage the stage.

Why this answer

After the Project Board authorizes the project and the first stage, the Project Manager uses the Controlling a Stage process to assign work, monitor progress, handle issues, and report to the Board throughout the stage. This process governs the day-to-day management of the stage and ensures it stays within tolerance.

Exam trap

The trap here is confusing the Project Manager's role in Controlling a Stage with the Team Manager's role in Managing Product Delivery, or assuming that Initiating a Project continues into the first stage.

How to eliminate wrong answers

Option A is wrong because Initiating a Project is used to create the Project Initiation Documentation and plan the project, not to manage the work of an authorized stage. Option C is wrong because Managing a Stage Boundary is used to prepare the next stage plan and update the business case at the end of a stage, not to manage ongoing work. Option D is wrong because Managing Product Delivery is the process used by the Team Manager to accept and deliver work packages, not by the Project Manager to manage the stage.

273
MCQmedium

During which process does the Project Manager produce a Highlight Report for the Project Board?

A.Controlling a Stage
B.Managing a Stage Boundary
C.Starting Up a Project
D.Managing Product Delivery
AnswerA

Highlight Reports are produced by the PM in CS to inform the Project Board.

Why this answer

The Controlling a Stage process includes producing Highlight Reports at intervals defined by the Project Board. Managing Product Delivery produces Checkpoint Reports from the Team Manager to the PM. Managing a Stage Boundary produces End Stage Reports.

Starting Up a Project does not produce Highlight Reports.

274
Multi-Selecthard

Which TWO of the following are true about the Managing Product Delivery process?

Select 2 answers
A.It produces Highlight Reports for the Project Board
B.It is performed by the Project Manager
C.It includes the acceptance of Work Packages
D.It produces End Stage Reports
E.It produces Checkpoint Reports for the Project Manager
AnswersC, E

Correct. Team Managers accept Work Packages in this process.

Why this answer

Managing Product Delivery is the process where Team Managers accept Work Packages, execute them, and deliver products. Checkpoint Reports are produced by Team Managers for the Project Manager. Highlight Reports are produced by the PM, and End Stage Reports are produced in Managing a Stage Boundary.

275
Multi-Selectmedium

Which TWO of the following are outputs of the Initiating a Project process?

Select 2 answers
A.End Project Report
B.Lessons Report
C.Project Brief
D.Project Initiation Documentation
E.Stage Plan for the next stage
AnswersD, E

Key output of IP.

Why this answer

The Initiating a Project process produces the Project Initiation Documentation (PID), which is the definitive document that defines the project's scope, objectives, and approach. It also produces the Stage Plan for the next stage, which details the work, resources, and controls for the first management stage. These are mandatory outputs that enable the Project Board to authorize the project to proceed.

Exam trap

PeopleCert often tests the confusion between the Project Brief (an input from Starting Up a Project) and the Project Initiation Documentation (an output of Initiating a Project), leading candidates to incorrectly select the Project Brief as an output.

276
MCQhard

In the Managing Product Delivery process, who produces the Checkpoint Report?

A.The Project Manager
B.The Team Manager
C.The Project Board
D.The Senior User
AnswerB

The Team Manager produces Checkpoint Reports during MP.

Why this answer

The Team Manager (or Team Member acting on behalf of the Team Manager) produces Checkpoint Reports to inform the Project Manager of progress against the Work Package. The Project Manager produces Highlight Reports. The Project Board receives Highlight Reports.

The Senior User is a Project Board role.

277
MCQmedium

In the Managing Product Delivery process, who is responsible for producing Checkpoint Reports?

A.The Project Support
B.The Project Board
C.The Team Manager
D.The Project Manager
AnswerC

The Team Manager produces Checkpoint Reports to report progress on Work Packages.

Why this answer

In PRINCE2, the Checkpoint Report is produced by the Team Manager to inform the Project Manager of progress on Work Packages. The Team Manager (or the team) prepares these reports at intervals defined in the Work Package. The Project Manager receives them, not the Project Board.

Therefore, option C is correct.

278
MCQeasy

Who is responsible for approving the End Project Report?

A.Senior Supplier
B.Project Manager
C.Project Board
D.Senior User
AnswerC

The Project Board approves the End Project Report and authorizes closure.

Why this answer

The Project Board, through the Directing a Project process, approves the End Project Report and authorizes project closure.

279
MCQmedium

Which document is produced in the Initiating a Project process and provides a baseline for the project?

A.End Stage Report
B.Project Brief
C.Project Initiation Documentation
D.Lessons Report
AnswerC

Correct. The PID is the definitive document for the project.

Why this answer

The Project Initiation Documentation (PID) is the key output of Initiating a Project. It provides the foundation for project management and includes the Project Plan, Business Case, and management approaches.

280
MCQhard

In which process does the Project Manager prepare an Exception Plan?

A.Initiating a Project
B.Directing a Project
C.Managing a Stage Boundary
D.Controlling a Stage
AnswerC

SB includes the activity to produce an Exception Plan if requested by the Project Board.

Why this answer

The Exception Plan is prepared by the Project Manager in the Managing a Stage Boundary process when a stage is forecast to exceed its tolerances. This process allows the Project Manager to present options to the Project Board, including an Exception Plan to replace the current stage plan, ensuring continued control within agreed tolerances.

Exam trap

The trap here is that candidates confuse the preparation of an Exception Plan with the Controlling a Stage process, where issues are first identified, but the actual plan creation occurs only at the stage boundary when tolerances are breached.

How to eliminate wrong answers

Option A is wrong because Initiating a Project focuses on establishing the project's foundation, such as the Project Brief and Initiation Stage Plan, not on handling exceptions that arise during stage execution. Option B is wrong because Directing a Project is the Project Board's process for making key decisions and authorizing plans, not for preparing detailed Exception Plans, which is a management-level activity. Option D is wrong because Controlling a Stage involves day-to-day management of work and issue handling within a stage, but preparing an Exception Plan requires escalating beyond stage tolerances, which is done at the stage boundary.

281
Multi-Selectmedium

Which THREE of the following are responsibilities of the Project Board during the Directing a Project process?

Select 3 answers
A.Authorize initiation
B.Authorize project closure
C.Produce Highlight Reports
D.Manage day-to-day work
E.Authorize Stage Plans
AnswersA, B, E

The Project Board decides whether to initiate the project.

Why this answer

The Project Board must authorize initiation to allow the project to proceed from the Starting Up a Project process into the Initiation Stage. This formal approval ensures that sufficient resources are committed and that the project aligns with corporate or programme strategy before detailed planning begins.

Exam trap

PeopleCert often tests the distinction between strategic (Board) and operational (Project Manager) responsibilities, so candidates mistakenly assign Highlight Reports or day-to-day management to the Board instead of the Project Manager.

282
Multi-Selectmedium

Which TWO statements about the Managing Product Delivery process are correct?

Select 2 answers
A.It is the process where the project manager assigns work packages to team managers.
B.It is the process where the project board reviews the Business Case.
C.It is the process where the team manager ensures that work is completed according to quality criteria.
D.It is the process where the project manager authorizes work packages.
E.It is the process where the Stage Plan is created for the next stage.
AnswersA, C

Assigning work packages is a key activity in this process.

Why this answer

The Managing Product Delivery process is where the Project Manager assigns work packages to Team Managers. This process focuses on the acceptance, execution, and delivery of work packages, ensuring that the team manager receives clear requirements and acceptance criteria. It bridges the gap between the Project Manager's planning and the team's execution.

Exam trap

The trap here is confusing the assignment of work packages (Managing Product Delivery) with their authorization (Controlling a Stage), leading candidates to incorrectly select Option D as correct.

283
Multi-Selectmedium

Which TWO activities are part of the Closing a Project process?

Select 2 answers
A.Create the project plan.
B.Plan the next stage.
C.Evaluate the project and document lessons learned.
D.Prepare the End Project Report.
E.Approve work packages.
AnswersC, D

This is part of Closing a Project.

Why this answer

Evaluating the project and documenting lessons learned is a key activity in the Closing a Project process, as it captures knowledge for future projects. Option D is correct because preparing the End Project Report is also a mandatory activity in this process, providing a final assessment of project performance against the business case and plans.

Exam trap

PeopleCert often tests the distinction between the Closing a Project process and other processes like Managing a Stage Boundary or Controlling a Stage, so candidates may confuse activities that occur at stage boundaries (e.g., planning the next stage) with those that finalize the entire project.

284
MCQeasy

In the Managing Product Delivery process, who is responsible for producing Checkpoint Reports?

A.Project Manager
B.Team Manager
C.Senior User
D.Project Board
AnswerB

Correct. The Team Manager produces Checkpoint Reports.

Why this answer

In PRINCE2, the Team Manager is responsible for producing Checkpoint Reports during the Managing Product Delivery process. These reports provide the Project Manager with progress updates on work package execution at a frequency defined in the Work Package. The Team Manager uses the Checkpoint Report to communicate completed products, next steps, and any issues or risks to the Project Manager.

Exam trap

In PRINCE2, a common exam trap is confusing who produces Checkpoint Reports (Team Manager) with who produces Highlight Reports (Project Manager).

How to eliminate wrong answers

Option A is wrong because the Project Manager receives Checkpoint Reports but does not produce them; they are responsible for producing Highlight Reports for the Project Board. Option C is wrong because the Senior User is a role on the Project Board focused on defining user requirements and benefits, not on operational progress reporting from delivery teams. Option D is wrong because the Project Board is the decision-making body that receives End Stage Reports and Highlight Reports, not Checkpoint Reports, which are internal to the delivery level.

285
MCQeasy

Which process is responsible for authorising the initiation of a project?

A.Starting Up a Project
B.Controlling a Stage
C.Initiating a Project
D.Directing a Project
AnswerD

DP includes the decision to authorise initiation based on the Project Brief.

Why this answer

The Directing a Project process is the Project Board’s process, which includes authorising initiation, the project itself, stage plans, and closure.

286
MCQeasy

What is the purpose of the Starting Up a Project process?

A.To monitor the progress of the current stage
B.To ensure that the prerequisites for initiating a project are in place
C.To close the project in a controlled manner
D.To approve the project and authorize initiation
AnswerB

SU ensures that the project is viable and that the necessary roles and plans are ready before initiation.

Why this answer

Starting Up a Project is a pre-project process to ensure that the project has a viable Business Case and that the necessary resources and people are in place before initiation. It does not approve, close, or monitor the project.

287
MCQmedium

During the Controlling a Stage process, the Project Manager receives a Checkpoint Report from the Team Manager. What should the Project Manager do with this report?

A.File it as a record and take no further action
B.Return it to the Team Manager for corrections
C.Use it to review progress and produce the Highlight Report
D.Forward it directly to the Project Board without review
AnswerC

Checkpoint Reports feed into the PM's review of stage progress and the creation of the Highlight Report.

Why this answer

Checkpoint Reports provide progress information on Work Packages. The Project Manager uses them to review progress, update the stage status, and produce the Highlight Report for the Project Board. Option C is correct.

288
MCQmedium

Who produces Checkpoint Reports?

A.Team Manager
B.Project Manager
C.Project Support
D.Senior User
AnswerA

The Team Manager produces Checkpoint Reports to inform the PM of progress.

Why this answer

Checkpoint Reports are produced by the Team Manager (or the person managing the Work Package) and are sent to the Project Manager. They provide progress on the Work Package.

289
MCQeasy

Which document is the key output of the Initiating a Project process?

A.Project Initiation Documentation
B.Project Brief
C.End Stage Report
D.Exception Report
AnswerA

The PID is the comprehensive document created during IP.

Why this answer

The Initiating a Project process produces the Project Initiation Documentation (PID) as its key output. The PID consolidates all the information needed to justify the project, define its scope, and establish the baselines for plans, risks, and controls. It is the definitive document that authorizes the project to proceed into the Delivery Stages.

Exam trap

PRINCE2 exams often test the distinction between the Project Brief (created in Starting Up a Project) and the Project Initiation Documentation (created in Initiating a Project), leading candidates to confuse the two outputs.

How to eliminate wrong answers

Option B (Project Brief) is wrong because the Project Brief is created during the Starting Up a Project process, not Initiating a Project; it provides the initial outline but is refined into the PID. Option C (End Stage Report) is wrong because it is produced at the end of each management stage (including the final stage) to report performance against the PID, not as an output of initiation. Option D (Exception Report) is wrong because it is created during the Controlling a Stage process when a stage is forecast to exceed tolerances, not during initiation.

290
MCQeasy

Which process is triggered when the Project Manager identifies that a stage tolerance is forecast to be exceeded?

A.Starting Up a Project
B.Controlling a Stage
C.Managing Product Delivery
D.Directing a Project
AnswerB

In Controlling a Stage, the Project Manager monitors progress and raises an Exception Report when tolerances are forecast to be exceeded.

Why this answer

The Exception Plan is produced during Managing a Stage Boundary, but the initial identification and escalation occur in Controlling a Stage, where the Exception Report is raised.

291
Multi-Selectmedium

Which TWO of the following are outputs of the Closing a Project process?

Select 2 answers
A.Business Case
B.Project Plan
C.End Project Report
D.Stage Plan
E.Lessons Report
AnswersC, E

The End Project Report summarizes the project and recommends closure.

Why this answer

Closing a Project produces the End Project Report and the Lessons Report.

292
MCQmedium

Who is responsible for authorizing the initiation of a project?

A.Project Manager
B.Executive
C.Senior User
D.Project Board
AnswerD

Correct. The Project Board authorizes initiation.

Why this answer

The Project Board is responsible for authorizing initiation during the Directing a Project process. The Project Manager recommends, but the Board decides.

293
MCQmedium

A project manager is planning a project and needs to decide at which point the project board should approve the project's initiation. According to PRINCE2, which process is responsible for obtaining approval to proceed with the initiation stage?

A.Initiating a Project
B.Starting up a Project
C.Managing a Stage Boundary
D.Directing a Project
AnswerD

This process authorizes initiation after reviewing the project mandate.

Why this answer

In PRINCE2, the 'Directing a Project' process is responsible for the project board's key decision-making activities, including authorizing project initiation. The project board must approve the initiation stage before the project manager can proceed with detailed planning. This approval is obtained during the 'Directing a Project' process, not during the 'Starting up a Project' or 'Initiating a Project' processes.

Exam trap

The trap here is that candidates often confuse the 'Starting up a Project' process (which creates the Project Brief and appoints the board) with the actual approval to initiate, but PRINCE2 explicitly separates the creation of the brief (Starting up) from the board's authorization to proceed with detailed planning (Directing a Project).

How to eliminate wrong answers

Option A is wrong because 'Initiating a Project' is the process where the project manager creates the Project Initiation Documentation (PID) and detailed plans, but it does not include the board's approval to start initiation; that approval comes from the board via the 'Directing a Project' process. Option B is wrong because 'Starting up a Project' is the pre-project process that produces the Project Brief and appoints the project board, but it does not include the board's approval to proceed with the initiation stage; that approval is a separate decision made after the project board reviews the Project Brief. Option C is wrong because 'Managing a Stage Boundary' is used to request approval to proceed to the next stage after the current one, not to approve the initiation stage itself; initiation stage approval is a one-time event at the start of the project.

294
MCQeasy

Which process includes the activity 'Authorize a Work Package'?

A.Managing Product Delivery
B.Controlling a Stage
C.Initiating a Project
D.Directing a Project
AnswerB

In CS, the PM authorizes Work Packages to the Team Manager.

Why this answer

Authorizing a Work Package is an activity performed by the Project Manager in the Controlling a Stage process.

295
MCQeasy

During which process does the Project Manager produce a Highlight Report?

A.Managing Product Delivery
B.Managing a Stage Boundary
C.Controlling a Stage
D.Directing a Project
AnswerC

Highlight Reports are a key output of CS.

Why this answer

The Highlight Report is produced during the Controlling a Stage process to provide the Project Board with a summary of progress against the stage plan. The Project Manager creates this report at a frequency defined in the Communication Management Approach, typically to report on achievements, planned activities, and any issues or risks.

Exam trap

The trap here is confusing the process that produces the report (Controlling a Stage) with the process that receives it (Directing a Project), leading candidates to incorrectly select D.

How to eliminate wrong answers

Option A is wrong because Managing Product Delivery focuses on the Team Manager's work to create specialist products and does not involve the Project Manager producing a Highlight Report. Option B is wrong because Managing a Stage Boundary is where the Project Manager produces an End Stage Report and a Plan for the next stage, not a Highlight Report. Option D is wrong because Directing a Project is the Project Board's process for making key decisions and receiving reports like the Highlight Report, not for producing them.

296
MCQmedium

Who is responsible for producing Checkpoint Reports?

A.Project Manager
B.Team Manager
C.Project Assurance
D.Project Board
AnswerB

The Team Manager produces Checkpoint Reports.

Why this answer

Checkpoint Reports are produced by the Team Manager (or team members) to inform the Project Manager about progress on Work Packages.

297
Multi-Selectmedium

Which TWO of the following are outputs of the Initiating a Project process?

Select 2 answers
A.Benefits Management Approach
B.Project Brief
C.Project Initiation Documentation
D.Exception Report
E.End Stage Report
AnswersA, C

Benefits Management Approach is created during IP.

Why this answer

The PID and the Benefits Management Approach are outputs of IP. The Project Brief is from SU, and the End Stage Report is from SB.

298
MCQeasy

What is the purpose of the Starting Up a Project process?

A.To manage the day-to-day activities of the project
B.To confirm that the project is viable and worthwhile before committing to detailed planning
C.To close the project in a controlled manner
D.To produce the Project Initiation Documentation
AnswerB

SU determines whether there is a justifiable business case and sufficient information to proceed.

Why this answer

SU is a pre-project process that ensures basic conditions exist before deciding to proceed with initiation. It does not formally start the project; that happens in IP.

299
MCQmedium

A Team Manager has completed the work assigned in a Work Package. Which process is used to deliver the completed products back to the Project Manager?

A.Managing a Stage Boundary
B.Controlling a Stage
C.Managing Product Delivery
D.Closing a Project
AnswerC

MP handles Work Package delivery.

Why this answer

Managing Product Delivery (MP) is the process where the Team Manager accepts, executes, and delivers Work Packages.

300
MCQmedium

Which process includes the activity of 'authorizing a Work Package'?

A.Directing a Project
B.Controlling a Stage
C.Managing Product Delivery
D.Starting Up a Project
AnswerB

CS includes the activity 'Authorize a Work Package'.

Why this answer

Authorizing a Work Package is a key activity in the Controlling a Stage process, where the Project Manager assigns work to the Team Manager.

← PreviousPage 4 of 7 · 479 questions totalNext →

Ready to test yourself?

Try a timed practice session using only PRINCE2 Processes questions.