Which process includes the activity of 'authorizing a Work Package'?
Answer choices
Why each option matters
Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.
Correct answer & explanation
✓
Controlling a Stage
Authorizing a Work Package is a key activity in the Controlling a Stage process, where the Project Manager assigns work to the Team Manager.
Answer analysis
Option-by-option breakdown
For each option: why learners choose it and why it is or isn't the right answer here.
- ✗
Directing a Project
Why it's wrong here
DP authorizes stages, not individual Work Packages.
- ✓
Controlling a Stage
Why this is correct
CS includes the activity 'Authorize a Work Package'.
- ✗
Managing Product Delivery
Why it's wrong here
MP involves accepting and delivering Work Packages, not authorizing them.
- ✗
Starting Up a Project
Why it's wrong here
SU is pre-project and does not involve Work Packages.
Go deeper
Related to this question
About these practice questions
This PRINCE2F question is part of Courseiva's 1,599-question bank — original exam-style content with full explanations and wrong-answer analysis, never real exam questions or exam dumps. Learn why practice questions differ from exam dumps →
JA
Written by Johnson Ajibi, MSc IT Security
Senior Network & Security Engineer · founder of Courseiva
This PRINCE2F practice question is part of Courseiva's free PeopleCert certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PRINCE2F exam.