PRINCE2F PRINCE2 Processes Practice Question
Which process is responsible for authorising the initiation of a project?
⚠ Common exam trap
PRINCE2F often tests the boundary between Starting Up a Project and Directing a Project — candidates may think Starting Up a Project authorizes initiation, but it only prepares the Project Brief; the actual authorization comes from Directing a Project.
Answer choices
Why each option matters
Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.
Correct answer & explanation
✓
Directing a Project
The Directing a Project process is responsible for authorizing the initiation of a project. It is performed by the Project Board, which makes key decisions including authorizing the project initiation, stage boundaries, and project closure. The Project Board authorizes the Project Manager to proceed with Initiating a Project.
Answer analysis
Option-by-option breakdown
For each option: why learners choose it and why it is or isn't the right answer here.
- ✗
Starting Up a Project
Why it's wrong here
Starting Up a Project prepares the project brief and appoints the executive, then requests authorisation; the actual authorisation of initiation happens in Directing a Project, where the project board approves the initiation stage. It tempts because Starting Up a Project produces the very material being authorised.
- ✗
Controlling a Stage
Why it's wrong here
Controlling a Stage monitors and directs work within an already-authorised stage, so it cannot authorise initiation. It tempts because it handles stage boundaries and exception decisions, and would be correct if the question concerned authorising the next stage plan during delivery.
- ✗
Initiating a Project
Why it's wrong here
Initiating a Project produces the project initiation documentation and is itself authorised by the project board; it does not grant that authorisation. It tempts because it is the process being authorised, and would be correct if the question asked which process assembles the PID for approval.
- ✓
Directing a Project
Why this is correct
Directing a Project authorises the initiation of a project through the DP1 Authorise Initiation activity, where the Project Board reviews the project mandate and approves the Project Brief. This satisfies the requirement that initiation only proceeds with explicit board-level authority.
Go deeper
Related to this question
About these practice questions
This PRINCE2F question is part of Courseiva's 1,189-question bank — original exam-style content with full explanations and wrong-answer analysis, never real exam questions or exam dumps. Learn why practice questions differ from exam dumps →
Same concept, more angles
4 more ways this is tested on PRINCE2F
These questions test the same concept from different angles. Work through them to make sure you can recognise it however the exam phrases it.
Variation 1. Which process covers the Project Board's decision to authorise project closure?
easy- A.Managing a Stage Boundary
- B.Initiating a Project
- ✓ C.Directing a Project
- D.Closing a Project
Why C: The Directing a Project process is the responsibility of the Project Board and includes the activity 'Authorise Project Closure'. This activity is where the Project Board reviews the End Project Report and gives approval to close the project. It is a decision-making process, not a delivery or management process, and it sits above the other processes in the PRINCE2 process model.
Variation 2. In which process does the Project Board decide whether to authorise an Exception Plan?
hard- A.Starting Up a Project
- ✓ B.Directing a Project
- C.Managing a Stage Boundary
- D.Controlling a Stage
Why B: The Project Board decides whether to authorize an Exception Plan during the Directing a Project process. This process covers the Project Board's decision-making responsibilities, including reviewing and approving exception plans when a stage is forecast to exceed its tolerances. The board either approves the exception plan, allowing the project to continue, or requests alternatives.
Variation 3. Which process is used by the Project Board to authorise the start of a new stage?
medium- ✓ A.Directing a Project
- B.Initiating a Project
- C.Controlling a Stage
- D.Managing a Stage Boundary
Why A: In PRINCE2, the Directing a Project (DP) process is owned by the Project Board and includes the activity 'Authorise a Stage or Exception Plan.' The Project Board uses DP to authorize the start of each new stage after reviewing the End Stage Report and Next Stage Plan produced by Managing a Stage Boundary. This is the governance checkpoint where the Board commits resources to the next stage.
Variation 4. Which process is responsible for authorising the project's closure?
easy- ✓ A.Directing a Project
- B.Closing a Project
- C.Controlling a Stage
- D.Managing a Stage Boundary
Why A: The 'Directing a Project' process is responsible for authorizing the project's closure because it is the decision-making process performed by the Project Board. The Board reviews the End Project Report and confirms that all objectives have been met or that the project should be prematurely closed, then issues the formal authorization to close. This ensures that closure is a controlled, board-level decision, not an operational activity.
JA
Written and reviewed by Johnson Ajibi, MSc IT Security
Senior Network & Security Engineer · founder of Courseiva
Last reviewed September 2026 · checked against the official PeopleCert exam blueprint
This PRINCE2F practice question is part of Courseiva's free PeopleCert certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PRINCE2F exam.