Courseiva
PRINCE2 ProcesseseasyMultiple ChoiceObjective-mapped

PRINCE2F PRINCE2 Processes Practice Question

Which process is responsible for authorising the initiation of a project?

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

Directing a Project

The Directing a Project process is the Project Board’s process, which includes authorising initiation, the project itself, stage plans, and closure.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • Starting Up a Project

    Why it's wrong here

    SU prepares the Project Brief and assigns the Executive and PM, but does not authorise initiation.

  • Controlling a Stage

    Why it's wrong here

    CS is for day-to-day management of a stage after initiation is authorised.

  • Initiating a Project

    Why it's wrong here

    IP creates the PID but is only done after authorisation from DP.

  • Directing a Project

    Why this is correct

    DP includes the decision to authorise initiation based on the Project Brief.

About these practice questions

This PRINCE2F question is part of Courseiva's 1,599-question bank — original exam-style content with full explanations and wrong-answer analysis, never real exam questions or exam dumps. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

Same concept, more angles

4 more ways this is tested on PRINCE2F

These questions test the same concept from different angles. Work through them to make sure you can recognise it however the exam phrases it.

Variation 1. Which process covers the Project Board's decision to authorise project closure?

easy
  • A.Managing a Stage Boundary
  • B.Initiating a Project
  • C.Directing a Project
  • D.Closing a Project

Why C: The Project Board uses the Directing a Project process to authorise closure, based on the recommendation from CP.

Variation 2. In which process does the Project Board decide whether to authorise an Exception Plan?

hard
  • A.Starting Up a Project
  • B.Directing a Project
  • C.Managing a Stage Boundary
  • D.Controlling a Stage

Why B: The Project Board decides whether to authorize an Exception Plan during the Directing a Project process. This process covers the Project Board's decision-making responsibilities, including reviewing and approving exception plans when a stage is forecast to exceed its tolerances. The board either approves the exception plan, allowing the project to continue, or requests alternatives.

Variation 3. Which process is used by the Project Board to authorise the start of a new stage?

medium
  • A.Directing a Project
  • B.Initiating a Project
  • C.Controlling a Stage
  • D.Managing a Stage Boundary

Why A: Directing a Project includes authorising stage plans (including exception plans) and project closure.

Variation 4. Which process is responsible for authorising the project's closure?

easy
  • A.Directing a Project
  • B.Closing a Project
  • C.Controlling a Stage
  • D.Managing a Stage Boundary

Why A: The 'Directing a Project' process is responsible for authorizing the project's closure because it is the decision-making process performed by the Project Board. The Board reviews the End Project Report and confirms that all objectives have been met or that the project should be prematurely closed, then issues the formal authorization to close. This ensures that closure is a controlled, board-level decision, not an operational activity.

JA

Written by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

This PRINCE2F practice question is part of Courseiva's free PeopleCert certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PRINCE2F exam.