Courseiva
PRINCE2 ProcesseshardMultiple ChoiceObjective-mapped

PRINCE2F PRINCE2 Processes Practice Question

During the Controlling a Stage process, a Team Manager reports that a work package is complete. What is the next step for the Project Manager?

⚠ Common exam trap

Candidates often confuse the completion of a single work package with the end of a stage, leading them to incorrectly select options related to stage boundaries or project closure.

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

Accept the completed work package and update the stage plan

According to PRINCE2, when a Team Manager reports a work package as complete, the Project Manager must first accept the completed work package and then update the stage plan to reflect the actual progress. This ensures the stage plan remains accurate and provides a basis for assessing the impact on the project plan and any necessary corrective actions.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • Inform the Project Board immediately

    Why it's wrong here

    The Project Board is informed via periodic Highlight Reports, not immediate notification for each completed work package.

  • Close the project

    Why it's wrong here

    Closing the project is a separate process that occurs after all stages are complete.

  • Accept the completed work package and update the stage plan

    Why this is correct

    The Project Manager accepts the completed products and updates the stage plan to reflect progress.

  • Start planning the next stage immediately

    Why it's wrong here

    Planning the next stage is done during Managing a Stage Boundary, not upon completion of a single work package.

About these practice questions

This PRINCE2F question is part of Courseiva's 1,599-question bank — original exam-style content with full explanations and wrong-answer analysis, never real exam questions or exam dumps. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

This PRINCE2F practice question is part of Courseiva's free PeopleCert certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PRINCE2F exam.