Courseiva
PRINCE2 ProcessesmediumMultiple ChoiceObjective-mapped

PRINCE2F PRINCE2 Processes Practice Question

The Project Manager has identified an issue that could cause a delay in the current stage. The issue cannot be resolved within the stage's tolerance. What should the Project Manager do?

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

Raise an Exception Report and seek direction from the Project Board

When a tolerance is forecast to be exceeded, the Project Manager must escalate to the Project Board via an Exception Report. The PM cannot ignore the issue or update the plan without authorisation. Closing the project is premature.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • Close the project and produce an End Project Report

    Why it's wrong here

    Closure is a Project Board decision; the PM should escalate first.

  • Update the Stage Plan to accommodate the delay and inform the Project Board

    Why it's wrong here

    The PM cannot change the Stage Plan without Project Board authorisation when tolerance is exceeded.

  • Record the issue in the Daily Log and continue with the plan

    Why it's wrong here

    The Daily Log is for informal issues; a tolerance breach requires formal escalation.

  • Raise an Exception Report and seek direction from the Project Board

    Why this is correct

    When an issue exceeds the stage's agreed tolerance, the Project Manager must escalate by raising an Exception Report, which formally notifies the Project Board that the stage's delegated authority is breached. This triggers the Board to assess the deviation and either approve a revised plan or take corrective action, satisfying the PRINCE2 principle of management by exception.

Visual reference

Client Recursive Resolver Root DNS (13 root servers) TLD DNS (.com, .org, …) Authoritative example.com query IP addr answer

About these practice questions

This PRINCE2F question is part of Courseiva's 1,599-question bank — original exam-style content with full explanations and wrong-answer analysis, never real exam questions or exam dumps. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

This PRINCE2F practice question is part of Courseiva's free PeopleCert certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PRINCE2F exam.