Courseiva
PRINCE2 ProcesseseasyMultiple ChoiceObjective-mapped

PRINCE2F PRINCE2 Processes Practice Question

During which process does the Project Manager produce a Highlight Report?

⚠ Common exam trap

A common mix-up: candidates confuse the process that produces the report (Controlling a Stage) with the process that receives it (Directing a Project), leading candidates to incorrectly select D.

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

Controlling a Stage

The Highlight Report is produced during the Controlling a Stage process to provide the Project Board with a summary of progress against the stage plan. The Project Manager creates this report at a frequency defined in the Communication Management Approach, typically to report on achievements, planned activities, and any issues or risks.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • Managing Product Delivery

    Why it's wrong here

    MP produces Checkpoint Reports, not Highlight Reports.

  • Managing a Stage Boundary

    Why it's wrong here

    SB produces End Stage Report, not Highlight Report.

  • Controlling a Stage

    Why this is correct

    Highlight Reports are a key output of CS.

  • Directing a Project

    Why it's wrong here

    DP receives Highlight Reports but does not produce them.

About these practice questions

One of 1,599 original PRINCE2F practice questions on Courseiva, each with a full explanation and wrong-answer analysis — not exam dumps or protected exam content. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

Same concept, more angles

1 more way this is tested on PRINCE2F

These questions test the same concept from different angles. Work through them to make sure you can recognise it however the exam phrases it.

Variation 1. During which process does the Project Manager produce a Highlight Report for the Project Board?

medium
  • A.Controlling a Stage
  • B.Managing a Stage Boundary
  • C.Starting Up a Project
  • D.Managing Product Delivery

Why A: The Controlling a Stage process includes producing Highlight Reports at intervals defined by the Project Board. Managing Product Delivery produces Checkpoint Reports from the Team Manager to the PM. Managing a Stage Boundary produces End Stage Reports. Starting Up a Project does not produce Highlight Reports.

JA

Written by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

This PRINCE2F practice question is part of Courseiva's free PeopleCert certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PRINCE2F exam.