Courseiva
PRINCE2 ProcesseshardMultiple SelectObjective-mapped

PRINCE2F PRINCE2 Processes Practice Question

Which THREE of the following are outputs of the Starting Up a Project process?

⚠ Common exam trap

A common mistake is confusing the outputs of the Starting Up a Project process with those of the Initiating a Project process. Candidates often think the Project Initiation Documentation (PID) is an output of Starting Up a Project, but it is actually produced during Initiating a Project.

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

Project Brief

The Starting Up a Project process produces the Project Brief, which provides a high-level overview of the project's justification, scope, and approach. It also produces the Initiation Stage Plan, which details the activities and resources needed for the initiation stage, and the Daily Log, which records informal issues and actions. These outputs are created before the project board authorizes initiation.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • End Stage Report

    Why it's wrong here

    Produced in SB.

  • Project Brief

    Why this is correct

    Produced in SU.

  • Project Initiation Documentation (PID)

    Why it's wrong here

    Produced in IP.

  • Daily Log

    Why this is correct

    Created in SU.

  • Initiation Stage Plan

    Why this is correct

    Produced in SU.

About these practice questions

Courseiva writes every PRINCE2F question from scratch — 1,599 in total, each with an explanation and a wrong-answer breakdown. None are copied from real exams or dumps. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

Same concept, more angles

1 more way this is tested on PRINCE2F

These questions test the same concept from different angles. Work through them to make sure you can recognise it however the exam phrases it.

Variation 1. Which TWO of the following are outputs of the Starting Up a Project process?

medium
  • A.Project Brief
  • B.Benefits Management Approach
  • C.Project Initiation Documentation
  • D.Daily Log
  • E.End Stage Report

Why A: Starting Up a Project produces the Project Brief, Initiation Stage Plan, and Daily Log. PID and Benefits Management Approach are from Initiating a Project. End Stage Report is from Managing a Stage Boundary.

JA

Written by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

This PRINCE2F practice question is part of Courseiva's free PeopleCert certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PRINCE2F exam.