Courseiva
PRINCE2 ProcesseshardMultiple ChoiceObjective-mapped

PRINCE2F PRINCE2 Processes Practice Question

A Work Package is being executed. The Team Manager discovers a product cannot meet its quality criteria due to an unforeseen technical limitation. What should the Team Manager do?

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

Raise an issue to the Project Manager

The Team Manager should raise an issue (or off-specification) to the Project Manager via the MP process. The Project Manager will then decide on corrective action or escalation.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • Directly inform the Project Board

    Why it's wrong here

    The Team Manager reports to the Project Manager, not directly to the Project Board.

  • Raise an issue to the Project Manager

    Why this is correct

    The Team Manager should report the issue so that the Project Manager can decide on appropriate action.

  • Proceed with the work and accept the lower quality

    Why it's wrong here

    This violates the quality requirements and needs Project Manager authorization.

  • Update the Work Package and continue

    Why it's wrong here

    Any change to the Work Package requires authorization.

About these practice questions

This PRINCE2F question is part of Courseiva's 1,599-question bank — original exam-style content with full explanations and wrong-answer analysis, never real exam questions or exam dumps. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

Same concept, more angles

2 more ways this is tested on PRINCE2F

These questions test the same concept from different angles. Work through them to make sure you can recognise it however the exam phrases it.

Variation 1. A Work Package is being executed by the Team Manager. During this, the Team Manager identifies a new risk that could delay delivery. What should the Team Manager do?

medium
  • A.Update the Risk Register and inform the Project Manager
  • B.Update the Project Plan
  • C.Stop work and wait for instructions
  • D.Inform the Project Board directly

Why A: The Team Manager manages the Work Package and reports issues/risks to the Project Manager via Checkpoint Reports and the Issue Register.

Variation 2. A Team Manager identifies a quality problem in a product that is being delivered. What should the Team Manager do?

hard
  • A.Record the problem and inform the Project Manager
  • B.Update the Checkpoint Report and ignore the problem
  • C.Reject the product and stop all work
  • D.Fix the product immediately to meet quality criteria

Why A: The Team Manager should first record the quality problem as an issue and escalate it to the Project Manager, who will decide how to handle it. The Team Manager cannot unilaterally change the product or stop work without authorization.

JA

Written by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

This PRINCE2F practice question is part of Courseiva's free PeopleCert certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PRINCE2F exam.