A project is in the Initiating a Project process. Which document describes how changes to baselined products will be managed?
Answer choices
Why each option matters
Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.
Correct answer & explanation
✓
Change Control Approach
The Change Control Approach defines how changes to baselined products are managed, including the change control procedure.
Answer analysis
Option-by-option breakdown
For each option: why learners choose it and why it is or isn't the right answer here.
- ✗
Project Plan
Why it's wrong here
The Project Plan describes the overall project timeline and costs, not change management.
- ✓
Change Control Approach
Why this is correct
The Change Control Approach documents how changes to baselined products will be handled.
- ✗
Risk Management Approach
Why it's wrong here
The Risk Management Approach defines risk management procedures, not change control.
- ✗
Quality Management Approach
Why it's wrong here
The Quality Management Approach defines quality standards and procedures, not change control.
Go deeper
Related to this question
About these practice questions
Courseiva writes every PRINCE2F question from scratch — 1,599 in total, each with an explanation and a wrong-answer breakdown. None are copied from real exams or dumps. Learn why practice questions differ from exam dumps →
JA
Written by Johnson Ajibi, MSc IT Security
Senior Network & Security Engineer · founder of Courseiva
This PRINCE2F practice question is part of Courseiva's free PeopleCert certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PRINCE2F exam.