A project is in the Initiating a Project process. Which document describes how changes to baselined products will be managed?

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

Change Control Approach

The Change Control Approach defines how changes to baselined products are managed, including the change control procedure.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • Project Plan

    Why it's wrong here

    The Project Plan describes the overall project timeline and costs, not change management.

  • Change Control Approach

    Why this is correct

    The Change Control Approach documents how changes to baselined products will be handled.

  • Risk Management Approach

    Why it's wrong here

    The Risk Management Approach defines risk management procedures, not change control.

  • Quality Management Approach

    Why it's wrong here

    The Quality Management Approach defines quality standards and procedures, not change control.

About these practice questions

Courseiva writes every PRINCE2F question from scratch — 1,599 in total, each with an explanation and a wrong-answer breakdown. None are copied from real exams or dumps. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

This PRINCE2F practice question is part of Courseiva's free PeopleCert certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PRINCE2F exam.