Courseiva
PRINCE2 ProcesseshardMultiple ChoiceObjective-mapped

PRINCE2F PRINCE2 Processes Practice Question

During which process does the Project Manager produce an Exception Plan?

⚠ Common exam trap

It's easy for candidates to confuse the creation of an Exception Plan with the Controlling a Stage process, but the Exception Plan is specifically produced during Managing a Stage Boundary when tolerances are forecast to be exceeded, not during routine stage management.

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

Managing a Stage Boundary

The Exception Plan is produced during the Managing a Stage Boundary process because this process is triggered when a stage is forecast to exceed its tolerances. The Project Manager creates the Exception Plan to replace the current Stage Plan and submit it to the Project Board for approval, ensuring continued control over the project.

About these practice questions

One of 1,599 original PRINCE2F practice questions on Courseiva, each with a full explanation and wrong-answer analysis — not exam dumps or protected exam content. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

Same concept, more angles

2 more ways this is tested on PRINCE2F

These questions test the same concept from different angles. Work through them to make sure you can recognise it however the exam phrases it.

Variation 1. In which process does the Project Manager prepare an Exception Plan?

hard
  • A.Initiating a Project
  • B.Directing a Project
  • C.Managing a Stage Boundary
  • D.Controlling a Stage

Why C: The Exception Plan is prepared by the Project Manager in the Managing a Stage Boundary process when a stage is forecast to exceed its tolerances. This process allows the Project Manager to present options to the Project Board, including an Exception Plan to replace the current stage plan, ensuring continued control within agreed tolerances.

Variation 2. In which process does the Project Manager produce an Exception Plan?

medium
  • A.Initiating a Project
  • B.Controlling a Stage
  • C.Managing a Stage Boundary
  • D.Directing a Project

Why C: When a stage tolerance is forecast to be exceeded, the Project Manager raises an Exception Report and then, if directed by the Project Board, produces an Exception Plan during Managing a Stage Boundary.

JA

Written by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

This PRINCE2F practice question is part of Courseiva's free PeopleCert certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PRINCE2F exam.