During the Controlling a Stage process, the Project Manager needs to assign work to a team. What should the Project Manager create?
Answer choices
Why each option matters
Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.
Correct answer & explanation
✓
Work Package
The Project Manager authorizes work by issuing a Work Package to the Team Manager.
Answer analysis
Option-by-option breakdown
For each option: why learners choose it and why it is or isn't the right answer here.
- ✓
Work Package
Why this is correct
A Work Package is the set of instructions for the team to produce one or more products.
- ✗
Team Plan
Why it's wrong here
Team Plans are created by the Team Manager, not the Project Manager.
- ✗
Project Plan
Why it's wrong here
The Project Plan is a high-level plan, not for assigning work to teams.
- ✗
Product Description
Why it's wrong here
Product Descriptions define product requirements, but the Work Package is the authorization to do the work.
Go deeper
Related to this question
About these practice questions
One of 1,599 original PRINCE2F practice questions on Courseiva, each with a full explanation and wrong-answer analysis — not exam dumps or protected exam content. Learn why practice questions differ from exam dumps →
JA
Written by Johnson Ajibi, MSc IT Security
Senior Network & Security Engineer · founder of Courseiva
This PRINCE2F practice question is part of Courseiva's free PeopleCert certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PRINCE2F exam.