During the Controlling a Stage process, the Project Manager needs to assign work to a team. What should the Project Manager create?

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

Work Package

The Project Manager authorizes work by issuing a Work Package to the Team Manager.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • Work Package

    Why this is correct

    A Work Package is the set of instructions for the team to produce one or more products.

  • Team Plan

    Why it's wrong here

    Team Plans are created by the Team Manager, not the Project Manager.

  • Project Plan

    Why it's wrong here

    The Project Plan is a high-level plan, not for assigning work to teams.

  • Product Description

    Why it's wrong here

    Product Descriptions define product requirements, but the Work Package is the authorization to do the work.

About these practice questions

One of 1,599 original PRINCE2F practice questions on Courseiva, each with a full explanation and wrong-answer analysis — not exam dumps or protected exam content. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

This PRINCE2F practice question is part of Courseiva's free PeopleCert certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PRINCE2F exam.