PRINCE2F PRINCE2 Processes Practice Question
Who is responsible for producing the End Project Report?
Answer choices
Why each option matters
Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.
Correct answer & explanation
✓
Project Manager
The Project Manager produces the End Project Report as part of the Closing a Project process.
Answer analysis
Option-by-option breakdown
For each option: why learners choose it and why it is or isn't the right answer here.
- ✗
Team Manager
Why it's wrong here
Team Managers produce Checkpoint Reports and deliver work packages.
- ✗
Senior User
Why it's wrong here
The Senior User provides requirements but does not produce the End Project Report.
- ✗
Project Board
Why it's wrong here
The Board receives and reviews the report but does not produce it.
- ✓
Project Manager
Why this is correct
Correct. The PM produces the End Project Report to summarize project performance.
Go deeper
Related to this question
About these practice questions
Courseiva writes every PRINCE2F question from scratch — 1,599 in total, each with an explanation and a wrong-answer breakdown. None are copied from real exams or dumps. Learn why practice questions differ from exam dumps →
JA
Written by Johnson Ajibi, MSc IT Security
Senior Network & Security Engineer · founder of Courseiva
This PRINCE2F practice question is part of Courseiva's free PeopleCert certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PRINCE2F exam.