Courseiva
PRINCE2 ProcesseseasyMultiple ChoiceObjective-mapped

PRINCE2F PRINCE2 Processes Practice Question

Who is responsible for producing the End Project Report?

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

Project Manager

The Project Manager produces the End Project Report as part of the Closing a Project process.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • Team Manager

    Why it's wrong here

    Team Managers produce Checkpoint Reports and deliver work packages.

  • Senior User

    Why it's wrong here

    The Senior User provides requirements but does not produce the End Project Report.

  • Project Board

    Why it's wrong here

    The Board receives and reviews the report but does not produce it.

  • Project Manager

    Why this is correct

    Correct. The PM produces the End Project Report to summarize project performance.

About these practice questions

Courseiva writes every PRINCE2F question from scratch — 1,599 in total, each with an explanation and a wrong-answer breakdown. None are copied from real exams or dumps. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

This PRINCE2F practice question is part of Courseiva's free PeopleCert certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PRINCE2F exam.