PRINCE2F PRINCE2 Processes Practice Question
The Project Board is reviewing the End Stage Report and the next Stage Plan. Which process are they performing?
Answer choices
Why each option matters
Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.
Correct answer & explanation
✓
Directing a Project
The Project Board reviews stage-end reports and decides whether to authorize the next stage. This is part of Directing a Project (DP). The PM produces the End Stage Report and next Stage Plan during Managing a Stage Boundary (SB).
Answer analysis
Option-by-option breakdown
For each option: why learners choose it and why it is or isn't the right answer here.
- ✗
Closing a Project
Why it's wrong here
CP is the final process for project closure.
- ✗
Managing a Stage Boundary
Why it's wrong here
SB is performed by the Project Manager, not the Project Board.
- ✗
Controlling a Stage
Why it's wrong here
CS is for day-to-day management, not stage-end decisions.
- ✓
Directing a Project
Why this is correct
DP includes the activity of authorizing a stage plan.
Go deeper
Related to this question
About these practice questions
This PRINCE2F question is part of Courseiva's 1,599-question bank — original exam-style content with full explanations and wrong-answer analysis, never real exam questions or exam dumps. Learn why practice questions differ from exam dumps →
JA
Written by Johnson Ajibi, MSc IT Security
Senior Network & Security Engineer · founder of Courseiva
This PRINCE2F practice question is part of Courseiva's free PeopleCert certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PRINCE2F exam.