Courseiva
PRINCE2 Processes →mediumMultiple Select

PRINCE2F PRINCE2 Processes Practice Question

Which TWO outputs are produced during the Initiating a Project process?

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

✓

Project Initiation Documentation (PID)

The Project Initiation Documentation (PID) (option A) is the primary output of the Initiating a Project process, as it consolidates the business case, project plan, risk, quality, change, and communication approaches into a single baseline document. The Benefits Management Approach (option B) is also produced during Initiating a Project, defining how and when the project's benefits will be measured, reviewed, and realized. The Project Brief (option C) is created earlier in the Starting up a Project process, not during Initiating a Project. A Work Package (option D) is produced during Controlling a Stage when work is authorized to a team, and an End Stage Report (option E) is produced during Managing a Stage Boundary, so neither belongs to Initiating a Project.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • ✓

    Project Initiation Documentation (PID)

    Why this is correct

    The Project Initiation Documentation (PID) is assembled during Initiating a Project, consolidating the business case, project plan, risk and quality approaches into a single baseline. This satisfies the stem's requirement for an output produced by that process, since the PID is formally created and approved before the project board authorises the project to proceed.

  • ✓

    Benefits Management Approach

    Why this is correct

    The Benefits Management Approach is produced during Initiating a Project, documenting how the project's benefits will be measured, managed and reviewed after delivery. It satisfies the process's requirement to define benefit realisation responsibilities before the project proceeds into subsequent stages.

  • ✗

    Project Brief

    Why it's wrong here

    The Project Brief is an input to Initiating a Project, created during Starting up a Project; it feeds the PID rather than being produced by initiation. It is tempting because it defines the project's early scope, but it would be the correct output of the preceding pre-project process.

  • ✗

    Work Package

    Why it's wrong here

    A Work Package is produced during Controlling a Stage and Managing Product Delivery, not Initiating a Project, which outputs the Project Initiation Documentation. It tempts because work packages are genuine PRINCE2 outputs, and would be correct when authorising and tracking stage-level work.

  • ✗

    End Stage Report

    Why it's wrong here

    An End Stage Report is produced during Managing a Stage Boundary, reviewing a stage's performance before the next one begins. It is tempting because it sounds like an initiation artefact, but it would be the correct output at the end of a delivery stage, not while authorising the project.

About these practice questions

One of 1,189 original PRINCE2F practice questions on Courseiva, each with a full explanation and wrong-answer analysis — not exam dumps or protected exam content. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

This PRINCE2F practice question is part of Courseiva's free PeopleCert certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PRINCE2F exam.