Courseiva
PRINCE2 ProcessesmediumMultiple SelectObjective-mapped

PRINCE2F PRINCE2 Processes Practice Question

Which TWO outputs are produced during the Initiating a Project process?

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

Project Initiation Documentation (PID)

The PID and Benefits Management Approach are both produced in IP. The Project Brief is from SU, and the End Stage Report is from SB.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • Project Initiation Documentation (PID)

    Why this is correct

    PID is the key output of Initiating a Project.

  • Benefits Management Approach

    Why this is correct

    The Benefits Management Approach is created during IP.

  • Project Brief

    Why it's wrong here

    Project Brief is produced in Starting Up a Project.

  • Work Package

    Why it's wrong here

    Work Packages are produced in Controlling a Stage.

  • End Stage Report

    Why it's wrong here

    End Stage Report is produced in Managing a Stage Boundary.

About these practice questions

One of 1,599 original PRINCE2F practice questions on Courseiva, each with a full explanation and wrong-answer analysis — not exam dumps or protected exam content. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

This PRINCE2F practice question is part of Courseiva's free PeopleCert certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PRINCE2F exam.