PRINCE2F PRINCE2 Processes Practice Question
Which TWO of the following are outputs of the Closing a Project process?
Answer choices
Why each option matters
Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.
Correct answer & explanation
✓
End Project Report
Closing a Project produces the End Project Report and the Lessons Report.
Answer analysis
Option-by-option breakdown
For each option: why learners choose it and why it is or isn't the right answer here.
- ✗
Business Case
Why it's wrong here
The Business Case is created in SU and maintained throughout the project.
- ✗
Project Plan
Why it's wrong here
Project Plan is created in IP and updated in SB.
- ✓
End Project Report
Why this is correct
The End Project Report summarizes the project and recommends closure.
- ✗
Stage Plan
Why it's wrong here
Stage Plans are created in SB.
- ✓
Lessons Report
Why this is correct
The Lessons Report is produced to capture lessons learned for future projects.
Go deeper
Related to this question
About these practice questions
Courseiva writes every PRINCE2F question from scratch — 1,599 in total, each with an explanation and a wrong-answer breakdown. None are copied from real exams or dumps. Learn why practice questions differ from exam dumps →
JA
Written by Johnson Ajibi, MSc IT Security
Senior Network & Security Engineer · founder of Courseiva
This PRINCE2F practice question is part of Courseiva's free PeopleCert certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PRINCE2F exam.