Courseiva
PRINCE2 ProcesseshardMultiple ChoiceObjective-mapped

PRINCE2F PRINCE2 Processes Practice Question

During the Controlling a Stage process, the Project Manager identifies an issue that could affect the project's ability to meet its agreed tolerances. What is the first action the Project Manager should take?

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

Record the issue in the Issue Register

The PM must first record the issue in the Issue Register and then decide on the appropriate response. If the issue could breach tolerances, an Exception Report is needed, but the immediate step is to log it.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • Update the Project Plan to reflect the impact

    Why it's wrong here

    Updating the plan is a later step after analysis and decision.

  • Instruct the Team Manager to take corrective action

    Why it's wrong here

    The PM must first assess the issue before instructing corrective action.

  • Escalate the issue to the Project Board via an Exception Report

    Why it's wrong here

    Escalation is appropriate only if the issue is forecast to exceed tolerances; the first step is to log the issue.

  • Record the issue in the Issue Register

    Why this is correct

    The PM must first log the issue in the Issue Register, then assess and decide on action.

About these practice questions

Courseiva writes every PRINCE2F question from scratch — 1,599 in total, each with an explanation and a wrong-answer breakdown. None are copied from real exams or dumps. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

Same concept, more angles

1 more way this is tested on PRINCE2F

These questions test the same concept from different angles. Work through them to make sure you can recognise it however the exam phrases it.

Variation 1. During the Controlling a Stage process, the Project Manager identifies that the project is forecast to exceed the agreed cost tolerance for the current stage. What should the Project Manager do?

medium
  • A.Close the project immediately as the Business Case is no longer viable
  • B.Raise an Exception Report to the Project Board and await their direction before proceeding
  • C.Increase the project budget to absorb the additional cost and continue with the current Stage Plan
  • D.Continue with the current Stage Plan and report the cost overrun in the next Highlight Report

Why B: When a stage tolerance is forecast to be exceeded, the Project Manager must escalate to the Project Board via an Exception Report. This is PRINCE2's management by exception principle.

JA

Written by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

This PRINCE2F practice question is part of Courseiva's free PeopleCert certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PRINCE2F exam.