PRINCE2 Processes →mediumMultiple Choice

PRINCE2F PRINCE2 Processes Practice Question

The Project Manager receives a Highlight Report from the Project Board. Is this correct?

⚠ Common exam trap

A common mix-up: candidates confuse the direction of communication, assuming the Project Board sends reports to the Project Manager, when in fact the Highlight Report is a bottom-up reporting mechanism from the Project Manager to the Project Board.

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

✓

No, the Project Manager sends Highlight Reports to the Project Board

In PRINCE2, the Highlight Report is a management product that is prepared by the Project Manager and sent to the Project Board. The purpose of the Highlight Report is to provide the Project Board with a summary of the project's progress at intervals defined in the Communication Management Strategy. Therefore, the statement that the Project Manager receives a Highlight Report from the Project Board is incorrect; the flow is from the Project Manager to the Project Board.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • ✓

    No, the Project Manager sends Highlight Reports to the Project Board

    Why this is correct

    Highlight Reports flow upward from the Project Manager to the Project Board at each reporting stage, providing progress, status and exception information. The Project Board does not author them; it receives them, so the statement that the Project Manager receives one from the Board is incorrect.

  • ✗

    Yes, the Project Board uses Highlight Reports to direct the Project Manager

    Why it's wrong here

    Highlight Reports travel from the Project Manager to the Project Board, not the reverse; the Board directs via Directing a Project decisions. The option inverts that flow. It tempts because the Board does issue direction, but through Exception Reports and tolerance decisions, not Highlight Reports.

  • ✗

    No, Highlight Reports are only used during the Initiating a Project process

    Why it's wrong here

    Highlight Reports are a Controlling a Stage and Managing a Stage Boundary product, produced throughout delivery, not confined to Initiating a Project. It tempts because Initiating a Project does create the Project Initiation Documentation, but Highlight Reports continue in every subsequent stage.

  • ✗

    Yes, the Project Board sends Highlight Reports to the Project Manager

    Why it's wrong here

    Highlight Reports are produced by the Project Manager and sent to the Project Board to summarise progress, so the Board never sends them. The direction of communication is reversed. It tempts because the Board does communicate with the Project Manager, but via decisions and advice, not Highlight Reports.

About these practice questions

One of 1,189 original PRINCE2F practice questions on Courseiva, each with a full explanation and wrong-answer analysis — not exam dumps or protected exam content. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

This PRINCE2F practice question is part of Courseiva's free PeopleCert certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PRINCE2F exam.