PRINCE2 Processes →mediumMultiple Choice

PRINCE2F PRINCE2 Processes Practice Question

During which process does the Project Manager produce a Highlight Report for the Project Board?

⚠ Common exam trap

PRINCE2F often tests the confusion between the various reports and which process/role produces them — candidates frequently mix up Highlight Reports (Project Manager to Project Board, Controlling a Stage) with Checkpoint Reports (Team Manager to Project Manager, Managing Product Delivery) or End Stage Reports (Managing a Stage Boundary).

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

✓

Controlling a Stage

The Highlight Report is a progress report produced by the Project Manager for the Project Board during the Controlling a Stage process. It is created at regular intervals (typically monthly or as defined in the Communication Management Strategy) to summarize stage progress, status, and any issues or risks. This is a core activity within Controlling a Stage, where the Project Manager monitors and reports on stage performance.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • ✓

    Controlling a Stage

    Why this is correct

    The Highlight Report is produced by the Project Manager during Controlling a Stage, giving the Project Board a regular progress summary at the frequency agreed in the Communication Management Approach. It is a Controlling a Stage output.

  • ✗

    Managing a Stage Boundary

    Why it's wrong here

    Managing a Stage Boundary produces the End Stage Report at stage closure, not periodic Highlight Reports. It is tempting because the Project Manager reports progress to the Project Board there, but that report covers stage-end performance and next-stage plans, whereas Highlight Reports are issued during Controlling a Stage.

  • ✗

    Starting Up a Project

    Why it's wrong here

    Starting Up a Project appoints the project manager and produces the project brief and initiation documentation; Highlight Reports flow to the Board during Controlling a Stage. It is tempting because it is the earliest process and does involve the Board, but reporting against stage tolerances belongs to delivery, not pre-project setup.

  • ✗

    Managing Product Delivery

    Why it's wrong here

    Managing Product Delivery covers the Team Manager's work accepting, executing and delivering work packages; the Project Manager does not produce Highlight Reports there. It is tempting because delivery progress feeds those reports, but the process itself generates Checkpoint Reports, not Project Board progress updates.

About these practice questions

This PRINCE2F question is part of Courseiva's 1,189-question bank — original exam-style content with full explanations and wrong-answer analysis, never real exam questions or exam dumps. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written and reviewed by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

Last reviewed September 2026 · checked against the official PeopleCert exam blueprint

This PRINCE2F practice question is part of Courseiva's free PeopleCert certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PRINCE2F exam.