PRINCE2F PRINCE2 Processes Practice Question
During which process does the Project Manager produce a Highlight Report for the Project Board?
Answer choices
Why each option matters
Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.
Correct answer & explanation
✓
Controlling a Stage
The Controlling a Stage process includes producing Highlight Reports at intervals defined by the Project Board. Managing Product Delivery produces Checkpoint Reports from the Team Manager to the PM. Managing a Stage Boundary produces End Stage Reports. Starting Up a Project does not produce Highlight Reports.
Answer analysis
Option-by-option breakdown
For each option: why learners choose it and why it is or isn't the right answer here.
- ✓
Controlling a Stage
Why this is correct
Highlight Reports are produced by the PM in CS to inform the Project Board.
- ✗
Managing a Stage Boundary
Why it's wrong here
SB produces End Stage Reports, not Highlight Reports.
- ✗
Starting Up a Project
Why it's wrong here
SU does not involve stage-level reporting; it is a pre-project process.
- ✗
Managing Product Delivery
Why it's wrong here
MP produces Checkpoint Reports from the Team Manager to the PM.
Go deeper
Related to this question
About these practice questions
This PRINCE2F question is part of Courseiva's 1,599-question bank — original exam-style content with full explanations and wrong-answer analysis, never real exam questions or exam dumps. Learn why practice questions differ from exam dumps →
JA
Written by Johnson Ajibi, MSc IT Security
Senior Network & Security Engineer · founder of Courseiva
This PRINCE2F practice question is part of Courseiva's free PeopleCert certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PRINCE2F exam.