- A
Stop the project and close it prematurely.
Why wrong: The project board should decide based on the exception report.
- B
Negotiate with the supplier for a discount and continue the stage work without escalation.
Why wrong: The increase exceeds tolerance; escalation is mandatory.
- C
Approve the additional cost from the project's contingency budget without informing the board.
Why wrong: The project manager cannot authorize exceeding stage tolerance.
- D
Raise an exception report to the project board, detailing the cost increase and seeking guidance.
When tolerances are forecast to be exceeded, an exception report is required.
PRINCE2F PRINCE2 Processes Practice Question
This PRINCE2F practice question tests your understanding of prince2 processes. The scenario asks you to isolate a root cause — eliminate options that address a different problem before choosing. After answering, compare your reasoning against the explanation and wrong-answer breakdown below. Once you have made your selection, read the full explanation to reinforce the concept and understand why each distractor is designed to mislead on exam day.
You are the project manager for a software development project following PRINCE2. The project is in its second stage, which has a budget tolerance of 10% above the planned cost of $200,000. The project board is composed of the executive, senior user, and senior supplier. The team has been working on a critical feature, but a key supplier has announced a 15% price increase for their services, effective immediately. This increase will push the stage costs to $230,000, exceeding the tolerance. The project manager must decide the best course of action. Which option should the project manager take?
Clue words in this question
Noticing these words before you look at the options changes how you read each choice.
Clue:
"best"Why it matters: Signals that multiple options may be partially correct. Choose the option that most directly solves the exact problem described, not the one that sounds most complete.
Clue:
"immediately / without restart"Why it matters: Time or reboot constraint — the correct answer must take effect right away without requiring a reboot or reload.
Answer choices
Why each option matters
Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.
Correct answer & explanation
Raise an exception report to the project board, detailing the cost increase and seeking guidance.
Option D is correct because PRINCE2 mandates that when a stage's forecast exceeds its tolerance (here, 10% above $200,000 = $220,000, and the new cost is $230,000), the project manager must raise an Exception Report to the project board. The board, comprising the executive, senior user, and senior supplier, then decides on corrective actions—such as approving additional budget, renegotiating scope, or stopping the project. The project manager cannot unilaterally approve the overrun or bypass the board.
Key principle: Answer the scenario, not the keyword: identify the specific constraint before choosing the most familiar-sounding option.
Answer analysis
Option-by-option breakdown
For each option: why learners choose it and why it is or isn't the right answer here.
- ✗
Stop the project and close it prematurely.
Why it's wrong here
The project board should decide based on the exception report.
- ✗
Negotiate with the supplier for a discount and continue the stage work without escalation.
Why it's wrong here
The increase exceeds tolerance; escalation is mandatory.
- ✗
Approve the additional cost from the project's contingency budget without informing the board.
Why it's wrong here
The project manager cannot authorize exceeding stage tolerance.
- ✓
Raise an exception report to the project board, detailing the cost increase and seeking guidance.
Why this is correct
When tolerances are forecast to be exceeded, an exception report is required.
Clue confirmation
The clue words "best", "immediately / without restart" in the question point toward this answer.
Related concept
Read the scenario before looking for a memorised answer.
Common exam traps
Common exam trap: answer the scenario, not the keyword
The trap here is that candidates may think the project manager can handle the overrun internally (e.g., by negotiating or using contingency), but PRINCE2 strictly requires escalation via an Exception Report when stage tolerance is exceeded, regardless of the cause.
Detailed technical explanation
How to think about this question
In PRINCE2, stage tolerances are set by the project board in the Stage Plan, and the project manager must monitor actual vs. planned costs against these tolerances. When a forecast breach occurs, the project manager raises an Exception Report, which triggers an Exception Plan if the board decides to proceed. This ensures the board retains control over significant deviations, aligning with PRINCE2's 'manage by exception' principle. In real-world software projects, supplier price hikes are common; failing to escalate can lead to unauthorized budget overruns and audit failures.
KKey Concepts to Remember
- Read the scenario before looking for a memorised answer.
- Find the constraint that changes the correct option.
- Eliminate answers that are true in general but not in this case.
TExam Day Tips
- Watch for words such as best, first, most likely and least administrative effort.
- Review why wrong options are wrong, not only why the correct option is correct.
Key takeaway
Answer the scenario, not the keyword: identify the specific constraint before choosing the most familiar-sounding option.
Real-world example
How this comes up in practice
A practitioner preparing for the PRINCE2F exam encounters this exact type of scenario on the job. The correct answer here is not the most general option — it is the best answer for the specific constraint described. Answer the scenario, not the keyword: identify the specific constraint before choosing the most familiar-sounding option. Real exam questions reward reading the full scenario before eliminating options, because the constraint defines which answer fits.
What to study next
Got this wrong? Here's your next step.
Identify which exam domain this question belongs to, review the core concept, then practise similar questions from the same domain.
- →
PRINCE2 Processes — study guide chapter
Learn the concepts, then practise the questions
- →
PRINCE2 Processes practice questions
Targeted practice on this topic area only
- →
All PRINCE2F questions
1,731 questions across all exam domains
- →
PRINCE2 Foundation study guide
Full concept coverage aligned to exam objectives
- →
PRINCE2F practice test guide
How to use practice tests most effectively before exam day
Related practice questions
Related PRINCE2F practice-question pages
Use these pages to review the topic behind this question. This is how one missed question becomes focused revision.
Overview of PRINCE2 and Principles practice questions
Practise PRINCE2F questions linked to Overview of PRINCE2 and Principles.
Business Case and Organizing practice questions
Practise PRINCE2F questions linked to Business Case and Organizing.
Project Initiation and Stages practice questions
Practise PRINCE2F questions linked to Project Initiation and Stages.
Overview of PRINCE2 and the project environment practice questions
Practise PRINCE2F questions linked to Overview of PRINCE2 and the project environment.
People: organizations, teams, and leadership practice questions
Practise PRINCE2F questions linked to People: organizations, teams, and leadership.
PRINCE2 Practices practice questions
Practise PRINCE2F questions linked to PRINCE2 Practices.
PRINCE2 Processes practice questions
Practise PRINCE2F questions linked to PRINCE2 Processes.
PRINCE2F fundamentals practice questions
Practise PRINCE2F questions linked to PRINCE2F fundamentals.
PRINCE2F scenario practice questions
Practise PRINCE2F questions linked to PRINCE2F scenario.
PRINCE2F troubleshooting practice questions
Practise PRINCE2F questions linked to PRINCE2F troubleshooting.
Practice this exam
Start a free PRINCE2F practice session
Short sessions build daily habit. Longer sessions build exam-day stamina. Try a timed session to simulate real conditions.
FAQ
Questions learners often ask
What does this PRINCE2F question test?
PRINCE2 Processes — This question tests PRINCE2 Processes — Read the scenario before looking for a memorised answer..
What is the correct answer to this question?
The correct answer is: Raise an exception report to the project board, detailing the cost increase and seeking guidance. — Option D is correct because PRINCE2 mandates that when a stage's forecast exceeds its tolerance (here, 10% above $200,000 = $220,000, and the new cost is $230,000), the project manager must raise an Exception Report to the project board. The board, comprising the executive, senior user, and senior supplier, then decides on corrective actions—such as approving additional budget, renegotiating scope, or stopping the project. The project manager cannot unilaterally approve the overrun or bypass the board.
What should I do if I get this PRINCE2F question wrong?
Identify which exam domain this question belongs to, review the core concept, then practise similar questions from the same domain.
Are there clue words in this question I should notice?
Yes — watch for: "best", "immediately / without restart". Signals that multiple options may be partially correct. Choose the option that most directly solves the exact problem described, not the one that sounds most complete.
What is the key concept behind this question?
Read the scenario before looking for a memorised answer.
About these practice questions
Courseiva creates original exam-style practice questions with explanations and wrong-answer analysis. It does not publish real exam questions, exam dumps, or protected exam content. Learn why practice questions differ from exam dumps →
Last reviewed: Jun 11, 2026
This PRINCE2F practice question is part of Courseiva's free PeopleCert certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PRINCE2F exam.
Question Discussion
Share a tip, memory trick, or ask about the reasoning behind this question. Do not post real exam questions, leaked content, braindumps, or copyrighted exam material. Comments are moderated and may be removed without notice.
Sign in to join the discussion.