PRINCE2F PRINCE2 Processes Practice Question
You are the project manager for a software development project following PRINCE2. The project is in its second stage, which has a budget tolerance of 10% above the planned cost of $200,000. The project board is composed of the executive, senior user, and senior supplier. The team has been working on a critical feature, but a key supplier has announced a 15% price increase for their services, effective immediately. This increase will push the stage costs to $230,000, exceeding the tolerance. The project manager must decide the best course of action. Which option should the project manager take?
⚠ Common exam trap
Many exam-takers think the project manager can handle the overrun internally (e.g., by negotiating or using contingency), but PRINCE2 strictly requires escalation via an Exception Report when stage tolerance is exceeded, regardless of the cause.
Answer choices
Why each option matters
Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.
Correct answer & explanation
✓
Raise an exception report to the project board, detailing the cost increase and seeking guidance.
PRINCE2 mandates that when a stage's forecast exceeds its tolerance (here, 10% above $200,000 = $220,000, and the new cost is $230,000), the project manager must raise an Exception Report to the project board. The board, comprising the executive, senior user, and senior supplier, then decides on corrective actions—such as approving additional budget, renegotiating scope, or stopping the project. The project manager cannot unilaterally approve the overrun or bypass the board.
Answer analysis
Option-by-option breakdown
For each option: why learners choose it and why it is or isn't the right answer here.
- ✗
Stop the project and close it prematurely.
Why it's wrong here
The project board should decide based on the exception report.
- ✗
Negotiate with the supplier for a discount and continue the stage work without escalation.
Why it's wrong here
The increase exceeds tolerance; escalation is mandatory.
- ✗
Approve the additional cost from the project's contingency budget without informing the board.
Why it's wrong here
The project manager cannot authorize exceeding stage tolerance.
- ✓
Raise an exception report to the project board, detailing the cost increase and seeking guidance.
Why this is correct
When tolerances are forecast to be exceeded, an exception report is required.
Go deeper
Related to this question
About these practice questions
One of 1,599 original PRINCE2F practice questions on Courseiva, each with a full explanation and wrong-answer analysis — not exam dumps or protected exam content. Learn why practice questions differ from exam dumps →
JA
Written by Johnson Ajibi, MSc IT Security
Senior Network & Security Engineer · founder of Courseiva
This PRINCE2F practice question is part of Courseiva's free PeopleCert certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PRINCE2F exam.