PRINCE2F PRINCE2 Processes Practice Question
Which process is responsible for ensuring that the project does not proceed until the Project Board has authorized the initiation?
Answer choices
Why each option matters
Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.
Correct answer & explanation
✓
Directing a Project
Directing a Project includes the activity 'Authorise Initiation' where the Project Board reviews the Project Brief and decides whether to allow initiation. Starting Up a Project prepares the Project Brief but does not authorise initiation.
Answer analysis
Option-by-option breakdown
For each option: why learners choose it and why it is or isn't the right answer here.
- ✗
Controlling a Stage
Why it's wrong here
CS occurs after initiation.
- ✗
Initiating a Project
Why it's wrong here
IP begins only after authorisation from the Project Board.
- ✗
Starting Up a Project
Why it's wrong here
SU prepares the Project Brief but does not authorise initiation.
- ✓
Directing a Project
Why this is correct
DP includes authorising initiation based on the Project Brief.
Go deeper
Related to this question
About these practice questions
This PRINCE2F question is part of Courseiva's 1,599-question bank — original exam-style content with full explanations and wrong-answer analysis, never real exam questions or exam dumps. Learn why practice questions differ from exam dumps →
JA
Written by Johnson Ajibi, MSc IT Security
Senior Network & Security Engineer · founder of Courseiva
This PRINCE2F practice question is part of Courseiva's free PeopleCert certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PRINCE2F exam.