PRINCE2F PRINCE2 Processes Practice Question
A Team Manager has completed the work assigned in a Work Package. Which process is used to deliver the completed products back to the Project Manager?
⚠ Common exam trap
The trap is that candidates might confuse Managing Product Delivery with Controlling a Stage, but the former is specifically for the Team Manager delivering work packages, while the latter is for the Project Manager controlling the stage.
Answer choices
Why each option matters
Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.
Correct answer & explanation
✓
Managing Product Delivery
In PRINCE2, the Managing Product Delivery process is responsible for accepting, executing, and delivering work packages. When a Team Manager completes a work package, they deliver the completed products back to the Project Manager through this process, which includes reporting completion and handing over the products.
Answer analysis
Option-by-option breakdown
For each option: why learners choose it and why it is or isn't the right answer here.
- ✗
Managing a Stage Boundary
Why it's wrong here
Managing a Stage Boundary prepares the next stage plan, updates the project plan and assembles the end stage report for the board. It occurs at stage end, not when a Team Manager delivers a Work Package. Managing a Stage Boundary would be correct when requesting authorisation to proceed to the next stage.
- ✗
Controlling a Stage
Why it's wrong here
Controlling a Stage covers the Project Manager's day-to-day management of a stage, including authorising work packages and receiving completed products. However, the Team Manager returns completed work through the Work Package's completion notification, which the Project Manager then accepts within Controlling a Stage — the question asks which process delivers products back, and that is Managing Product Delivery.
- ✓
Managing Product Delivery
Why this is correct
Managing Product Delivery governs the Work Package interface, covering acceptance of work, execution, and delivery of completed products back to the Project Manager. The Team Manager returns finished products through this process, which also handles Checkpoint Reports.
- ✗
Closing a Project
Why it's wrong here
Closing a Project confirms the project has delivered its products and that the business case, objectives and benefits have been reviewed, then hands over to operations. It runs after the final stage, not when a Team Manager returns a Work Package. Closing a Project would be correct at project end.
Go deeper
Related to this question
About these practice questions
Courseiva writes every PRINCE2F question from scratch — 1,189 in total, each with an explanation and a wrong-answer breakdown. None are copied from real exams or dumps. Learn why practice questions differ from exam dumps →
Same concept, more angles
1 more way this is tested on PRINCE2F
These questions test the same concept from different angles. Work through them to make sure you can recognise it however the exam phrases it.
Variation 1. A Team Manager is assigned a Work Package. In which process does the Team Manager execute the work and deliver the products?
medium- A.Controlling a Stage
- B.Managing a Stage Boundary
- ✓ C.Managing Product Delivery
- D.Directing a Project
Why C: The Team Manager executes the work and delivers the products within the Managing Product Delivery process. This process defines the interface between the Project Manager (who controls the stage) and the Team Manager (who accepts, executes, and delivers the Work Package). It contains the activities 'Accept a Work Package', 'Execute a Work Package', and 'Deliver a Work Package'.
JA
Written and reviewed by Johnson Ajibi, MSc IT Security
Senior Network & Security Engineer · founder of Courseiva
Last reviewed September 2026 · checked against the official PeopleCert exam blueprint
This PRINCE2F practice question is part of Courseiva's free PeopleCert certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PRINCE2F exam.