Which process is performed by the Project Board to authorize the start of a project?

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

Directing a Project

Directing a Project includes the activity 'Authorize Initiation' and later 'Authorize the Project' to formally start the project.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • Directing a Project

    Why this is correct

    The Project Board authorizes project initiation and the project itself via DP.

  • Initiating a Project

    Why it's wrong here

    IP prepares the PID but the Project Board authorizes the project.

  • Starting Up a Project

    Why it's wrong here

    SU is pre-project and does not authorize the project.

  • Controlling a Stage

    Why it's wrong here

    CS is about managing a stage, not authorizing the project.

About these practice questions

One of 1,599 original PRINCE2F practice questions on Courseiva, each with a full explanation and wrong-answer analysis — not exam dumps or protected exam content. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

This PRINCE2F practice question is part of Courseiva's free PeopleCert certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PRINCE2F exam.