PRINCE2F PRINCE2 Processes Practice Question
Which process is performed by the Project Board to authorize the start of a project?
Answer choices
Why each option matters
Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.
Correct answer & explanation
✓
Directing a Project
Directing a Project includes the activity 'Authorize Initiation' and later 'Authorize the Project' to formally start the project.
Answer analysis
Option-by-option breakdown
For each option: why learners choose it and why it is or isn't the right answer here.
- ✓
Directing a Project
Why this is correct
The Project Board authorizes project initiation and the project itself via DP.
- ✗
Initiating a Project
Why it's wrong here
IP prepares the PID but the Project Board authorizes the project.
- ✗
Starting Up a Project
Why it's wrong here
SU is pre-project and does not authorize the project.
- ✗
Controlling a Stage
Why it's wrong here
CS is about managing a stage, not authorizing the project.
Go deeper
Related to this question
About these practice questions
One of 1,599 original PRINCE2F practice questions on Courseiva, each with a full explanation and wrong-answer analysis — not exam dumps or protected exam content. Learn why practice questions differ from exam dumps →
JA
Written by Johnson Ajibi, MSc IT Security
Senior Network & Security Engineer · founder of Courseiva
This PRINCE2F practice question is part of Courseiva's free PeopleCert certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PRINCE2F exam.