Courseiva
PRINCE2 Processes →mediumMultiple Select

PRINCE2F PRINCE2 Processes Practice Question

Which TWO of the following reports are produced by the Project Manager during the Controlling a Stage process?

⚠ Common exam trap

PRINCE2F often tests the direction and process ownership of reports — candidates confuse who produces a report (Project Manager vs Team Manager) and in which process it is created, leading them to pick Checkpoint Report or End Stage Report incorrectly.

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

✓

Highlight Report

In PRINCE2, the Controlling a Stage process is where the Project Manager monitors and controls the work of a stage, and it produces two key reports: the Highlight Report (option B), a time-driven progress report sent to the Project Board at agreed intervals to summarize stage status, and the Exception Report (option D), produced when a stage or project is forecast to exceed the tolerances set by the Project Board, documenting the exception and proposed options. The Lessons Report (option A) is instead produced during Managing a Stage Boundary (and at project closure) to capture lessons for the organization, not during Controlling a Stage. The End Stage Report (option C) is also produced in Managing a Stage Boundary to summarize stage performance for the Project Board's decision on the next stage. The Checkpoint Report (option E) is a Team Manager product, created during Managing Product Delivery to report progress to the Project Manager, so it is not produced by the Project Manager in Controlling a Stage.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • ✗

    Lessons Report

    Why it's wrong here

    The Lessons Report is produced during Closing a Project, not Controlling a Stage; the Project Manager captures lessons throughout but formally compiles the report at project closure. It is tempting because lessons are reviewed during stage boundaries, yet the report itself belongs to the closing process.

  • ✓

    Highlight Report

    Why this is correct

    The Highlight Report is a progress report the Project Manager produces at intervals agreed with the Project Board during Controlling a Stage, summarising stage status. It is one of the two reports named in the stem, distinct from reports produced in other processes.

  • ✗

    End Stage Report

    Why it's wrong here

    The End Stage Report is produced during Closing a Stage, not Controlling a Stage, so it falls outside the process named in the stem. It is tempting because the Project Manager does author it, and it would be the right answer if the question asked about reports from the Closing a Stage process.

  • ✓

    Exception Report

    Why this is correct

    The Exception Report is produced by the Project Manager during Controlling a Stage when a stage or project tolerance is forecast to be exceeded, escalating the situation to the Project Board for a decision. It is one of the two reports named in the stem.

  • ✗

    Checkpoint Report

    Why it's wrong here

    Checkpoint Reports are produced by the Team Manager and sent to the Project Manager, not produced by the Project Manager during Controlling a Stage. It is tempting because they are reviewed within that process, but the Project Manager's own reports there are Highlight Reports and Exception Reports.

About these practice questions

Courseiva writes every PRINCE2F question from scratch — 1,189 in total, each with an explanation and a wrong-answer breakdown. None are copied from real exams or dumps. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written and reviewed by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

Last reviewed September 2026 · checked against the official PeopleCert exam blueprint

This PRINCE2F practice question is part of Courseiva's free PeopleCert certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PRINCE2F exam.