PRINCE2F PRINCE2 Processes Practice Question
Which TWO of the following reports are produced by the Project Manager during the Controlling a Stage process?
Answer choices
Why each option matters
Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.
Correct answer & explanation
✓
Highlight Report
During Controlling a Stage, the Project Manager produces Highlight Reports and Exception Reports. Checkpoint Reports are produced by Team Managers during Managing Product Delivery. The End Stage Report is from Managing a Stage Boundary. The Lessons Report is from Closing a Project.
Answer analysis
Option-by-option breakdown
For each option: why learners choose it and why it is or isn't the right answer here.
- ✗
Lessons Report
Why it's wrong here
The Lessons Report is produced during Closing a Project.
- ✓
Highlight Report
Why this is correct
The Project Manager produces Highlight Reports during Controlling a Stage.
- ✗
End Stage Report
Why it's wrong here
The End Stage Report is produced during Managing a Stage Boundary.
- ✓
Exception Report
Why this is correct
The Project Manager produces Exception Reports when tolerances are forecast to be exceeded.
- ✗
Checkpoint Report
Why it's wrong here
Checkpoint Reports are produced by Team Managers during Managing Product Delivery.
Go deeper
Related to this question
About these practice questions
Courseiva writes every PRINCE2F question from scratch — 1,599 in total, each with an explanation and a wrong-answer breakdown. None are copied from real exams or dumps. Learn why practice questions differ from exam dumps →
JA
Written by Johnson Ajibi, MSc IT Security
Senior Network & Security Engineer · founder of Courseiva
This PRINCE2F practice question is part of Courseiva's free PeopleCert certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PRINCE2F exam.