PRINCE2F Checkpoint Report Practice Question

In the Managing Product Delivery process, who is responsible for producing Checkpoint Reports?

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

✓

The Team Manager

In PRINCE2, the Checkpoint Report is produced by the Team Manager to inform the Project Manager of progress on Work Packages. The Team Manager (or the team) prepares these reports at intervals defined in the Work Package. The Project Manager receives them, not the Project Board. Therefore, option C is correct.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • ✗

    The Project Support

    Why it's wrong here

    Checkpoint Reports are produced by the Team Manager to inform the Project Manager of Work Package progress, so assigning them to Project Support misplaces the accountability. Project Support is tempting because it administers configuration records, tools and information flows, and would legitimately produce such reports only where the project has formally delegated that administrative task.

  • ✗

    The Project Board

    Why it's wrong here

    The Project Board receives Highlight Reports and gives direction; it does not author Checkpoint Reports. Those are written by the Team Manager during Work Package delivery, so the Board's governance role is not the reporting source here.

  • ✓

    The Team Manager

    Why this is correct

    The Team Manager produces Checkpoint Reports, satisfying the Managing Product Delivery requirement to keep the Project Manager informed of work package progress. This role controls the team's daily work and reports status at agreed intervals, whereas the Project Manager receives these reports and escalates exceptions through Highlight Reports.

  • ✗

    The Project Manager

    Why it's wrong here

    The Project Manager receives Checkpoint Reports and reviews Work Package progress; producing them belongs to the Team Manager, who controls delivery. The Project Manager's own reporting instrument is the Highlight Report to the Project Board.

About these practice questions

One of 1,189 original PRINCE2F practice questions on Courseiva, each with a full explanation and wrong-answer analysis — not exam dumps or protected exam content. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

This PRINCE2F practice question is part of Courseiva's free PeopleCert certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PRINCE2F exam.