Correct answer & explanation
✓
SU creates the Project Brief; IP creates the Project Initiation Documentation
SU is a pre-project process to determine if the project is viable; IP formally establishes the project by creating the PID.
Answer analysis
Option-by-option breakdown
For each option: why learners choose it and why it is or isn't the right answer here.
- ✓
SU creates the Project Brief; IP creates the Project Initiation Documentation
Why this is correct
The Starting Up a Project (SU) process produces the Project Brief, which provides the outline business case and project mandate, whereas the Initiating a Project (IP) process generates the Project Initiation Documentation (PID), which contains the detailed plans, risk register, and business justification. This satisfies the stem’s requirement for a correct distinction by naming the specific deliverables each process creates.
- ✗
SU is performed by the Project Board; IP is performed by the Project Manager
Why it's wrong here
Both processes are performed by the Project Manager, with the Project Board only authorising them; the split described does not exist. It is tempting because the Board does own decision gates, which would make this true if the question concerned authorisation rather than execution responsibility.
- ✗
SU produces the Stage Plan for the first delivery stage; IP produces the initiation stage plan
Why it's wrong here
The Stage Plan for the first delivery stage is produced during Initiating a Project, not Starting Up a Project, which instead produces the project brief and initiation stage plan. It is tempting because SU does assemble the initiation stage plan, so the two plans are easily transposed.
- ✗
SU authorises the project; IP authorises the initiation stage
Why it's wrong here
The Project Board authorises the project at the end of Initiating a Project, not during Starting Up a Project, which only ends with authorisation to initiate. It is tempting because SU does secure a Board decision, but that decision concerns whether to initiate, not the project itself.
Go deeper
Related to this question
About these practice questions
One of 1,189 original PRINCE2F practice questions on Courseiva, each with a full explanation and wrong-answer analysis — not exam dumps or protected exam content. Learn why practice questions differ from exam dumps →
JA
Written by Johnson Ajibi, MSc IT Security
Senior Network & Security Engineer · founder of Courseiva
This PRINCE2F practice question is part of Courseiva's free PeopleCert certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PRINCE2F exam.