SU creates the Project Brief; IP creates the Project Initiation Documentation

SU is a pre-project process to determine if the project is viable; IP formally establishes the project by creating the PID.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • ✓

    SU creates the Project Brief; IP creates the Project Initiation Documentation

    Why this is correct

    The Starting Up a Project (SU) process produces the Project Brief, which provides the outline business case and project mandate, whereas the Initiating a Project (IP) process generates the Project Initiation Documentation (PID), which contains the detailed plans, risk register, and business justification. This satisfies the stem’s requirement for a correct distinction by naming the specific deliverables each process creates.

  • ✗

    SU is performed by the Project Board; IP is performed by the Project Manager

    Why it's wrong here

    Both processes are performed by the Project Manager, with the Project Board only authorising them; the split described does not exist. It is tempting because the Board does own decision gates, which would make this true if the question concerned authorisation rather than execution responsibility.

  • ✗

    SU produces the Stage Plan for the first delivery stage; IP produces the initiation stage plan

    Why it's wrong here

    The Stage Plan for the first delivery stage is produced during Initiating a Project, not Starting Up a Project, which instead produces the project brief and initiation stage plan. It is tempting because SU does assemble the initiation stage plan, so the two plans are easily transposed.

  • ✗

    SU authorises the project; IP authorises the initiation stage

    Why it's wrong here

    The Project Board authorises the project at the end of Initiating a Project, not during Starting Up a Project, which only ends with authorisation to initiate. It is tempting because SU does secure a Board decision, but that decision concerns whether to initiate, not the project itself.

About these practice questions

One of 1,189 original PRINCE2F practice questions on Courseiva, each with a full explanation and wrong-answer analysis — not exam dumps or protected exam content. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

This PRINCE2F practice question is part of Courseiva's free PeopleCert certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PRINCE2F exam.