PRINCE2F PRINCE2 Processes Practice Question
A project is being set up. The Project Manager needs to confirm that the project has a viable Business Case and that the Project Board has authorised the initiation stage. Which process covers the appointment of the Project Manager and the preparation of the Project Brief?
⚠ Common exam trap
A common mix-up: candidates confuse the pre-project setup activities with Initiating a Project, which produces the PID but does not appoint the Project Manager or create the Project Brief.
Answer choices
Why each option matters
Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.
Correct answer & explanation
✓
Starting Up a Project
Starting Up a Project is the pre-project process that ensures the prerequisites for initiating the project are in place. It appoints the Project Manager and Project Board, captures and evaluates the project mandate, prepares the Project Brief, and plans initiation. The Project Board then decides whether to authorise initiation. The scenario's activities therefore fall squarely within Starting Up a Project.
Answer analysis
Option-by-option breakdown
For each option: why learners choose it and why it is or isn't the right answer here.
- ✗
Initiating a Project
Why it's wrong here
Initiating a Project builds on the Project Brief to create the Project Initiation Documentation and establish the project's controls. It occurs after the Project Brief exists and after the Project Board has authorised initiation. Appointing the Project Manager and preparing the Project Brief happen earlier, in Starting Up a Project.
- ✓
Starting Up a Project
Why this is correct
Starting Up a Project is the pre-project process that appoints the Project Manager and Project Board, captures the project mandate, and prepares the Project Brief. It ensures the project has a viable Business Case and that initiation is authorised. The activities described in the scenario are exactly those of Starting Up a Project.
- ✗
Directing a Project
Why it's wrong here
Directing a Project is the ongoing Project Board process that authorises the project, stages, and closure. It provides direction and decisions but does not itself appoint the Project Manager or prepare the Project Brief. Those preparatory activities belong to Starting Up a Project, which feeds the Project Board's authorisation decision.
- ✗
Controlling a Stage
Why it's wrong here
Controlling a Stage is the Project Manager's day-to-day process for managing work during a stage, including authorising Work Packages and monitoring progress. It operates after initiation, once stages are underway. It does not cover the pre-project setup activities of appointing the Project Manager or preparing the Project Brief.
Go deeper
Related to this question
About these practice questions
Courseiva writes every PRINCE2F question from scratch — 1,189 in total, each with an explanation and a wrong-answer breakdown. None are copied from real exams or dumps. Learn why practice questions differ from exam dumps →
JA
Written and reviewed by Johnson Ajibi, MSc IT Security
Senior Network & Security Engineer · founder of Courseiva
Last reviewed September 2026 · checked against the official PeopleCert exam blueprint
This PRINCE2F practice question is part of Courseiva's free PeopleCert certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PRINCE2F exam.