During the Controlling a Stage process, the Project Manager receives a Checkpoint Report from the Team Manager. What should the Project Manager do with this report?

⚠ Common exam trap

PRINCE2F often tests the reporting chain — candidates confuse who produces what and who receives what, especially the Checkpoint Report (Team Manager → Project Manager) versus the Highlight Report (Project Manager → Project Board).

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

✓

Use it to review progress and produce the Highlight Report

In PRINCE2, the Checkpoint Report is produced by the Team Manager and sent to the Project Manager at a frequency defined in the Work Package. The Project Manager uses it to review progress of the work package, and this information feeds into the Highlight Report, which the Project Manager produces for the Project Board. Therefore, the Project Manager should use the Checkpoint Report to review progress and produce the Highlight Report.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • ✗

    File it as a record and take no further action

    Why it's wrong here

    Filing without action discards the report's purpose: the Project Manager must review progress, compare it against the Stage Plan and take corrective action where needed. It is tempting because records are retained, and filing alone would suit a routine document with no bearing on stage control.

  • ✗

    Return it to the Team Manager for corrections

    Why it's wrong here

    Checkpoint Reports are progress updates the Project Manager reviews and acts on, not documents returned for correction; there is no stated error requiring amendment. It is tempting because quality review of products is normal PRINCE2 practise, and returning a report would suit a genuinely inaccurate or incomplete document.

  • ✓

    Use it to review progress and produce the Highlight Report

    Why this is correct

    Checkpoint Reports give the Project Manager progress data from the Team Manager. Controlling a Stage uses this to monitor work package status, update the Stage Plan, and feed the Highlight Report to the Project Board.

  • ✗

    Forward it directly to the Project Board without review

    Why it's wrong here

    Checkpoint Reports inform the Project Manager's own monitoring and control; the Project Board receives Highlight Reports and Exception Reports instead, so forwarding bypasses the agreed reporting line. It is tempting because escalation feels diligent, and forwarding would suit an Exception Report requiring board direction.

About these practice questions

This PRINCE2F question is part of Courseiva's 1,189-question bank — original exam-style content with full explanations and wrong-answer analysis, never real exam questions or exam dumps. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written and reviewed by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

Last reviewed September 2026 · checked against the official PeopleCert exam blueprint

This PRINCE2F practice question is part of Courseiva's free PeopleCert certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PRINCE2F exam.