PRINCE2 Processes →mediumMultiple Choice

PRINCE2F PRINCE2 Processes Practice Question

During which process are lessons for the project first recorded?

⚠ Common exam trap

Candidates often confuse 'Initiating a Project' (where detailed planning and the PID are created) with the first recording of lessons, but PRINCE2 explicitly requires lessons to be captured before initiation begins, during the 'Starting Up a Project' process.

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

✓

Starting Up a Project

In PRINCE2, the first formal recording of lessons occurs during the 'Starting Up a Project' process. This process includes the activity 'Capture Previous Lessons' (from the 'Learn from Experience' principle), where the project manager reviews lessons from similar previous projects and records them in the Lessons Log before the project is even initiated. This ensures that the project starts with the benefit of past experience.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • ✗

    Initiating a Project

    Why it's wrong here

    Initiating a Project compiles the Lessons Log from previous projects and corporate lessons, but the first lessons of this project are captured during Starting up a Project, before the project mandate is approved. Initiating is chosen when building the PID.

  • ✗

    Managing a Stage Boundary

    Why it's wrong here

    Managing a Stage Boundary reviews and updates the Lessons Log at each stage end, so entries already exist from earlier processes. It is the correct process when authorising the next stage plan and reporting stage-end performance to the project board.

  • ✓

    Starting Up a Project

    Why this is correct

    Starting Up a Project captures lessons from previous projects in the Lessons Log as part of the Lessons Learned approach, before the Project Initiation Documentation is assembled, making it the earliest point at which project lessons are recorded.

  • ✗

    Closing a Project

    Why it's wrong here

    Closing a Project captures end-project lessons and handover information, but by then lessons have already been logged throughout delivery. This process is chosen when formally disbanding the project team and confirming acceptance of the final products.

About these practice questions

Courseiva writes every PRINCE2F question from scratch — 1,189 in total, each with an explanation and a wrong-answer breakdown. None are copied from real exams or dumps. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

This PRINCE2F practice question is part of Courseiva's free PeopleCert certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PRINCE2F exam.