PRINCE2F PRINCE2 Processes Practice Question
Which document is produced in the Initiating a Project process and provides a baseline for the project?
⚠ Common exam trap
PRINCE2F often tests the distinction between documents produced in different processes; candidates may incorrectly choose the Project Brief because it is also a key document, but it is an input to Initiating a Project, not an output that provides a baseline.
Answer choices
Why each option matters
Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.
Correct answer & explanation
✓
Project Initiation Documentation
The Project Initiation Documentation (PID) is the key output of the Initiating a Project process. It consolidates the business case, project plan, risk register, and other baselines, and is approved by the Project Board to authorize the project. The PID provides the baseline against which the project's progress and performance are measured.
Answer analysis
Option-by-option breakdown
For each option: why learners choose it and why it is or isn't the right answer here.
- ✗
End Stage Report
Why it's wrong here
The End Stage Report is produced during Managing a Stage Boundary to review a stage's performance, not during Initiating a Project. It is tempting because it does establish an information baseline, but for the closing stage rather than the whole project, making it the wrong process here.
- ✗
Project Brief
Why it's wrong here
The Project Brief is an input to Initiating a Project, assembled during Starting up a Project, and it is superseded by the Project Initiation Documentation. It is tempting because it does outline the project, but it lacks the PID's baselines, so it cannot serve as the baseline.
- ✓
Project Initiation Documentation
Why this is correct
The Project Initiation Documentation is assembled during Initiating a Project and provides the baseline against which the project is managed, containing the Business Case, Project Plan, benefits, risks and controls approved by the Project Board.
- ✗
Lessons Report
Why it's wrong here
The Lessons Report is created during Managing a Stage Boundary and at project closure, capturing lessons for future projects, not during Initiating a Project. It is tempting because lessons appear in the PID's lessons log, but the report itself is a different product from a different process.
Go deeper
Related to this question
About these practice questions
One of 1,189 original PRINCE2F practice questions on Courseiva, each with a full explanation and wrong-answer analysis — not exam dumps or protected exam content. Learn why practice questions differ from exam dumps →
JA
Written and reviewed by Johnson Ajibi, MSc IT Security
Senior Network & Security Engineer · founder of Courseiva
Last reviewed September 2026 · checked against the official PeopleCert exam blueprint
This PRINCE2F practice question is part of Courseiva's free PeopleCert certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PRINCE2F exam.