Which process includes the activity 'Authorize a Work Package'?

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

Controlling a Stage

Authorizing a Work Package is an activity performed by the Project Manager in the Controlling a Stage process.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • Managing Product Delivery

    Why it's wrong here

    MP accepts Work Packages, but authorization is done by the PM in CS.

  • Controlling a Stage

    Why this is correct

    In CS, the PM authorizes Work Packages to the Team Manager.

  • Initiating a Project

    Why it's wrong here

    IP does not authorize Work Packages; it plans the stage.

  • Directing a Project

    Why it's wrong here

    DP is the Board's process, not involved in Work Package authorization.

About these practice questions

This PRINCE2F question is part of Courseiva's 1,599-question bank — original exam-style content with full explanations and wrong-answer analysis, never real exam questions or exam dumps. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

This PRINCE2F practice question is part of Courseiva's free PeopleCert certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PRINCE2F exam.