PRINCE2F PRINCE2 Processes Practice Question
Which process includes the activity 'Authorize a Work Package'?
Answer choices
Why each option matters
Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.
Correct answer & explanation
✓
Controlling a Stage
Authorizing a Work Package is an activity performed by the Project Manager in the Controlling a Stage process.
Answer analysis
Option-by-option breakdown
For each option: why learners choose it and why it is or isn't the right answer here.
- ✗
Managing Product Delivery
Why it's wrong here
MP accepts Work Packages, but authorization is done by the PM in CS.
- ✓
Controlling a Stage
Why this is correct
In CS, the PM authorizes Work Packages to the Team Manager.
- ✗
Initiating a Project
Why it's wrong here
IP does not authorize Work Packages; it plans the stage.
- ✗
Directing a Project
Why it's wrong here
DP is the Board's process, not involved in Work Package authorization.
Go deeper
Related to this question
About these practice questions
This PRINCE2F question is part of Courseiva's 1,599-question bank — original exam-style content with full explanations and wrong-answer analysis, never real exam questions or exam dumps. Learn why practice questions differ from exam dumps →
JA
Written by Johnson Ajibi, MSc IT Security
Senior Network & Security Engineer · founder of Courseiva
This PRINCE2F practice question is part of Courseiva's free PeopleCert certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PRINCE2F exam.