Courseiva
PRINCE2 ProcesseshardMultiple ChoiceObjective-mapped

PRINCE2F PRINCE2 Processes Practice Question

What is the difference between a Checkpoint Report and a Highlight Report in PRINCE2?

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

Checkpoint Reports are produced by the Team Manager for the Project Manager; Highlight Reports are produced by the Project Manager for the Project Board

Checkpoint Reports are produced by the Team Manager for the Project Manager during Managing Product Delivery. Highlight Reports are produced by the Project Manager for the Project Board during Controlling a Stage. They serve different audiences and have different frequencies.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • Checkpoint Reports are produced by the Project Board; Highlight Reports are produced by the Project Manager

    Why it's wrong here

    Checkpoint Reports are from the Team Manager, not the Project Board.

  • Checkpoint Reports contain only quality information; Highlight Reports contain only progress information

    Why it's wrong here

    Both reports contain progress and other information; this is not the defining difference.

  • Checkpoint Reports are produced by the Team Manager for the Project Manager; Highlight Reports are produced by the Project Manager for the Project Board

    Why this is correct

    This correctly identifies the source and recipient for each report.

  • Checkpoint Reports are produced weekly; Highlight Reports are produced monthly

    Why it's wrong here

    Frequency is not defined by PRINCE2; it is project-specific.

About these practice questions

One of 1,599 original PRINCE2F practice questions on Courseiva, each with a full explanation and wrong-answer analysis — not exam dumps or protected exam content. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

Same concept, more angles

2 more ways this is tested on PRINCE2F

These questions test the same concept from different angles. Work through them to make sure you can recognise it however the exam phrases it.

Variation 1. What is the difference between a Highlight Report and a Checkpoint Report?

hard
  • A.Highlight Reports are produced weekly; Checkpoint Reports are produced daily
  • B.There is no difference; they are the same document
  • C.Highlight Reports are produced by the Project Manager; Checkpoint Reports are produced by the Team Manager
  • D.Highlight Reports are for the Project Board; Checkpoint Reports are for the team

Why C: In PRINCE2, the Highlight Report is a formal report produced by the Project Manager for the Project Board to provide a summary of progress, while the Checkpoint Report is produced by the Team Manager for the Project Manager to report on progress within a Work Package. This distinction is defined in the PRINCE2 manual's 'Reporting' theme and the 'Controlling a Stage' process.

Variation 2. Which TWO of the following are differences between the Highlight Report and the Checkpoint Report?

hard
  • A.The Highlight Report is sent to the Project Board, while the Checkpoint Report is sent to the Project Manager
  • B.The Highlight Report is a written document, while the Checkpoint Report is always verbal
  • C.The Highlight Report is produced by the Project Manager, while the Checkpoint Report is produced by the Team Manager
  • D.The Highlight Report covers the entire project, while the Checkpoint Report covers only a specific Work Package
  • E.The Highlight Report is produced at the end of each stage, while the Checkpoint Report is produced weekly

Why A: The Highlight Report is a formal report from the Project Manager to the Project Board, providing an overview of the stage's progress, while the Checkpoint Report is a detailed report from the Team Manager to the Project Manager, focusing on the Work Package status. This distinction is a key difference in PRINCE2's management reporting lines.

JA

Written by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

This PRINCE2F practice question is part of Courseiva's free PeopleCert certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PRINCE2F exam.