PRINCE2F PRINCE2 Processes Practice Question
Who is responsible for approving the End Project Report?
Answer choices
Why each option matters
Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.
Correct answer & explanation
✓
Project Board
The Project Board, through the Directing a Project process, approves the End Project Report and authorizes project closure.
Answer analysis
Option-by-option breakdown
For each option: why learners choose it and why it is or isn't the right answer here.
- ✗
Senior Supplier
Why it's wrong here
Same as above; approval is by the Project Board as a whole.
- ✗
Project Manager
Why it's wrong here
The Project Manager produces the End Project Report but does not approve it.
- ✓
Project Board
Why this is correct
The Project Board approves the End Project Report and authorizes closure.
- ✗
Senior User
Why it's wrong here
The Senior User is part of the Project Board but approval is a collective decision.
Go deeper
Related to this question
About these practice questions
Courseiva writes every PRINCE2F question from scratch — 1,599 in total, each with an explanation and a wrong-answer breakdown. None are copied from real exams or dumps. Learn why practice questions differ from exam dumps →
JA
Written by Johnson Ajibi, MSc IT Security
Senior Network & Security Engineer · founder of Courseiva
This PRINCE2F practice question is part of Courseiva's free PeopleCert certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PRINCE2F exam.