Who is responsible for approving the End Project Report?

⚠ Common exam trap

PRINCE2F often tests the distinction between roles responsible for creating versus approving management products. Candidates might incorrectly assume the Project Manager approves the End Project Report because they are deeply involved in its creation, but approval is a governance responsibility of the Project Board.

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

✓

Project Board

In PRINCE2, the End Project Report is a key management product that provides a summary of the project's performance and is used to gain approval to close the project. The Project Board is responsible for approving this report because it holds the ultimate decision-making authority and accountability for the project's outcomes. The Project Manager prepares the report, but the Board approves it.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • ✗

    Senior Supplier

    Why it's wrong here

    The Senior Supplier provides resources and technical assurance for products, and holds no accountability for confirming project closure. It is tempting because suppliers report on deliverable completion, which would be the correct role when approving product acceptance or supplier work packages.

  • ✗

    Project Manager

    Why it's wrong here

    The Project Manager drafts the End Project Report and submits it, but cannot approve it, since approval is a Project Board decision. It is tempting because the Project Manager owns project documentation and closure activities, which would be the correct role for preparing and circulating the report.

  • ✓

    Project Board

    Why this is correct

    The Project Board approves the End Project Report, since it confirms whether the project delivered its products and achieved the Business Case. This satisfies the stem because closure approval is a board-level decision within Directing a Project, not a Project Manager responsibility.

  • ✗

    Senior User

    Why it's wrong here

    The Senior User represents user interests and benefits realisation, not project closure authorisation; the End Project Report is approved by the Project Board, with accountability resting elsewhere. It is tempting because the Senior User validates that products meet requirements, which would be the correct role for accepting delivered products.

About these practice questions

Courseiva writes every PRINCE2F question from scratch — 1,189 in total, each with an explanation and a wrong-answer breakdown. None are copied from real exams or dumps. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written and reviewed by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

Last reviewed September 2026 · checked against the official PeopleCert exam blueprint

This PRINCE2F practice question is part of Courseiva's free PeopleCert certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PRINCE2F exam.