Courseiva
PRINCE2 ProcesseseasyMultiple ChoiceObjective-mapped

PRINCE2F PRINCE2 Processes Practice Question

Who is responsible for approving the End Project Report?

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

Project Board

The Project Board, through the Directing a Project process, approves the End Project Report and authorizes project closure.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • Senior Supplier

    Why it's wrong here

    Same as above; approval is by the Project Board as a whole.

  • Project Manager

    Why it's wrong here

    The Project Manager produces the End Project Report but does not approve it.

  • Project Board

    Why this is correct

    The Project Board approves the End Project Report and authorizes closure.

  • Senior User

    Why it's wrong here

    The Senior User is part of the Project Board but approval is a collective decision.

About these practice questions

Courseiva writes every PRINCE2F question from scratch — 1,599 in total, each with an explanation and a wrong-answer breakdown. None are copied from real exams or dumps. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

This PRINCE2F practice question is part of Courseiva's free PeopleCert certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PRINCE2F exam.