PRINCE2 Processes →mediumMultiple Choice

PRINCE2F PRINCE2 Processes Practice Question

During the Managing Product Delivery process, what does the Team Manager produce to inform the Project Manager of progress?

⚠ Common exam trap

Candidates often confuse the Checkpoint Report (produced by the Team Manager) with the Highlight Report (produced by the Project Manager), as both report progress but at different levels and to different audiences.

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

✓

Checkpoint Report

In PRINCE2, the Team Manager produces a Checkpoint Report during the Managing Product Delivery process to inform the Project Manager of progress at a regular, predefined frequency. This report provides a snapshot of actual progress against the Work Package plan, including achievements, next steps, and any issues or risks. It is the primary mechanism for the Team Manager to communicate status to the Project Manager within this process.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • ✗

    Exception Report

    Why it's wrong here

    An Exception Report is raised only when a stage or project deviates beyond tolerance, so it cannot serve as routine progress communication. It is tempting because Team Managers do escalate exceptions, but that is a one-off control action, not the regular checkpoint the Project Manager expects during Managing Product Delivery.

  • ✓

    Checkpoint Report

    Why this is correct

    The Team Manager provides Checkpoint Reports to the Project Manager at the frequency agreed in the Work Package, covering progress, issues and risks. Highlight Reports are produced by the Project Manager for the Project Board, not by the Team Manager.

  • ✗

    End Stage Report

    Why it's wrong here

    The End Stage Report is assembled by the Project Manager at stage boundaries, not by the Team Manager mid-delivery. It is tempting because it does summarise progress, but its timing and authorship belong to the Controlling a Stage process, so it cannot inform ongoing delivery progress here.

  • ✗

    Highlight Report

    Why it's wrong here

    The Highlight Report is produced by the Project Manager for the Project Board, not by the Team Manager for the Project Manager. It is tempting because it is a periodic progress summary, but the direction of reporting is upward to governance, not from the delivery team.

About these practice questions

This PRINCE2F question is part of Courseiva's 1,189-question bank — original exam-style content with full explanations and wrong-answer analysis, never real exam questions or exam dumps. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

This PRINCE2F practice question is part of Courseiva's free PeopleCert certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PRINCE2F exam.