Which TWO of the following are true about the Managing Product Delivery process?

⚠ Common exam trap

PRINCE2F often tests the confusion between roles and reports across processes — candidates may incorrectly assign Highlight Reports or End Stage Reports to Managing Product Delivery, or assume the Project Manager performs this process, when it is actually the Team Manager's domain.

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

✓

It includes the acceptance of Work Packages

Option C is correct because Managing Product Delivery is the process where the Team Manager accepts a Work Package from the Project Manager, agreeing to deliver the specified products within the given constraints. Option E is correct because this process produces Checkpoint Reports, which the Team Manager sends to the Project Manager to report progress on the Work Package. Option A is incorrect because Highlight Reports are produced by the Project Manager in the Controlling a Stage process, not by Managing Product Delivery. Option B is incorrect because Managing Product Delivery is performed by the Team Manager (or the person responsible for delivering the Work Package), not the Project Manager. Option D is incorrect because End Stage Reports are produced by the Project Manager during Managing a Stage Boundary, not within Managing Product Delivery.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • ✗

    It produces Highlight Reports for the Project Board

    Why it's wrong here

    Highlight Reports are produced during Controlling a Stage, giving the Project Board periodic progress updates. It is tempting because Managing Product Delivery generates progress information, but that flows upward as Checkpoint Reports from the Team Manager, not as Highlight Reports.

  • ✗

    It is performed by the Project Manager

    Why it's wrong here

    Managing Product Delivery is performed by the Team Manager, who accepts, executes and delivers work packages; the Project Manager owns Controlling a Stage and Managing a Stage Boundary. It is tempting because the Project Manager retains overall accountability, but PRINCE2 assigns this process's day-to-day activity to the Team Manager role.

  • ✓

    It includes the acceptance of Work Packages

    Why this is correct

    Accepting Work Packages from the Project Manager is a core activity of Managing Product Delivery, satisfying the process's interface with the Controlling a Stage process. The Team Manager confirms the Work Package's content, then agrees and accepts it before commencing work, ensuring the team understands the products, tolerances and reporting requirements.

  • ✗

    It produces End Stage Reports

    Why it's wrong here

    End Stage Reports are produced during Managing a Stage Boundary, where the Project Manager reports stage performance to the Project Board. It is tempting because both processes involve reporting, but Managing Product Delivery yields Checkpoint Reports and completed work packages instead.

  • ✓

    It produces Checkpoint Reports for the Project Manager

    Why this is correct

    Checkpoint Reports are produced by the Team Manager during Managing Product Delivery, providing the Project Manager with progress information at agreed intervals. This satisfies the process's requirement to report progress to the Project Manager, distinguishing it from Work Package status accounting, which remains internal to the team.

About these practice questions

One of 1,189 original PRINCE2F practice questions on Courseiva, each with a full explanation and wrong-answer analysis — not exam dumps or protected exam content. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written and reviewed by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

Last reviewed September 2026 · checked against the official PeopleCert exam blueprint

This PRINCE2F practice question is part of Courseiva's free PeopleCert certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PRINCE2F exam.