PRINCE2F PRINCE2 Practices Practice Question
In PRINCE2, what is the difference between a Highlight Report and a Checkpoint Report?
Answer choices
Why each option matters
Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.
Correct answer & explanation
✓
Highlight Report is sent to the Project Board; Checkpoint Report is sent to the Project Manager
A Highlight Report is sent from the Project Manager to the Project Board regularly, while a Checkpoint Report is sent from the Team Manager to the Project Manager more frequently.
Answer analysis
Option-by-option breakdown
For each option: why learners choose it and why it is or isn't the right answer here.
- ✗
Highlight Report covers the entire project; Checkpoint Report covers only a stage
Why it's wrong here
Both cover specific periods.
- ✗
Highlight Report is sent by the Team Manager; Checkpoint Report is sent by the Project Manager
Why it's wrong here
It is the opposite.
- ✗
There is no difference; they are the same document
Why it's wrong here
They have different audiences and frequencies.
- ✓
Highlight Report is sent to the Project Board; Checkpoint Report is sent to the Project Manager
Why this is correct
This is correct.
Go deeper
Related to this question
About these practice questions
This PRINCE2F question is part of Courseiva's 1,599-question bank — original exam-style content with full explanations and wrong-answer analysis, never real exam questions or exam dumps. Learn why practice questions differ from exam dumps →
JA
Written by Johnson Ajibi, MSc IT Security
Senior Network & Security Engineer · founder of Courseiva
This PRINCE2F practice question is part of Courseiva's free PeopleCert certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PRINCE2F exam.