Courseiva
PRINCE2 PracticesmediumMultiple SelectObjective-mapped

PRINCE2F PRINCE2 Practices Practice Question

Which THREE of the following are true about the PRINCE2 progress control approach?

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

The Highlight Report is sent from the Project Manager to the Project Board

Options A, C, and E are correct. The Highlight Report is sent from the Project Manager to the Project Board (A). The End Project Report evaluates the project's performance against the Project Initiation Documentation (C). The Checkpoint Report is produced by the Team Manager for the Project Manager (E). Option B is false because the Lessons Report is created at the end of the project, not at each stage boundary. Option D is false because the Exception Report is produced by the Project Manager, not the Project Board.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • The Highlight Report is sent from the Project Manager to the Project Board

    Why this is correct

    The Highlight Report provides the Project Board with a summary of stage progress at regular intervals.

  • The Lessons Report is created at the end of each stage

    Why it's wrong here

    The Lessons Report is created at the end of the project (or at stage boundaries if appropriate), but not as a routine end-of-stage report.

  • The End Project Report is used to evaluate the project's performance against the Project Initiation Documentation

    Why this is correct

    The End Project Report reviews project performance and confirms handover of products.

  • The Exception Report is produced by the Project Board

    Why it's wrong here

    The Exception Report is produced by the Project Manager when tolerances are forecast to be exceeded.

  • The Checkpoint Report is produced by the Team Manager for the Project Manager

    Why this is correct

    Checkpoint Reports provide detailed progress information on work packages.

About these practice questions

This PRINCE2F question is part of Courseiva's 1,599-question bank — original exam-style content with full explanations and wrong-answer analysis, never real exam questions or exam dumps. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

This PRINCE2F practice question is part of Courseiva's free PeopleCert certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PRINCE2F exam.