PRINCE2F PRINCE2 Practices Practice Question
Which THREE of the following are true about the PRINCE2 progress control approach?
Answer choices
Why each option matters
Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.
Correct answer & explanation
✓
The Highlight Report is sent from the Project Manager to the Project Board
Options A, C, and E are correct. The Highlight Report is sent from the Project Manager to the Project Board (A). The End Project Report evaluates the project's performance against the Project Initiation Documentation (C). The Checkpoint Report is produced by the Team Manager for the Project Manager (E). Option B is false because the Lessons Report is created at the end of the project, not at each stage boundary. Option D is false because the Exception Report is produced by the Project Manager, not the Project Board.
Answer analysis
Option-by-option breakdown
For each option: why learners choose it and why it is or isn't the right answer here.
- ✓
The Highlight Report is sent from the Project Manager to the Project Board
Why this is correct
The Highlight Report provides the Project Board with a summary of stage progress at regular intervals.
- ✗
The Lessons Report is created at the end of each stage
Why it's wrong here
The Lessons Report is created at the end of the project (or at stage boundaries if appropriate), but not as a routine end-of-stage report.
- ✓
The End Project Report is used to evaluate the project's performance against the Project Initiation Documentation
Why this is correct
The End Project Report reviews project performance and confirms handover of products.
- ✗
The Exception Report is produced by the Project Board
Why it's wrong here
The Exception Report is produced by the Project Manager when tolerances are forecast to be exceeded.
- ✓
The Checkpoint Report is produced by the Team Manager for the Project Manager
Why this is correct
Checkpoint Reports provide detailed progress information on work packages.
Go deeper
Related to this question
About these practice questions
This PRINCE2F question is part of Courseiva's 1,599-question bank — original exam-style content with full explanations and wrong-answer analysis, never real exam questions or exam dumps. Learn why practice questions differ from exam dumps →
JA
Written by Johnson Ajibi, MSc IT Security
Senior Network & Security Engineer · founder of Courseiva
This PRINCE2F practice question is part of Courseiva's free PeopleCert certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PRINCE2F exam.