PRINCE2F PRINCE2 Processes Practice Question
Which TWO roles are appointed during the Starting Up a Project process?
Answer choices
Why each option matters
Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.
Correct answer & explanation
✓
Executive
During SU, the Executive and the Project Manager are appointed. The Project Board is also appointed, but the question asks for two specific roles. The Senior User and Senior Supplier are part of the Project Board but may be appointed later if not already in place.
Answer analysis
Option-by-option breakdown
For each option: why learners choose it and why it is or isn't the right answer here.
- ✗
Project Assurance
Why it's wrong here
Project Assurance roles are assigned, but not necessarily appointed as individuals in SU.
- ✓
Executive
Why this is correct
The Executive is appointed in SU as the key decision-maker.
- ✗
Senior User
Why it's wrong here
The Senior User is appointed as part of the Project Board, but this may occur during SU or early IP.
- ✓
Project Manager
Why this is correct
The Project Manager is appointed in SU to lead the initiation.
- ✗
Team Manager
Why it's wrong here
Team Managers are appointed later, during stage execution.
Go deeper
Related to this question
About these practice questions
This PRINCE2F question is part of Courseiva's 1,599-question bank — original exam-style content with full explanations and wrong-answer analysis, never real exam questions or exam dumps. Learn why practice questions differ from exam dumps →
JA
Written by Johnson Ajibi, MSc IT Security
Senior Network & Security Engineer · founder of Courseiva
This PRINCE2F practice question is part of Courseiva's free PeopleCert certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PRINCE2F exam.