PRINCE2F PRINCE2 Practices Practice Question
Who is responsible for project assurance in PRINCE2?
Answer choices
Why each option matters
Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.
Correct answer & explanation
✓
Project Board
Project Assurance is the Project Board's responsibility, but it can be delegated to individuals or teams independent of the Project Manager.
Answer analysis
Option-by-option breakdown
For each option: why learners choose it and why it is or isn't the right answer here.
- ✗
Senior Supplier
Why it's wrong here
Senior Supplier is a role on the Project Board but does not solely handle assurance.
- ✓
Project Board
Why this is correct
The Project Board is ultimately responsible for project assurance.
- ✗
Project Support
Why it's wrong here
Project Support provides administrative services, not assurance.
- ✗
Project Manager
Why it's wrong here
Project Manager is responsible for day-to-day management, not assurance.
Go deeper
Related to this question
About these practice questions
Courseiva writes every PRINCE2F question from scratch — 1,599 in total, each with an explanation and a wrong-answer breakdown. None are copied from real exams or dumps. Learn why practice questions differ from exam dumps →
JA
Written by Johnson Ajibi, MSc IT Security
Senior Network & Security Engineer · founder of Courseiva
This PRINCE2F practice question is part of Courseiva's free PeopleCert certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PRINCE2F exam.