Who is responsible for project assurance in PRINCE2?

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

✓

Project Board

Project Assurance is the Project Board's responsibility, but it can be delegated to individuals or teams independent of the Project Manager.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • ✗

    Senior Supplier

    Why it's wrong here

    The Senior Supplier represents those providing resources and expertise, ensuring supplier deliverables meet requirements; it holds no assurance remit. Project assurance is delegated by the Project Board to assure the project against its business case, plans and standards. Senior Supplier would be correct when answering who represents supplier interests on the board.

  • ✓

    Project Board

    Why this is correct

    The Project Board owns project assurance, monitoring the project across business, user and supplier interests to confirm it remains viable and controlled. It is a board accountability, not delegated to the Project Manager, who handles day-to-day management, or to assurance roles.

  • ✗

    Project Support

    Why it's wrong here

    Project Support provides administrative services such as maintaining the project's documentation, configuration records and change logs; it has no assurance authority. Assurance is delegated by the Project Board, independent of the Project Manager. Project Support would be correct if the question asked who administers the project filing and configuration management systems.

  • ✗

    Project Manager

    Why it's wrong here

    The Project Manager runs the project day to day within the tolerances set by the Project Board, so cannot independently assure their own work. Assurance must sit outside that line of authority. Project Manager would be the correct answer if the question asked who is accountable for delivering the project's products on a daily basis.

About these practice questions

Courseiva writes every PRINCE2F question from scratch — 1,189 in total, each with an explanation and a wrong-answer breakdown. None are copied from real exams or dumps. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

This PRINCE2F practice question is part of Courseiva's free PeopleCert certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PRINCE2F exam.