PRINCE2F People: organizations, teams, and leadership Practice Question
Which TWO statements about the Project Board are true?
Answer choices
Why each option matters
Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.
Correct answer & explanation
✓
It provides direction and decisions to the Project Manager.
The Project Board is accountable for the project's success, meets exception-driven, and comprises SRO, Senior User, and Senior Supplier. It does not meet regularly; it meets when exceptions occur or at stage boundaries.
Answer analysis
Option-by-option breakdown
For each option: why learners choose it and why it is or isn't the right answer here.
- ✓
It provides direction and decisions to the Project Manager.
Why this is correct
The Project Board directs the PM and makes key decisions.
- ✓
It is accountable for the success of the project.
Why this is correct
The Project Board is ultimately accountable.
- ✗
It is responsible for day-to-day management of the project.
Why it's wrong here
Day-to-day management is the PM's role.
- ✗
It meets on a regular basis (e.g., weekly).
Why it's wrong here
It meets exception-driven, not regularly.
- ✗
It includes the Project Manager as a member.
Why it's wrong here
The PM is not a member of the Project Board.
Go deeper
Related to this question
About these practice questions
Courseiva writes every PRINCE2F question from scratch — 1,599 in total, each with an explanation and a wrong-answer breakdown. None are copied from real exams or dumps. Learn why practice questions differ from exam dumps →
JA
Written by Johnson Ajibi, MSc IT Security
Senior Network & Security Engineer · founder of Courseiva
This PRINCE2F practice question is part of Courseiva's free PeopleCert certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PRINCE2F exam.