During a stage, a Team Manager identifies a quality problem with a product. This is reported as an Off-specification. According to PRINCE2, what is the first action the Project Manager should take?

⚠ Common exam trap

PeopleCert often tests the misconception that immediate corrective action (like rework or escalation) is the first step, when PRINCE2 mandates formal logging and impact assessment first to maintain control and auditability.

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

Log the Off-specification in the Issue Register and assess its impact

According to PRINCE2, when an Off-specification is identified, the Project Manager must first log it in the Issue Register and assess its impact. This ensures that all issues are formally recorded and evaluated before any corrective action is taken, maintaining control over project baselines.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • Log the Off-specification in the Issue Register and assess its impact

    Why this is correct

    This is the correct first step per PRINCE2's issue management procedure.

  • Reject the product and ask the Team Manager to rework it immediately

    Why it's wrong here

    The PM must first formally log and assess the issue.

  • Request a change to the product's quality criteria

    Why it's wrong here

    Changing quality criteria is a separate process and not the first step.

  • Escalate the issue to the Project Board via an Exception Report

    Why it's wrong here

    Escalation only occurs if the impact cannot be resolved within stage tolerances.

About these practice questions

One of 1,599 original PRINCE2F practice questions on Courseiva, each with a full explanation and wrong-answer analysis — not exam dumps or protected exam content. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

This PRINCE2F practice question is part of Courseiva's free PeopleCert certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PRINCE2F exam.