Courseiva
PRINCE2 Processes →easyMultiple Choice

PRINCE2F PRINCE2 Processes Practice Question

Which role produces Highlight Reports?

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

✓

Project Manager

Highlight Reports are produced by the Project Manager and sent to the Project Board during Controlling a Stage.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • ✗

    Executive

    Why it's wrong here

    The Executive owns the business case and chairs the Project Board, receiving Highlight Reports rather than authoring them. Producing them is the Project Manager's responsibility. The Executive role is tempting because it is accountable for project success, but accountability for outcomes differs from the operational task of compiling the report.

  • ✓

    Project Manager

    Why this is correct

    The Project Manager produces Highlight Reports to keep the Project Board informed of stage progress, status, issues and risks at agreed intervals. This satisfies the stem's requirement, since the Project Manager owns stage-level monitoring and control reporting.

  • ✗

    Team Manager

    Why it's wrong here

    The Team Manager produces Checkpoint Reports covering team-level progress, not Highlight Reports. Highlight Reports are the Project Manager's periodic summary to the Project Board. The Team Manager role is tempting because it also reports progress, but its reporting line runs upward to the Project Manager, not the Board.

  • ✗

    Project Support

    Why it's wrong here

    Project Support provides administrative assistance such as maintaining logs and configuration records, not the periodic progress summary sent to the Project Board. Highlight Reports are authored by the Project Manager. Project Support is tempting because it handles documentation, but producing management reports for the Board sits outside its remit.

About these practice questions

One of 1,189 original PRINCE2F practice questions on Courseiva, each with a full explanation and wrong-answer analysis — not exam dumps or protected exam content. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

This PRINCE2F practice question is part of Courseiva's free PeopleCert certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PRINCE2F exam.